Skip to content
Gridcensus

Planned transmission upgrades

9,999 transmission projects still to come — new lines, new and expanded substations, transformers and rebuilds — compiled from the seven grid operators' own published plans. Where a plan prices its projects, the open work adds up to about $113.2B. Upgrades near a site show up on the vet and in the site screen of the API. As of 2026-10-20.

By grid operator

OperatorProjectsPricedCostMappedSource
PJM5,7805,449$76.6B39%Every open RTEP upgrade (baseline, supplemental, network) from PJM's project-status feed. source
ERCOT1,7680—91%Future and planned projects from ERCOT's TPIT report. The public file carries no per-project cost; located by substation or county. source
SPP1,123965$24.2B16%Projects with a notification to construct, from SPP's quarterly project tracking report. source
MISO666658$12.1B37%New projects in the MTEP25 cycle only. MISO keeps the full approved-project status list behind its member portal. source
NYISO4160—61%Proposed transmission facilities, Gold Book 2026 Table VII. No cost published. source
CAISO2000—21%Approved transmission-plan projects still to energize, from the July 2025 Transmission Development Forum workbook (the newest posted). source
ISO-NE4613$281M20%Open projects on the Regional System Plan project list; costs are pool-supported (PTF) estimates. source

“Mapped” = placed on the map at a substation the plan names (or, for ERCOT, the county). Unmapped projects still list by state below and in the API.

Largest priced projects

ProjectOwnerStatekVCostIn serviceStatus
Construct a new bipolar +/- 525 kV HVDC link connecting Heritage and Mosby substations, where the link has a capability of transmitting 3,000 MW. The HVDC link, approximately 185 miles in length, will
DominionVA500$2.3B2032-06engineering & procurement
Crossroads - Bandit 765 kV Ckt 1 New Line
SPSNM765$2.1B2031-05delay - mitigation
Crawfish Draw - Bandit 765 kV Ckt 1 New Line
SPSTX765$1.4B—ntc-c project estimate window
Cargas 500 kV station will be cut into the Perryville to Sterlington 500 kV lines 1 and 2 and Perryville to Baxter Wilson 500 kV line.
ENTERGY SERVICES, LLC.LA500$1.2B2026-12m2 - appendix a approved
Construct a new ~145-mile 500 kV line from Babel to Webre 500 kV line.
ENTERGY SERVICES, LLC.LA500$1.1B2030-06m1 - proposed
Tecovas - Crossroads 765 kV Ckt 1 New Line
SPSNM765$937M2031-05delay - mitigation
Southwest Shreveport - Seminole 765 kV Ckt 1 New Line (AEP)
AEPLA765$911M—ntc-c project estimate window
Southwest Shreveport - Seminole 765 kV Ckt 1 New Line (OGE)
OGELA765$911M—ntc-c project estimate window
Design and construct a new Voltage Source Converter (VSC) HVDC station at Heritage substation to support the new HVDC link.
DominionVA500$774M2032-06engineering & procurement
Design and construct a new Voltage Source Converter (VSC) HVDC station at Mosby substation to support the new HVDC link.
DominionVA500$745M2032-06engineering & procurement
Construct a new 175 miles Amos to Welton Spring 765 kV line. (APS/FE Section of the line is 145 miles)
APSWV765$725M2031-05engineering & procurement
New 500 kV line from existing 502 Junction substation to the demarcation point between FE/NEET around Gore substation (bypass Black Oak) (NEET Portion).
NEETVA500$720M2031-12engineering & procurement
Wyoming Border - St. Germaine 345 kV Ckt 1 New Line (BEPC)
BEPCWY345$597M2034-10on schedule < 4
Construct a new single-circuit 765 kV transmission line between Kammer and proposed Buttermilk Falls substations (APS Zone). The total length of the line is 114 miles.
NEET—765$571M2031-06engineering & procurement
Build a new 115 mile 765kV line from Joshua Falls – Yeat. (Roughly 114 miles in Dominion section).
DominionVA765$561M2031-01engineering & procurement
Construct a new single-circuit 765 kV transmission line between proposed Buttermilk Falls and proposed Mountain Stone substations (PENELEC Zone). The total length of the line is 108 miles.
NEET—765$541M2031-06engineering & procurement
Holcomb - Sidney 345 kV Ckt 1 New Line (SEPC)
SEPCKS345$541M2030-10delay - mitigation
Construct new 765 kV transmission line from the existing ComEd Collins 765 kV substation to an interconnection point with MISO near the Illinois/Wisconsin state border.
ComEdIL765$522M2034-06engineering & procurement
Rebuild ~73.9 miles of the existing Tanners Creek-Junction Tower 345kV line asset as 345 kV single circuit utilizing 2-bundle 954 ACSR 54/7 Cardinal conductor. Rebuild ~5.65 miles of the existing Hann
AEPIN345$520M2031-10engineering & procurement
Holcomb - Sidney 345 kV Ckt 1 New Line (TSGT)
TSGTKS345$515M2030-12delay - mitigation
Entergy is proposing to construct • Sarepta 500 kV station including a Sarepta 500-345 kV Autotransformer • New ~60 mile Mt Olive to Sarepta 500 kV line. • Upgrade existing Mt Olive 500-230 kV Autotra
ENTERGY SERVICES, LLC.LA500$470M2028-12m2 - appendix a approved
Ft. Smith - Thistle 345 kV CKT 1
TBDAR345$461M—identified
Rebuild ~68.1 miles of double circuit 345kV on centerline. Costs include transmission line removal, OPGW, and Right of Way.
AEPIN345,765$453M2031-05engineering & procurement
Rebuild the Piney – Grandview – Titusville – Union City – Erie South 115 kV line using double circuit 115 kV construction adjacent to the existing 115 kV corridor (~82 miles). Energize the line in a
PENELECPA115$443M2034-06engineering & procurement
- Construct new 345/138 kV Mill Road SS, with one 500 MVA 345/138 kV transformer, - Loop in Granville – Arcadian 345 kV line and Cypress – Arcadian 345 kV line to new Mill Road 345 SS, Rebuild Mill Ro
AMERICAN TRANSMISSION COMPANYWI345$424M2027-10m2 - appendix a approved
Belfield 2 - Fox Ridge 345 kV Ckt 1 New Line
BEPCND345$413M2034-10delay - mitigation
Port Covington 115/13 kV Project
BGEMD115$407M2028-11engineering & procurement
Build new North Delta-High Ridge 500 kV line. (~59 miles).
BGEMD500$407M2030-12engineering & procurement
Build a 500kV line from a new substation called Thornburg (formerly Kraken) to Bristers using 5/2 structures. New conductor to have a minimum summer normal rating of 4357MVA.
DominionVA500$385M2030-09engineering & procurement
Anthem 765 kV New Substation
AEPOK765$377M—ntc-c project estimate window

Next 345 kV+ projects to energize

ProjectOwnerStatekVCostIn serviceStatus

By state

Texas2,034 projects · $4.3B priced · 610 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Crawfish Draw - Bandit 765 kV Ckt 1 New Line
SPS765$1.4B—ntc-c project estimate window
Beckham County - Potter 345 kV Ckt 1 New Line (SPS)
SPS345$195M2029-10on schedule < 4
Potter County 345 kV Substation Expansion #1
SPS345$178M2031-05delay - mitigation
New 765 kV Substation at Tecovas
SPS765$156M2031-05delay - mitigation
Construct a new War Eagle 138 kV substation approximately 0.3 miles north of the Oak Ridge 138 kV substation that cuts into the Oak Ridge – Metro 138 kV.
ENTERGY SERVICES, LLC.138$110M2029-06m1 - proposed
Build a new 138 kV switching station between College Station and Grimes 138 kV substations called Runny.
