Brownfield & Retired Power Plant Sites in Nevada

27 catalogued brownfield and retired-generation sites in Nevada, listed by former capacity. Each carries an existing utility-scale grid interconnection that a new datacenter load may be able to re-use.

At a glance

Nevada has 27 brownfield and retired-generation sites in GridCensus: 24 retired power plants from EIA-860 and 3 EPA-tracked contaminated or reuse sites. Together they record 6,102 MW of existing or former generating capacity, 16th among 50 states and DC. The largest by capacity is Mohave at 1,636.2 MW.

What kinds of former sites are in Nevada?

By former use, the list includes 10 geothermal, 6 oil, 5 natural gas, 3 coal, 2 RCRA hazardous-waste, 1 power plant. Recorded retirement dates run from December 1992 to May 2024, with 7 retirements in 2015 or later. 17 of 26 sites with a measured distance sit within 2 miles of a transmission substation.

How does Nevada compare with other states?

Nevada ranks 26th of 50 states and DC by number of brownfield and retired-generation sites, out of 2,085 nationally. By recorded capacity (6,102 MW) it ranks 16th, against 289,280 MW across all states. The state also has 1,809 scored datacenter candidate sites, 18 of them classed as brownfield sites, averaging 48.5 on the 0–100 DC Readiness scale.

Where in Nevada are these sites?

All brownfield and retired plant sites in Nevada

SiteFormer useCapacityRetiredCounty
Mohavecoal1,636 MW2012-07-01Clark
Ely Energy Centercoal1,500 MW—White Pine
Moapa Paiute Energy Centergas1,210 MW—Clark
Reid Gardnercoal637 MW2017-03-01Clark
Reid Gardner Power Stationpower_plant220 MW——
Clark (NVE)gas190 MW2005-09-01Clark
TS Power Plantoil168 MW—Eureka
Sunrisegas167 MW2011-12-01Clark
Tracygas150 MW2014-12-01Storey
Galena 3 Geothermal Power Plantgeothermal30 MW2018-01-01Washoe
Bradygeothermal26 MW2018-03-01Churchill
Steamboat Hills LPgeothermal22 MW2020-04-01Washoe
Stillwater Facilitygeothermal21 MW2009-01-01Churchill
Beowawegeothermal21 MW2024-05-01Lander
Nellis AFB Solar Array II Generating Stationrcra15 MW——
Winnemuccagas15 MW2011-01-01Humboldt
Nellis AFB Solar Facility Site Ircra13 MW——
McGinness Hillsgeothermal12 MW2023-08-01Lander
Desert Peak Power Plantgeothermal11 MW2006-05-01Lyon
Steamboat 1geothermal8 MW2009-12-01Washoe
Battle Mountainoil8 MW2011-01-01Lander
Valley Roadoil6 MW2011-01-01Washoe
Gabbsoil5 MW2013-01-01Nye
Empiregeothermal5 MW2011-12-01Washoe
Steamboat 1A Power Plantgeothermal2 MW2018-12-01Washoe
Fallonoil2 MW1998-12-01Churchill
Lahontanoil2 MW1992-12-01Churchill

Frequently asked questions

How many retired power plants are in Nevada?

GridCensus lists 24 retired power plant sites in Nevada from EIA-860 retirement records. 21 have a recorded retirement date, 7 of them in 2015 or later.

What is the largest retired power plant or brownfield site in Nevada?

Mohave in Laughlin is the largest by recorded capacity, at 1,636.2 MW. It is followed by Ely Energy Center (1,500 MW) and Moapa Paiute Energy Center (1,210 MW).

Which power plant in Nevada retired most recently?

Beowawe has the latest recorded retirement date in the state, May 2024, with 20.6 MW of capacity.

Which county in Nevada has the most brownfield and retired plant sites?

Washoe County has the most, with 6, followed by Clark County with 5.

How many EPA brownfield sites in Nevada have completed cleanup?

3 of the 3 EPA-tracked sites listed for Nevada are recorded as cleanup complete.

Looking for a specific record? The directory lists every brownfield site, A to Z.

More on Nevada, and states with similar counts

About this data

Source: EIA-860 retired generating units and EPA RE-Powering America's Land contaminated-site records, as published March 6, 2026. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Brownfield and retired power plant sites in Nevada”, https://gridcensus.com/brownfield-sites/nevada (data as of March 6, 2026).

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

Every site and score for brownfield sites in Nevada is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.