ENTERGY SERVICES, LLC.138$99.4M2030-06m1 - proposed
Crawfish Draw 345/765 kV Ckt 3 Transformer
SPS345$75.9M—ntc-c project estimate window
Crawfish Draw 345/765 kV Ckt 2 Transformer
SPS345$75.9M—ntc-c project estimate window
Crawfish Draw 345/765 kV Ckt 1 Transformer
SPS345$75.9M—ntc-c project estimate window
Tecovas 765/345 kV Transformer Ckt 1 (345 kV)
SPS765$73.7M2031-05delay - mitigation
Rebuild Dobbin - Tubular 138 kV line
ENTERGY SERVICES, LLC.138$65.0M2031-06m1 - proposed
Tecovas 765/345 kV Transformer Ckt 2 (345 kV)
SPS765$62.2M2031-05delay - mitigation
Tecovas 765/345 kV Transformer Ckt 3 (345 kV)
SPS765$62.2M2031-05delay - mitigation
Crawfish Draw 765 kV New Substation
SPS765$53.6M—ntc-c project estimate window
Crawfish Draw 765 kV Line Reactor
SPS765$49.5M—ntc-c project estimate window
Diana East 345 kV STATCOM Ckt 1
AEP345$47.0M—ntc-c project estimate window
Diana East 345 kV STATCOM Ckt 2
AEP345$47.0M—ntc-c project estimate window
Tecovas - Potter County 345 kV Ckt 2 New Line
SPS345$41.6M2031-05delay - mitigation
Tecovas - Potter County 345 kV Ckt 1 New Line
SPS345$41.6M2031-05delay - mitigation
Tecovas - Potter County 345 kV Ckt 3 New Line
SPS345$40.5M2031-05delay - mitigation
Big Sandy - Mt. Eara Ckt 1 138 kV Voltage Conversion
ETEC138$39.9M—delay - mitigation
Sawmill - Turnertown 69 kV Ckt 1 New Line
ETEC69$38.5M—delay - mitigation
Tecovas 765 kV Reactor 1
SPS765$36.0M2031-05delay - mitigation
Address aging and failing equipment such as structures, breakers, relay panels, RTU's, arresters, circuit switchers, etc
ENTERGY SERVICES, LLC.500$34.4M2026-12m1 - proposed
Gilmer - Pittsburg (Cox Tap) 138 kV Ckt 1 Voltage Conversion
ETEC138$29.3M—delay - mitigation
Ohio1,338 projects · $11.0B priced · 243 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Sammis – Star 345 kV Line: Rebuild the existing Sammis – Star 345 kV line (approximately 68.6 miles) At Sammis and Star substations: Replace line relaying
ATSI345$344M2031-05engineering & procurement
Greentown-Melissa 765 kV line: Construct a 49.92-mile 765 kV AC overhead transmission line between the existing Greentown 765 kV substation and the proposed Melissa 765 kV substation (DAYTON Portion).
Dayton765$231M2031-10engineering & procurement
Thistlewood (formerly Melissa) 765/345 kV substation scope: Construct a new 765/345 kV greenfield substation interconnecting the new 765 kV Marysville line and the new 765 kV Greentown line with three
ATSI765$223M2030-10engineering & procurement
Construct an ~ 25-mile 345 kV double circuit line from Atlanta substation to Fayette substation. The line is projected to be built with 2-1024.5 ACAR conductor and strung with OPGW for communications.
Dayton345$221M2029-04engineering & procurement
Construct an ~ 27-mile 345 kV single circuit from Clinton substation to Fayette substation. These lines will be built with 2-1024.5 ACAR conductor and strung with OPGW for communications.
Dayton345$187M2030-01engineering & procurement
Marysville 765 kV substation: Add one 765 kV STATCOM.
AEP765$164M2030-06engineering & procurement
Conesville-Bixby 345kV Line ( Bixby-Ohio Central & Ohio Central-Conesville Circuits ): Rebuild ~46.1 miles of the ~51.1 miles of line using 954 kCM ACSR bundled conductor & install OPGW fiber on new l
AEP345$155M2032-12engineering & procurement
Rebuild from Howard to Ohio Central as 138kV double-circuit (64 miles), using 795 ACSR conductor. Note that the approx. 0.5 mile 138kV line segments outside Ohio Central station will not be rebuilt,
AEP138$142M2030-10engineering & procurement
Construct greenfield 345kV ring bus switching station, comprising of six (6) 345kV 63kA 5000A breakers and a 150 MVAR STATCOM
AEP345$132M2027-12engineering & procurement
Rebuild the Greenfield - Beaver 138 kV corridor (32 miles) with 795 kcmil 26/7 ACSS. This corridor encompasses multiple 138 kV lines that are constructed on common towers.
ATSI138$131M2029-05engineering & procurement
Melissa-Marysville 765 kV: Construct a 35.4-mile 765 kV AC overhead transmission line between the proposed 765 kV Melissa substation and the existing 765 kV Marysville substation (AEP Portion).
AEP765$131M2030-10engineering & procurement
Rebuild the 35-miles of the South Point- Portsmouth double circuit 138 kV line between Millbrook Park – South Point; with 795 ACSR (257MVA) or equivalent conductor.
AEP138$128M2030-10engineering & procurement
Greentown-Melissa 765 kV line: Construct a 27.08-mile 765 kV AC overhead transmission line between the existing Greentown 765 kV substation and the proposed Melissa 765 kV substation (ATSI Portion).
ATSI765$125M2031-10engineering & procurement
Rebuild ~19.0 miles of Hyatt - Marysville 345 kV line using 4-bundled 795 ACSR conductor Bold construction (This is an EOL rebuild)
AEP345$117M2027-06engineering & procurement
Marysville 765 kV substation scope: Create a new 765 kV line position. Install two 765 kV circuit breakers. Create a new 765 kV line position to relocate the existing 765 kV Sorenson line. Install one
AEP765$112M2030-06engineering & procurement
Ayersville- Sand Ridge 69 kV Line - Conversion from 34.5 kV - Ayersville Substation: Install one (1) new 69 kV breaker. Install one (1) new 138 – 69 kV transformer. Install four (4) new 138 kV breaker
ATSI69$110M2027-05under construction
Phase I: Medina-Medina Industries-Seville 69 kV Line Upgrade Project -Build a new ~7.5 miles 69 kV line with new conductor to extend the Medina industries 69 kV line from/at Carlisle Brake & Friction
ATSI69$97.8M2028-12engineering & procurement
Wooster – South Coshocton: The 37.7-mile line will be rebuilt using 795 ACSR DRAKE to alleviate identified asset renewal conditions. This includes the 15.2-mile West Millersburg – Wooster 138kV circui
AEP138$96.5M2026-10engineering & procurement
Fostoria - East Lima 138: The 41.3 mile long line will be rebuilt using double circuit 795 ACSR Drake conductor. OPGW shield wire will be installed. Approximately one mile of line is being considered
AEP138$95.9M2026-11engineering & procurement
Rebuild 29.02 miles of the 138kV Lick-Addison line
AEP138$95.7M2032-10engineering & procurement
Rebuild ~0.95-mile section from structure #9 to structure #17 of the line asset as double circuit with 556 ACSR. Additionally, rebuild 18.5-mile section from structure #17 to Hammondsville as single c
AEP69,138$82.7M2029-03engineering & procurement
Construct double circuit 138 kV lines (~ 12 miles) from Dawson to Clinton with 795 ACSR conductor; utilize existing lines that are built for future 138 kV expansion for part of the new double circuit.
ATSI138$80.0M2031-06On Hold
Reconfigure Maliszewski 765 kV station from 2 breakers to a 6 breaker ring bus. Install a new 765/345 kV transformer. Establish new 345 kV breaker yard with 3 string breaker and a half to include a li
AEP765$79.7M2029-06engineering & procurement
Galion – Roberts North 138 kV Line and Galion – Roberts South 138 kV Line: Rebuild the double circuit Galion – Roberts North 138 kV Line and Galion – Roberts South 138 kV Line on shared structures. G
ATSI138$77.5M2026-11under construction
Vassell – Green Chapel 345 kV line: Install approximately 12.5-mile long 345 kV transmission between Vassell and Green Chapel stations to mitigate overloading on multiple transmission facilities inclu
AEP345$75.0M2026-04engineering & procurement
Virginia1,015 projects · $23.4B priced · 204 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Construct a new bipolar +/- 525 kV HVDC link connecting Heritage and Mosby substations, where the link has a capability of transmitting 3,000 MW. The HVDC link, approximately 185 miles in length, will
Dominion500$2.3B2032-06engineering & procurement
Design and construct a new Voltage Source Converter (VSC) HVDC station at Heritage substation to support the new HVDC link.
Dominion500$774M2032-06engineering & procurement
Design and construct a new Voltage Source Converter (VSC) HVDC station at Mosby substation to support the new HVDC link.
Dominion500$745M2032-06engineering & procurement
New 500 kV line from existing 502 Junction substation to the demarcation point between FE/NEET around Gore substation (bypass Black Oak) (NEET Portion).
NEET500$720M2031-12engineering & procurement
Build a new 115 mile 765kV line from Joshua Falls – Yeat. (Roughly 114 miles in Dominion section).
Dominion765$561M2031-01engineering & procurement
Build a 500kV line from a new substation called Thornburg (formerly Kraken) to Bristers using 5/2 structures. New conductor to have a minimum summer normal rating of 4357MVA.
Dominion500$385M2030-09engineering & procurement
Install one 500/230kV 1440MVA transformer at a new substation called Wishing Star. Cut and extend 500 kV Line #546 (Brambleton-Mosby) and 500 kV Line #590 (Brambleton-Mosby) to the proposed Wishing St
Dominion500$342M2026-06under construction
Install (2) 1400 MVA 500-230 kV transformers and associated 500 kV and 230 kV equipment (breakers, switches, leads) at Vint Hill Substation to supply the area with a 500 kV source Cut and loop 500 kV
Dominion230$307M2029-06engineering & procurement
Proposed Solution - Phase1 (01/2028): Rebuild approximately 6.5 miles of the existing 230kV Line #2090 between Summit DP and Fredericksburg Sub with double-circuit structures using a higher capacity
Dominion500,230$300M2029-07engineering & procurement
Construct a new 24.5-mile 230 kV line 9482 from Cloverhill substation to Ox substation.
Dominion230$288M2029-04engineering & procurement
Build new 230 kV Harpers Road switching station to terminate nine offshore wind export cables for AF1-123/124/125 and consolidate to three overhead 230 kV transmission lines to go to Fentress Substati
Dominion230$275M2025-12under construction
Install a breaker and a half scheme with a minimum of eight 230 kV breakers for five existing lines at Idylwood 230 kV
Dominion230$230M2017-06under construction
Rebuild approximately 37.4 miles of 500 kV line No. 563 from Carson-Midlothian. The proposed structures to be installed are mainly 500/230 kV double-circuit V-string suspension towers. The 230 kV circ
Dominion500$228M2032-06engineering & procurement
Build a new 500kV Line from Mars-Golden on 500/230kV double circuit structures with substation upgrades at Golden and Mars. New conductor to have a monimum summer normal rating of 4357 MVA.
Dominion500$228M2028-06engineering & procurement
Construct a 230kV UG line approx. 4.5 miles from Idylwood to Tysons. Tysons Substation will be rebuilt, within its existing footprint, with a 6-breaker ring bus using GIS equipment.
Dominion230$228M2026-11under construction
Relocate the Joshua Falls 765 kV substation. Install (5) 765 kV breakers and relocate Joshua Falls 765/138 kV transformer to the new site. Terminate the 765 kV Cloverdale line and the 765 kV Yeat lin
AEP765$226M2029-06engineering & procurement
* Obtain land and build a new 500/230kV Finneywood switching station at the intersection of 500kV Line #556 (Clover-Rawlings) and 230kV Line #235 (Cloud – Farmville). * Cut and terminate 500kV Line #
Dominion500$220M2026-12under construction
Rebuild approximately 27.7 miles of 500 kV transmission line from Elmont to Chickahominy with current 500 kV standards construction practices to achieve a summer rating of 4330 MVA. Latest TEAC change
Dominion500$214M2026-06engineering & procurement
Rebuild 230 kV Line #2027: Midlothian-Bremo to current 230 kV standards to achieve a minimum normal summer rating of 1573 MVA. Upgrade substation equipment to 4000 A. Double-circuit 230 kV structures
Dominion500,230$212M2031-12engineering & procurement
Convert the OH portion (approx. 1500 Feet) of 230 kV Lines #248 & #2023 to UG and convert Glebe substation to GIS.
Dominion230$211M2027-09under construction
Rebuild approximately 33.09 miles of 500 kV line #579 from structure 579/1 inside Septa substation to structure 579/193 inside Yadkin substation.
Dominion500$191M2028-12engineering & procurement
Build a new 765/500KV substation called Yeat. Install (2) 765/500 kV transformers. Cut in 500kV line Spotsylvania – Morrisville into Yeat.
Dominion765$187M2031-01engineering & procurement
Build a 500kV line from North Anna substation (bypassing Ladysmith Substation) to a new substation called Thornburg (formerly Kraken) using 5/2 structures. New conductor to have a minimum summer norma
Dominion500$187M2030-09engineering & procurement
Build a new 500kV line from Aspen - Golden on 500/230kV double circuit structures with substation upgrades at Aspen and Golden. New conductor to have a minimum summer normal rating of 4357MVA.
Dominion500$176M2028-06engineering & procurement
Rebuild 500kV Line #569 Loudoun - Morrisville to accommodate the new 500 kV line in the existing right-of-way. New conductor to have a summer rating of 4357 MVA.
Dominion500$176M2030-06engineering & procurement
Pennsylvania991 projects · $9.9B priced · 152 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Rebuild the Piney – Grandview – Titusville – Union City – Erie South 115 kV line using double circuit 115 kV construction adjacent to the existing 115 kV corridor (~82 miles). Energize the line in a
PENELEC115$443M2034-06engineering & procurement
Rebuild Seward-Glory-Piney 115 kV line: rebuild ~66 miles of 115 kV line using double circuit 230 kV construction, install 1033 ACSR conductor (six-wired) energized at 115 kV.
PENELEC115$200M2028-12engineering & procurement
Build New North Delta 500 kV substation (four bay breaker and half configuration ) - the substation will include 12 - 500kV breakers and one 500/230 kV transformer, will allow the termination of six -
Transource500$164M2027-10under construction
Rebuild aging double circuit 138 kV tower line between Brunot Island and Crescent substations with 138 kV tower line.
DL138$160M2027-06under construction
Forest - Glade 230 kV Line Rebuild approximately 34.1 miles of 230 kV line from Forest Substation to structure 288 Glade Substation Replace the 1033 ACSR bus conductor Transmission Line Ratings: F
PENELEC230$157M2029-05engineering & procurement
Install a new 500-138kV substation with a four bay BAAH 500kV yard, four 500-138kV XFMRs, six bay BAAH 138kV yard, and one 138kV capacitor bank.
PPL500$148M2028-11engineering & procurement
Rebuild and reconductor approximately 33.0 miles of the Armstrong – Homer City 345 kV Line, of wood pole construction
PENELEC345$138M2031-12engineering & procurement
Rebuild the 38.0 miles of Corten tower sections of the Siegfried-Harwood & Harwood-East Palmerton/Siegfried-East Palmerton 230kV lines with steel monopoles and new conductor.
PPL230$137M2026-09under construction
Tap the Vinco - Hunterstown 500 kV line & create new Rice 500 kV & 230 kV stations. Install two 500/230 kV transformers, operated together.
Transource500$125M2029-01engineering & procurement
Rebuild the existing JUNI-TMIS 500kV line to double circuit for 13.3 miles from Juniata substation to Bernheisel substation. PPL’s standard is to have three sources into a BES substation.
PPL500$117M2027-12engineering & procurement
Rebuild the existing Sunbury - Eldred 230kV Line to double circuit 230kV from Sunbury to Eldred (24.8 miles)
PPL500,230$113M2028-05engineering & procurement
Peach Bottom North upgrades – substation work Add 3x 500 kV breakers to form a breaker-and-a-half bay.
PECO500$108M2028-10under construction
Rebuild the Sunbury – Lock Haven 69kV line (~39 miles) to double circuit 69kV operation with 795 ACSR conductor. Install new line terminals at Sunbury and Lock Haven substations to accommodate the new
PPL69$103M2027-12engineering & procurement
Install new 500/230kV substation on of Y2-015
PPL500$103M2017-07Active
Rebuild the 25.9-mile Corten tower section of the Frackville-Columbia 230kV line with steel monopoles and new conductor.
PPL230$91.9M2029-01engineering & procurement
Rebuild the existing JUNI-ALBU 500kV line to double circuit for 9.6 miles from Juniata substation to New Buffalo substation.
PPL500$83.0M2028-05engineering & procurement
Construct new 230/13kv substation in a Ring configuration. Install two 230kV–13kV 62MVA Distribution Transformers to support new distribution load in the area.
PECO230$82.0M2031-10engineering & procurement
Extend a double circuit 230kV (built for 500kV) for ~9 miles from Nescopeck to Tomhicken on existing PPL ROW. Extend single circuit 230kV (built for 500kV DlbCir) for 2.7 miles from Tomhicken to Harwo
PPL230$80.5M2028-02engineering & procurement
Extend a double circuit 230kV (built for 500kV) for ~9 miles from Nescopeck to Tomhicken on existing PPL ROW. Extend single circuit 230kV (built for 500kV DlbCir) for 2.7 miles from Tomhicken to Harwo
PPL230$80.5M2027-06engineering & procurement
Construct a new 69 kV transmission line from Shawnee to Walker substations (approximately 31.1 miles)
ME69$75.0M2028-12engineering & procurement
Build new Galloping Hill 230/69 kV sunstation. Cut and loop Springfield Rd. – Aldene 230kV circuit into new 230/69kV station. Install one (1) 230/69kV transformer. Construct a 69/13kV substation. Cut
PSEG230$72.4M2029-12engineering & procurement
Replace the substation conductors with 1590 ACSR. Replace two breakers, 4 switches and associated equipment with 3000amp rated equipment.
PPL230$71.8M2015-07Active
Install a new three bay BAAH 500kV yard with two 500-138kV Transformers and one 144MVAR Capacitor Bank
PPL500$71.0M2028-05engineering & procurement
Rebuild the 21.9 miles of Corten tower sections of the Montour-Susquehanna & Montour-Susquehanna T10 230kV lines with steel monopoles and new conductor.
PPL230$69.6M2029-12engineering & procurement
Reconductor 13.01 miles of line East Towanda to Canyon 230kV line. Replace transmission line drop at East Towanda.
PENELEC230$69.4M2028-06Active
Indiana458 projects · $4.9B priced · 178 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Rebuild ~73.9 miles of the existing Tanners Creek-Junction Tower 345kV line asset as 345 kV single circuit utilizing 2-bundle 954 ACSR 54/7 Cardinal conductor. Rebuild ~5.65 miles of the existing Hann
AEP345$520M2031-10engineering & procurement
Rebuild ~68.1 miles of double circuit 345kV on centerline. Costs include transmission line removal, OPGW, and Right of Way.
AEP345,765$453M2031-05engineering & procurement
a new 345kV ring bus and approx. 12 miles of 345kV line to the west side of Lebanon where WVPA will construct a 345/138kV substation. Approx. 15 miles of 345kV line will be built to network this 345/1
WABASH VALLEY POWER ASSOCIATION, INC.345$345M2029-06m2 - appendix a approved
Greentown-Teddy 765 kV line: Construct a 60-mile 765 kV AC overhead transmission line between the existing Greentown 765 kV substation and the proposed Teddy 765 kV substation (AEP Portion). The tota
AEP765$278M2030-06engineering & procurement
Sorenson - Desoto 345kV: Rebuild the ~51.5 mile line as is using double circuit 345kV construction. Replace jumpers at Sorenson and Desoto to accommodate the new structure entrances at the stations.
AEP345$202M2032-01engineering & procurement
345kV double circuit to new substation
WABASH VALLEY POWER ASSOCIATION, INC.345$99.0M2026-12m2 - appendix a approved
Line rebuild (~32.3mi) to bundled 954ACSS conductor or 4000A equivalent.
DUKE ENERGY INDIANA, LLC345$95.5M2029-06m2 - appendix a approved
New station to be constructed in a breaker and a half configuration consisting of sixteen (16) 345kV 5000A 63kA breakers, six (6) 345kV meters, and station fiber cable. Construct six (6) bus ties from
AEP345$79.5M2026-12engineering & procurement
Approximately 15 miles of 345kV transmission line
WABASH VALLEY POWER ASSOCIATION, INC.345$75.0M2028-12m2 - appendix a approved
Construct a new station in a breaker and a half configuration consisting of sixteen (16) 345kV 5000A 63kA breakers, six (6) 345kV meters, and station fiber cable to serve 550MW of new load. Construct
AEP345$70.4M2026-12engineering & procurement
Rebuild the Bluffton – Hillcrest 69 kV line as the ~26 mile Bluffton to Pleasant circuit as 6-wired 138 kV design structures.
AEP138$67.1M2029-11engineering & procurement
Rebuild ~21 miles of the circuit from Sorenson to north of Columbia. Retire the remaining 44.1 miles of the line.
AEP138$65.7M2032-12engineering & procurement
Expand Allen station with 2x additional 345/138kV transformers. Install 3x 345kV breaker and 3x 138kV breaker for transformer protection. Land purchase for station expansion is included. The transform
AEP345$58.5M2029-06engineering & procurement
Rebuilding 12.39 miles of the Illinois Rd - Gateway 69kV transmission line with steel poles and 556 ACSR conductor.
AEP69,138$53.9M2030-08engineering & procurement
Construct a new station in a breaker and a half configuration consisting of eleven (11) 345kV 5000A 63kA breakers, two (2) 345kV meters, and station fiber cable to serve 437MW of new load. Construct t
AEP345$50.4M2027-03engineering & procurement
Rebuild Allen –R.P. Mone 345kV line (18.6 miles).
AEP345$49.9M2027-06engineering & procurement
New 345/138kV substation with breaker and half at both voltage levels
WABASH VALLEY POWER ASSOCIATION, INC.345$49.5M2026-12m2 - appendix a approved
Line rebuild (~14mi) to bundled 954ACSS conductor or 4000A equivalent.
DUKE ENERGY INDIANA, LLC345$49.0M2029-06m2 - appendix a approved
138kV transmission network to serve customer sites
WABASH VALLEY POWER ASSOCIATION, INC.138$46.2M2026-12m2 - appendix a approved
Greentown 765 kV substation scope (AEP): Create a new 765 kV line position with three 100 MVAR single-phase reactors. Install two 765 kV circuit breakers.
AEP765$45.3M2030-06engineering & procurement
Reactive and thermal project mitigations for LEAP Phase 2 (MTEP 50208) area large load.
WABASH VALLEY POWER ASSOCIATION, INC.345$45.0M2029-06m2 - appendix a approved
Cut into 2x existing double circuit 138kV lines, (4x circuits total) and install 4x double circuit 0.2 mile extension to new Zodiac 138kV station. Rebuild both ~3.7 mile 138kV double circuit lines fro
AEP345,138$44.0M2029-07engineering & procurement
34530 Rebuild - Slugger to LGE Trimble to (2)954ACSS@200C (DEI-owned portion only)
DUKE ENERGY INDIANA, LLC345$43.0M2031-06m1 - proposed
Robison Park – Sowers 138kV line: Rebuild the 13.6 miles of wood construction with double circuit capable 138kV with one side strung. Reconductor 4.3 miles of the steel lattice section with 795 Drake
AEP138$42.3M2028-05engineering & procurement
Install greenfield 138kv breaker and a half station. Zodiac 138kV station will include 8-138kV AEP circuit exits and customer terminations to 5 customer buildings.
AEP138$38.1M2026-03engineering & procurement
New Jersey435 projects · $5.6B priced · 19 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Construct a new 69/13kV station on PSE&G owned adjacent property to Keasbey station. o Build a new 69kV line to Rahway station. o Build a new 69kV line to Blair Rd. o Install one (1) 230/69kV transfor
PSEG230$321M2029-12engineering & procurement
Install a 230kV switching station with one (1) 230/69kV transformer and Cut and loop the Metuchen - Sewaren 230kV line into the new 230kV bus.
PSEG230$271M2028-12under construction
Construct seven new 34.5 kV circuits on existing pole lines (total of 53.5 miles), Rebuild/Reconductor two 34.5 kV circuits (total of 5.5 miles) and install a 2nd 115/34.5 kV transformer (Werner)
JCPL35$223M2027-05engineering & procurement
Construct new 69-13kV substation at PSEG owned property in Elizabeth NJ. o Install two (2) 69/13kV transformers. o Cut and loop Roselle – Elizabeth 69kV line into the new 69kV bus. o Build new 69kV ci
PSEG69$223M2029-06engineering & procurement
Construct a new Constable Hook 69/13kV substation in the Bergen Neck Area to feed Bergen Point load and provide for future load growth.
PSEG69$163M2026-12under construction
Build two new 138 kV feeders from BL England and Merion to the Ocean City substation
AEC138$141M2031-05engineering & procurement
South Plainfield Area Upgrade
PSEG69$122M2027-05under construction
Convert existing Medford 69kV Straight bus to Seven breaker ring bus, , construct a new 230/69kV transformer at Cox's Corner and a new line from Cox's Corner to Medford.
PSEG69$116M2027-12under construction
Build a new Walnut Ave 69 kV Substation. Eliminate Clark substation. Transfer load from nearby heavily loaded Aldene, Warinanco, and Westfield to the new station
PSEG69$112M2027-11under construction
New 69-13kV Station at new property in Fairview N.J.
PSEG13$108M2030-02under construction
Construct a new Central Ave 69/4 kV Station in Western Newark Area
PSEG—$94.9M2026-12under construction
Construct new (Garfield Ave) 69-13-4kV station on existing property
PSEG—$92.6M2028-10under construction
Construct new 69-13kV substation with two transformers in acquired property in Prospect Park. Cut and loop Hinchmans – North Paterson and Hawthorne – Customer Sub 69kV lines into the new 69kV bus
PSEG69$92.4M2028-09under construction
Build 4 miles new 230 kV XLPE circuit using (345 kV rated 5000 kcmil cable) from Jackson Road 230 kV station to Cedar Grove 230 kV station.
PSEG230$82.7M2028-06under construction
Rebuild 69 kV line from Churchtown – Paulsboro substations. All structures, conductor, and static wire will be replaced with new steel poles, conductor, and OPGW.
AEC69$80.0M2029-10engineering & procurement
Construct a 230-13kV Substation at PSEG property adjacent to Meadow Road substation. o Construct a 230kV substation. o Install two (2) 230-13kV transformers. o Resolves contingency overload at Meadow
PSEG230$79.7M2028-11under construction
Rebuild 0725 and 0726 Churchtown – Woodstown 69kV lines using 795 ACSR and replacing the existing shield wire with new OPGW
ACE69$78.4M2030-06engineering & procurement
Construct a new 69-13kV substation in the Harlingen area . Construct new 69-13kV station on new property. Install two (2) 69-13kV transformers. Cut and loop the Bennetts Lane-Montgomery 69kV line into
PSEG69$78.2M2029-12engineering & procurement
Construct a four breaker 230 kV ring bus at Morristown
JCPL35$73.7M2027-06under construction
Install a 500 kV double-breaker double-bus at Montville substation Install a 500/230 kV transformer and 500 kV breaker. Install new breaker string in the 230 kV yard to create a breaker-and-a-half lay
JCPL500,230$72.1M2029-11engineering & procurement
Replace existing 138/26kV transformers 132-1 and 132-2 & add two (2) 138kV transformer head breakers.
PSEG138$71.5M2029-05engineering & procurement
Reconductor the Warinanco - Aldene 230 kV line
PSEG230$65.7M2017-06Active
Cut and loop the 69kV (prior approved) line from Roselle to Galloping Hill into the customer’s new substation. (Station In-Service date 06/2026)
PSEG23,069$63.8M2026-09engineering & procurement
Install a new 230kV substation (Oak Tree Road) with two (2) 230/13kV transformers. Cut and loop the New Dover-Metuchen 230kV line in to the 230kV bus and transfer load from heavily loaded New Dover an
PSEG230$61.7M2027-11under construction
Construct a second 230-69 transformer at the Bennetts Lane substation. Install one (1) 230-69 transformer . Modify 230kV bus at Bennetts Lane . Modify 69kV bus at Bennetts Lane
PSEG230$60.9M2029-12engineering & procurement
New York416 projects · — priced · 82 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Massena: Replacement of Massena Breaker 765 kV
NYPA765—2027-12proposed
735kV (Quebec) – Astoria Annex 345kV: -/+ 400 kV symmetrical monopole, VSC-HVDC
CHPE LLC Hertel400—2026-06proposed
735kV (Quebec) – Astoria Annex 345kV: -/+ 400 kV symmetrical monopole, VSC-HVDC
CHPE LLC Hertel400—2026-06proposed
Cricket Valley – CT State Line: Loop Line into new Dover Substation/2-795 ACSS
New York Transco345—2025-12proposed
Haverstock – Willis:
NYPA345—2025-12proposed
Barrett: LI PPTN: New 345 kV Substation
NYPA/TRANSCO345—2030-06proposed
Astoria Annex – Rainey:
NYPA345—2026-06proposed
Cricket Valley – Dover (New Station): Loop Line into new Dover Substation/2-795 ACSS
New York Transco345—2025-12proposed
Reynolds Rd: 115 kV relaying additions and upgrades
NGRID345—2030-12proposed
Rd (New Station) – Rotterdam: Two Gordon Road 345/115 kV transformers are to come online by Spring 2029; AC Transmission Seg A project
LSP Gordon345—2029-06proposed
Stolle Rd: One (1) 448 MVA 345/230 kV Transformer
NYSEG345—2031-06proposed
Fraser: Transformer #2 and Station Reconfiguration
NYSEG345—2027-12proposed
Oswego: Rebuild of Oswego 345kV Station (asset separation).
NGRID345—2025-12proposed
Bailey: Replace two 345kV switches
NGRID345—2025-12proposed
New Shore Road – Sprain Brook: LI PPTN: Two (2) New 345 kV Circuits (4000kcmil XLPE/1400mm2 Tri-core)
NYPA/TRANSCO345—2030-06proposed
Station (Marshville) Ames – Road Station (Marshville): Construct a new 345kV/115kV station in a breaker and a half configuration
NGRID Ames Road345—2028-06proposed
East Conklin: Replace three 345kV switches
NGRID345—2025-12proposed
Haverstock – Adirondack:
NYPA345—2025-12proposed
Dewitt: 345 kV Breaker Replacement
NGRID345—2025-12proposed
Sprain Brook – Sprain Brook Reconfiguration: LI PPTN: Additional bay(s) installation
ConEd345—2030-06proposed
Stolle Rd: One (1) 448 MVA 345/115 kV Transformer
NYSEG345—2031-06proposed
Watercure:
NYSEG345—2030-06proposed
Austin Road – Edic: SPCP: Austin Road -Edic Circuit-1 345 kV Line.2 – 795 kcmil ACSS 26/7 “Drake”
NGRID345—2026-12proposed
New Ruland Road: LI PPTN: One (1) New Phase Angle Regulator for Y55
NYPA/TRANSCO345—2030-06proposed
Marcy: Marcy Breaker Replacement 345 and 765 kV
NYPA345—2026-06proposed
West Virginia394 projects · $4.2B priced · 50 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Construct a new 175 miles Amos to Welton Spring 765 kV line. (APS/FE Section of the line is 145 miles)
APS765$725M2031-05engineering & procurement
Construct a new 86 miles Welton Spring to Rocky Point 765 kV line (Welton Spring to DVP local area, roughly 50 miles) (WV Portion)
APS765$248M2031-05engineering & procurement
Install four 250 MVAR shunt capacitors, and a +/-500 MVAR STATCOM at Welton Spring 765 kV substation
APS765$194M2031-05engineering & procurement
Rebuild approximately 47.2 miles of the Loughs Lane - Pickens 138 kV Line and install OPGW. At the Durbin Tap: Replace transmission line disconnect switches. At Loughs Lane Substation: Remove wave tr
APS138$183M2032-11engineering & procurement
Rebuild ~15 miles of the Stonewall-Millville 138 kV line with 500 kV overbuild (502 Jct to Woodside 500 kV line section).
APS500$165M2030-06engineering & procurement
Construct a new 175 miles Amos to Welton Spring 765 kV line. (AEP Section of the line is 30 miles)
APS765$148M2031-05engineering & procurement
Construct a new 765 kV switchyard (Welton Spring)
APS765$146M2031-05engineering & procurement
construct a new 345 kV line from Sporn 345 kV Station to Mercers Bottom 345 kV Station, approximately 26 miles.
AEP345$143M2026-04On Hold
Construct a new 86 miles Welton Spring to Rocky Point 765 kV line (Welton Spring to DVP local area, roughly 21 miles) (VA Portion)
APS765$105M2031-05engineering & procurement
Rebuild approximately 30.2 miles of Glenville - Weston 138 kV Line using steel structures and install new conductor. Replace one double circuit steel lattice structure #94-A with steel monopole struc
APS138$89.5M2030-12engineering & procurement
Rebuild the existing Belva – Clendenin 46 kV line to 138 kV standards (approximately 27 miles).
AEP138$85.6M2026-10engineering & procurement
Rebuild the Amos – Hopkins 138 kV circuit from structure 124-8A to Hopkins station as single circuit (~19.6 miles), including structure work near Saint Albans Tap and Angel Branch Tap.
AEP138$61.3M2028-11engineering & procurement
Rebuild 11.01 mile single circuit 138kV line to replace the existing single circuit 138kV line between East Lynn - Lavalette.
AEP138$60.6M2029-11engineering & procurement
Rebuild approximately 20 miles of line between Bancroft and Milton stations with 556 ACSR conductor
AEP69$56.5M2031-12engineering & procurement
Rebuild existing Apple Grove – Point Pleasant 69 kV line to 138 kV standards. (approx. 17.3 miles)
AEP69$50.3M2027-04engineering & procurement
Peter Creek - Wharncliffe 69kV line - Install new 69kV line with OPGW from the KY/WV State Line to Wharncliffe Station. Intermediate station includes Bear Creek. Includes switching structures Devil An
AEP69$44.7M2031-06engineering & procurement
Rebuild the Junction-Hardy 138kV line, approximately 21.5 miles, with wood pole equivalent steel structures. Replace limiting substation conductor and disconnect switch at Junction 138 kV substation R
APS138$42.6M2026-12under construction
Replace the Belmont 765/500 kV transformer No. 5 with a new transformer bank consisting of three single-phase transformers and an additional single phase spare transformer. The project will also repla
APS765$42.0M2029-06engineering & procurement
Rebuild 12.1 miles of the Junction - Parr Run 138 kV Line. Structures 1-18 (~4.9 miles) are double circuited with the Kelso Gap - Parr Run 138 kV Line and this section does not require a rebuild at th
APS138$35.0M2028-06engineering & procurement
Lester Fork - Tug Fork 69kV line - Install a new single circuit 69kV with OPGW line from Lester Fork to Tug Fork stations crossing the VA/WV state border totaling 8.0 miles long. Create greenfield ROW
AEP69$33.9M2031-06engineering & procurement
Rebuild approximately 10 miles of 46 kV line between Becco and the new Argyle substation. Retire approximately 16 miles of 46 kV line between the new Argyle substation and Chauncey station.
AEP46$33.7M2028-12engineering & procurement
Add two 765 kV breakers at Amos Substation to expand the breaker and a half scheme to accommodate the new Amos-Welton Spring 765 kV line.
AEP765$30.9M2029-06engineering & procurement
Rebuild existing Turner – Ward Hollow 46 kV line sections from Turner Station to Str. 359-213 (0.8 mi) and from Str. 359-203 to Str. 1189-24 (3.3 mi) and from Str. 359-174 to Str. 718-2 (1.8 mi double
AEP13,846$30.4M2027-08engineering & procurement
Phase 1 (Temporary Configuration): 138 kV Line Transmission Taps. Install two 2000 A load-break air switches on the Bedington – Marlowe BMA 138 kV Line. Build approximately 2.2 miles of double circui
APS138$30.4M2026-09under construction
Rebuild the existing Bancroft – Nitro 69kV line (~8.1 miles) to 69 kV standards.
AEP69$27.3M2027-09under construction
Illinois322 projects · $5.5B priced · 140 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Construct new 765 kV transmission line from the existing ComEd Collins 765 kV substation to an interconnection point with MISO near the Illinois/Wisconsin state border.
ComEd765$522M2034-06engineering & procurement
Construct a segment of a new 765 kV transmission line from the existing ComEd Collins 765 kV substation to a new 765 kV Woodford County substation. Interconnection point with MISO to be determined.
ComEd765$272M2034-06engineering & procurement
Replace 345 kV open air straight bus with GIS in a breaker and half configuration (34 Circuit Breakers) at Goodings Grove with 80kA capability.
ComEd345$264M2030-12engineering & procurement
Byron Station 6 - Wayne TSS144 - Build new 345kV line
ComEd345$250M2009-12Active
Install second 2500mm2 XLPE cable per phase on two 1.8 mile 138 kV underground lines from ComEd Elk Grove East substation (ComEd -2023-005) to ComEd Dierking substation (ComEd-2024-004). Install secon
ComEd138$194M2028-12engineering & procurement
Build new 28-mile transmission line from Mendota to Sandwich.
ComEd138$160M2030-12planned
Cut into existing 345 kV Des Plaines-Lombard lines and extend four lines to a new Elk Grove twelve CB 345 kV GIS bus in a breaker-and-a-half configuration. Install two new 420 MVA 345/138 kV autotrans
ComEd345,138$158M2027-10under construction
For the 138 kV L15518 (a three-terminal line between Rock Falls, Nelson, and Garden Plain), rebuild 23 miles of wood poles with 1113 kCMIL conductor on steel towers. Eliminate three terminal line by e
ComEd138$157M2027-06under construction
Replace existing 345kV line conductor and possibly tower structures for approx. 27 miles, Sag mitigation on existing 345kV line conductor for up to 13 miles, Upgrade station 345kV conductor and motor
ComEd345$146M2029-02engineering & procurement
Expand TSS Elk Grove to the east and build a new 138 kV GIS building. Existing overhead 138kV transmission lines, L.18407 and L.18408, will be cut over from the exiting GIS building to the new GIS bui
ComEd138$131M2027-12engineering & procurement
New customer will be radially served by two new 1.5 mile 138 kV underground lines consisting of 2500mm2 XLPE cables per phase from ComEd Dierking substation (ComEd-2024-004) to the customer site. Cust
ComEd138$125M2028-12engineering & procurement
Install two physically diverse 48-count single-mode fiber cables per ComEd standards from TSS 964 Clear Creek Substation to STA 21 Kincaid
ComEd345$108M2026-12On Hold
Cut into existing 345kV line 15502 (Nelson-Electric Junction 345 kV) and extend 2 lines 6 miles each to a new Keslinger substation 345 kV breaker-and-a-half bus. Provide four radial 345 kV leads to cu
ComEd345$105M2027-12engineering & procurement
Rebuild Elmhurst 345 kV bus as indoor GIS double ring bus expandable to breaker-and-a-half connecting two lines and three transformers.
ComEd345$93.0M2026-12under construction
Rebuild/Reconductor 40.61 miles of the AEP owned section of the Olive - University Park 345 kV ACSR/PE 1414 62/19 line section 1 and replace Olive switches and riser.
ComEd345$82.6M2020-06Active
40 miles of 345kV Reconductoring of Nelson to Cardova
ComEd345$80.0M2016-06Active
Rebuild the existing Princeton substation as a 4-position 138 kV substation in a ring bus configuration with two additional positions available for future expansion. Construct a new 4-position 138 kV
AMEREN ILLINOIS138$74.0M2029-06m2 - appendix a approved
Expand and reconfigure the existing ComEd Collins 765 kV substation to install bus positions for two new 765 kV transmission lines, two new 300 MVAR line reactors with dedicated circuit breakers for e
ComEd765$73.6M2034-06engineering & procurement
Rebuild McCook 138 kV with Breaker and a half GIS
ComEd138$72.9M2028-12under construction
Byron Station 6 - Nelson 155 - Build second 345kV line
ComEd345$70.0M2011-05Active
Cut into existing 138 kV lines 8309 (Glidden-Crego Rd) and 11307 (Waterman-Crego Rd) and extend 4 lines 0.7 miles to a new Keslinger substation 138 kV breaker-and-a-half bus. Connect two new 138/34 kV
ComEd345$70.0M2027-12engineering & procurement
Cut into existing 138 kV 0901 line (Davis Creek-East Frankfort-Joliet) and extend two 1.1 mile circuits to a new 138 kV breaker-and-a-half substation. New substation will have twelve 138 kV CBs and su
ComEd138$62.4M2027-12engineering & procurement
Reconductor 345 kV lines 11620 and 11622 from Elwood to Goodings Grove.
ComEd345$56.2M2028-06On Hold
28 miles of 345kV Reconductoring of Wempleton to Byron line and Substation Conductor
ComEd345$56.1M2016-06Active
26.7 miles of 345kV Reconductoring from Silver lake to GardenPR and Substation Conductor
ComEd345$54.1M2016-06Active
Oklahoma235 projects · $2.9B priced · 94 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Anthem 765 kV New Substation
AEP765$377M—ntc-c project estimate window
Delaware - Monett 345 kV Ckt 1 New Line
AEP345$250M2029-11delay - mitigation
Riverside Station - Matthewson 345 kV (OGE)
TBD345$181M—identified
Buffalo Flats - Delaware 345 kV Ckt 1 New Line
AEP345$113M2029-05delay - mitigation
Seminole 345/765 kV Ckt 1 Transformer
OGE345$92.3M—ntc-c project estimate window
Seminole 345/765 kV Ckt 2 Transformer
OGE345$92.3M—ntc-c project estimate window
Redbud - Mathewson 345 kV Ckt 1 New Line
TSOK345$89.5M2028-08delay - mitigation
Muskogee - Tahlequah 345 kV Ckt 1 Rebuild
OGE345$80.9M2028-12delay - mitigation
Riverside Station 138 kV Breakers
AEP138$67.3M2026-05delay - mitigation
Woodward 345/765 kV Ckt 1 Transformer
OGE345$61.5M—ntc-c project estimate window
Woodward 345/765 kV Ckt 2 Transformer
OGE345$61.5M—ntc-c project estimate window
Anthem 345 kV Substation Expansion or Rebuild
AEP345$50.0M—ntc-c project estimate window
Comanche Tap-OmDuncan 138 kV Ckt 1 Rebuild
AEP138$40.7M—identified
Pecan Creek - Keefton 345 kV Ckt 1 New Line
OGE345$37.3M—delay - mitigation
Oklaunion 345 kV Capacitive Reactive Power Support
AEP345$36.1M2026-05delay - mitigation
Talihina - Yanush 138 kV Ckt 1 New Line
AEP138$35.9M—delay - mitigation
Line - Duncan - Duncan Tap - Duncan Eastside - Rush Springs Tap - Marlow 138 kV Ckt 1 Rebuild
AEP138$30.5M2027-12delay - mitigation
Woodward 765 kV Line Reactor
OGE765$30.0M—ntc-c project estimate window
Woodward 765 kV Reactor
OGE765$30.0M—ntc-c project estimate window
Webb City Tap - Osage 138 kV Ckt 1 Rebuild (OGE)
OGE138$28.9M2026-12delay - mitigation
Seminole 765 kV New Substation
OGE765$27.0M—ntc-c project estimate window
Woodward 765 kV New Substation
OGE765$27.0M—ntc-c project estimate window
Beckham County - Potter 345 kV Ckt 1 New Line (TSOK)
TSOK345$25.2M2029-11on schedule < 4
Tulsa North 345/138 kV Transformer Ckt 2 (138 kV)
AEP345$24.9M2029-03delay - mitigation
Ft Smith - Muskogee 345 kV Ckt 2 New Line
OGE345$24.7M2029-12delay - mitigation
Kentucky200 projects · $1.2B priced · 11 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Rebuild the 19 mile long 138 kV line from Thelma - Busseyville.
AEP138$120M2030-11engineering & procurement
Rebuild approximately ~40 miles of Wooton – Pineville 161kV line to address the identified asset condition needs. This work also includes line removal work as well as access road construction. Majori
AEP161$115M2027-11engineering & procurement
Rebuild Prestonsburg - Thelma 46kV circuit connecting though Kenwood station, approximately 12.7 miles. Retire Jenny Wiley SS and Van Lear SS.
AEP46$63.6M2027-12engineering & procurement
Rebuild ~16.7 mi Dorton – Breaks 46kV line to 69kV
AEP69$58.5M2028-03engineering & procurement
Rebuild the 7 mile long section of Big Sandy - Busseyville 138 kV line.
AEP138$48.4M2030-11engineering & procurement
Construct 10.3 miles of single circuit 138kV from Soft Shell to Garrett picking up Salt Lick Co-op via Snag Fork along the way. Complete associated remote end relaying.
AEP138$35.3M2027-05under construction
At Hebron substation expand the box structure and install two new 69 kV, 2000A breakers to create a 4-position ring bus with individual positions for a circuit to Downing and a circuit to Oakbrook. Re
DEOK69$32.0M2027-11engineering & procurement
Install a third 765/345kV 2250 MVA transformer at Baker 765/345kV station.
AEP765$28.5M2014-06Active
Rebuild the 16.3 mile, Duncannon Lane Tap-West Berea 69 KV line sections using 795 conductor and steel pole construction. Construct a new Madison County 69 KV switching station near the Duncannon Lan
EKPC69$26.8M2027-10engineering & procurement
AEP is notifying PJM of our intention to suspend the project associated with S2200. Pending the sale, Liberty can decide on if they plan to move forward with the project as proposed or develop an alt
AEP46$25.5M2029-10On Hold
Add a 765 kV breaker at Baker station for the reactor on the Broadford 765 kV line.
AEP765$23.4M2027-06engineering & procurement
Rebuild 11.1 mile Dale-Newby line section as single circuit 138 kV using 795 ACSR, rebuild Newby as 138/69 kV and relocate the Dale 138/69 kV transformer, construct a 69 kV box structure and install 4
EKPC69$22.9M2029-12engineering & procurement
Install a new 69 kV breaker at EKPC’s Hebron substation, construct a new 7.6 mile 69 kV transmission line from EKPC’s Hebron 69 kV substation to serve a new 69/13.2 kV, 12/16/20 MVA Mineola Pike distr
EKPC69$21.8M2026-12under construction
Rebuild the 29.29 miles, Beattyville – Tyner 69 KV transmission line using 556.5 ACSR/TW conductor.
EKPC69$21.5M2029-08under construction
Rebuild the KU Wofford - Whitley City 69 kV line using 556.5 MCM ACSR/TW conductor (20.7 miles)
EKPC69$17.5M2027-12under construction
Retire the ~25 miles of the 46kV Beaver Creek – McKinney #1 46 KV circuit. Retire Spring Fork Tap.
AEP46$17.3M2028-02under construction
Rebuild the 18.97 mile, Windsor-Somerset 69 KV line sections using existing conductor size and steel pole construction.
EKPC69$17.1M2027-12under construction
Rebuild the Powell County-Bowen-High Rock-Zachariah 69kV line section
EKPC69$16.6M2030-10engineering & procurement
Rebuild the 12 mile, Fayette-Baker Lane 69 kV circuit using 556.5 conductor and steel pole construction. Expand the scope of a current project to rebuild the Nicholasville distribution substation to i
EKPC69$15.8M2030-05under construction
Rebuild the 16.42 mile, Stephensburg-Bonnieville 69 KV line using 556.5 conductor and steel pole construction.
EKPC69$15.3M2027-02under construction
Rebuild the 20.79 mile, Renaker-Penn 69 KV line sections using 556 conductor and steel pole construction.
EKPC69$15.1M2027-12under construction
Rebuild a total of 18.46 miles of 69kV transmission line between Renaker and Williamstown. Replacing 16.94 miles of 1/0 conductor and 1.52 miles of 4/0 conductor with 556.5 ACSR conductor.
EKPC13,869$14.8M2030-12engineering & procurement
Rebuild the 19.9 mile, Headquarters-Murphysville 69kV line using 556.5 ACSR/TW conductor and steel poles & structures (19.9 miles of H-Frame tangent structures will be evaluated on structure by struct
EKPC69$14.7M2026-08under construction
Bellefonte: Replace XFR #2 with a 200MVA Auto unit and retire XFR #1 & #5. The U/G feeder for XFR #3 69kV riser is getting reconductored under B3349. Reconductor sections of 138kV Bus #1 and 138kV Bus
AEP138$12.6M2027-10under construction
At Wilder substation, remove 138/69/34 kV Transformer 2. Install a 138/69 kV, 150 MVA transformer to feed the 69 kV bus and a 138/34 kV, 33 MVA transformer to feed the 34 kV bus. Install a circuit swi
DEOK138$12.1M2026-11under construction
California196 projects · — priced · 28 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Devers-Red Bluff 500 kV 1 and 2 Line Upgrade
SCE500—2030-12preliminary engineering
Manning 500/230 kV Substation Project
LS Power500—2028-04permitting
New Collinsville 500 kV substation
PG&E500—2028-05in-flight
Lugo Substation Install new 500 kV CBs for AA Banks
SCE500—2031-06design
New Humboldt 500 kV Substation with 500 kV line to Collinsville [HVDC operated as AC]
PG&E500—2034-05initiating
New Humboldt to Fern Road 500 kV Line
PG&E500—2034-05initiating
IV-North of Songs 500 kV line and North of Songs Substation
HWT500—2032-10permitting, engineering and design
Round Mountain 500 kV Dynamic Voltage Support (Fern Road Substation)
LS Power500—2026-03construction
Lugo-Victor-Kramer Upgrade (1/3) Add 3rd Lugo 500/230 kV Transformer
SCE500—2029-06preliminary engineering
Collinsville 500/230 kV Substation Project
LS Power500—2028-05permitting
San Jose Area HVDC 500 kV Line (Metcalf – San Jose)
PG&E500—2028-05in-flight
SWIP-North 500kV Transmission Project
GBT500—2028-05permitting
San Jose Area HVDC 500 kV Line (Metcalf – San Jose) - San Jose B Scope
PG&E500—2030-06in-flight
Table Mountain Second 500/230 kV Transformer
PG&E500—2029-05in-flight
Serrano–Del Amo–Mesa 500 kV Transmission Reinforcement
SCE500—2033-12licensing
Devers-Valley 500 kV 1 Line Upgrade
SCE500—2028-04preliminary engineering
Mira Loma 500 kV CB Upgrade Project
SCE500—2028-08design
New Manning 500 kV substation
PG&E500—2028-04in-flight
Serrano-Alberhill-Valley 500 kV 1 Line Upgrade
SCE500—2031-06engineering
Greater Bay Area 500 kV Transmission Reinforcement
PG&E500—2034-05initiating
North-Gila 500 kV line
HWT500—2031-12permitting, engineering and design
North of Songs-Sorreno 500 kV Line
Lotus Infrastructure Global Operations500—2032-01in development
Lugo – Victorville 500 kV Upgrade (SCE portion)
SCE500—2027-12construction
Serrano 500 kV SCD Mitigation
SCE500——new
Round Mountain 500 kV Dynamic Voltage Support
PG&E500—2026-03in-flight
Maryland186 projects · $5.9B priced · 53 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Port Covington 115/13 kV Project
BGE115$407M2028-11engineering & procurement
Build new North Delta-High Ridge 500 kV line. (~59 miles).
BGE500$407M2030-12engineering & procurement
Build a new Loch Raven 115/13 kV substation
BGE115$363M2027-04under construction
Construct a new substation called Rocky Point with a 765 kV and a 500 kV yard. Loop in the Doubs-Goose Creek 500 kV line, the Doubs-Aspen 500 kV line, and the Woodside-Goose Creek 500 kV line. Install
APS765$324M2031-05engineering & procurement
Network East Towson substation to new Loch Raven Distribution Substation with UG 115kV XLPE cables. Install East Towson and Summerfield substation breakers and equipment to accommodate transmission ne
BGE115$276M2031-12engineering & procurement
Build Solley Road substation + Statcom. New STATCOM rating: 350 MVAR Add 4x 230 kV breakers bays.
BGE230$240M2028-12engineering & procurement
Replace 9 miles of 110572-A OH circuit with new UG line The estimated cost of the project is $229.7M Line ratings will not change due to remaining OH sections outside Finksburg and Westminster station
BGE115$230M2029-12engineering & procurement
Brighton Statcom and capacitor New STATCOM rating: 350 MVAR New capacitor rating: 350 MVAR
PEPCO500$229M2027-12under construction
Graceton 500 kV expansion Add 3x 500 kV breaker bays, 2x 500/230 kV auto transformer, 1x 500 kV caps. New transformer rating: 1559 MVA SN / 1940 MVA SE New capacitor rating: 250 MVAR
BGE500$213M2028-12engineering & procurement
Graceton to Batavia Road 230 kV double circuit pole line New rating: 1331 MVA SN/ 1594 MVA SE
BGE230$207M2028-12engineering & procurement
Construct 35.8 miles of 500 kV overhead AC line between the Conastone vicinity and the Doubs substations (BGE zone portion).
PSEG500$207M2027-06engineering & procurement
Build Granite substation + Statcom. New STATCOM rating: 350 MVAR Add 4x 230 kV breaker bays.
BGE230$199M2028-12engineering & procurement
Construct 31.6 miles of 500 kV overhead AC line between the Conastone vicinity and the Doubs substations (APS zone portion).
PSEG500$184M2027-06engineering & procurement
Install four 250 MVAR cap banks (two on 765 and two on 500 kV side) and a +/-500 MVAR STATCOM on the 765 kV Rocky Point yard
APS765$153M2031-05engineering & procurement
Reconductor two (2) 230 kV circuits from Conastone to Northwest #2
BGE230$151M2026-12under construction
Build new 230 kV double circuit line between Rice and Ringgold 230 kV, operated as a single circuit.
Transource230$140M2029-01engineering & procurement
Build Batavia Road substation. Add 4x 230 kV breaker bays.
BGE230$128M2028-12engineering & procurement
Build new 115kV station to supply 34kV & 13kV distribution station, Provide diverse overhead transmission supplies from Riverside and Windy Edge substations to new 115kV station
BGE115$124M2026-12under construction
Construct new Marley Neck 115 kV substation. Marley Neck 115kV portion will accommodate 10 breaker-and-a-half bays, with only 6 bays planned for initial service while accommodating 4 future bays. Tw
BGE230$122M2029-12engineering & procurement
Construct new Woodside-Goose Creek 500 kV line for ~15 miles on single circuit monopole structures within the Doubs-Goose Creek Corridor. (FE Portion)
APS500$115M2031-12engineering & procurement
Rebuild the New Church - Piney Grove 138 kV line
DPL138$77.0M2027-06engineering & procurement
Rebuild 5012 (existing Peach Bottom-Conastone) (new Graceton-Conastone) 500 kV line on single circuit structures within existing ROW and cut into North Delta 500 kV and Gracetone 500 kV stations.
BGE500$61.2M2030-12engineering & procurement
Replace approx. 2 miles per circuit of existing HPFF cables with new 3500 KCM CU LPP HPFF cables.
BGE115$58.5M2030-06planned
Reconfigure Doubs 500 kV station and upgrade terminal equipment to terminate new line.
APS500$57.5M2027-06engineering & procurement
Batavia Road to Riverside 230 kV reconductor New rating: 1941 MVA SN / 2181 MVA SE
BGE230$57.3M2027-12engineering & procurement
Michigan138 projects · $859M priced · 17 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Construct ~36.5 miles of new 138 kV line on double-circuit structures (leave vacant side for future use) using 954 ACSR conductor.
METC138$107M2030-06m1 - proposed
Rebuild the Gaylord – Mio Dam 138kV line with 954 ACSR overhead conductor capable of double circuit 230kV. OPGW will be installed on the rebuild.
METC138$86.9M2029-12m1 - proposed
Replace aging and outdated equipment on a cycle that will ensure each piece of equipment is replaced near its expected end of life. Modern equipment can improve reliability, use state of the art techn
ITC345$59.8M2027-12m1 - proposed
New Buffalo – Bridgman 69kV line: Rebuild the 22.1 mile New Buffalo – Bridgman 69kV line with 556.5 ACSR Dove.
AEP69$55.5M2027-11engineering & procurement
Replace aging and outdated equipment on a cycle that will ensure each piece of equipment is replaced near its expected end of life. Modern equipment can improve reliability, use state of the art techn
METC345$53.9M2027-12m1 - proposed
East Elkhart – Mottville Hydro 138kV: Rebuild the ~10 miles of 1950’s wood on the East Elkhart – Mottville Hydro 138kV line using 795 Drake ACSR
AEP138$31.0M2027-08engineering & procurement
Replace the Caniff 303(AB) PST Transformer with at least 736 MVA (3543 Amps) summer emergency rated transformer.
ITC345$30.0M2028-12m1 - proposed
Rebuild the Pokagon – Niles 69 kV line as the ~9.3 mile Kenzie – FourFlag 69 kV line.
AEP69$22.8M2028-10engineering & procurement
Build new Oneida – Tallman 138 kV circuit utilizing 1431 ACSR and double circuit structures capable of OPGW. Use 9.5 miles METC existing easement and obtaining new 0.5 miles ROW to connect this corrid
METC138$20.9M2029-12m1 - proposed
Rebuild the ~8.4 mile 69 kV Pletcher – Buchanan Hydro line as the ~9 mile Pletcher – Buchanan South 69 kV line using 795 ACSR.
AEP69$20.0M2028-01engineering & procurement
Rebuild 6.7 miles of the 34.5 kV circuit Main Street-Hickory Creek circuit using 556 ACSR conductor.
AEP35$19.5M2027-01under construction
Rebuild the 7.7 mile long Bridgman-Pletcher line with 556 ACSR conductor.
AEP69$18.8M2028-01engineering & procurement
Main Street – Hickory Creek 138kV Line Asset: Rebuild ~3.47 miles of the Derby – Main Street 138kV circuit up to structure 125. Of that ~3.47 miles, the Main Street – Napier – Hickory Creek 34.5kV cir
AEP138$16.2M2030-03engineering & procurement
Derby – Hickory Creek 69kV Line:Rebuild the remaining ~6.2 miles of the Derby – Hickory Creek 69kV line utilizing 795 ACSR which will match the ~2.5 miles built in 2013
AEP69$14.7M2029-04engineering & procurement
Rebuild the 138 kV Alma station to three rows of breaker and a half station capable of three additional rows of BAH expansion. Install eight (8) 138 kV, 3000 A breakers with at least 40 kA interruptin
METC138$13.3M2029-12m1 - proposed
~10.4 Miles of OPGW Installation - This project will align with the 446 T-Line Reinsulate Project between the National and Presque Isle substations as well as the ~7.5 Miles of OPGW Installation on X-
AMERICAN TRANSMISSION COMPANY138$13.0M2027-12m1 - proposed
11.5 miles of single-circuit steel poles with 795 ACSS.
WOLVERINE POWER SUPPLY COOPERATIVE, INC69$13.0M2029-12m1 - proposed
Straits SS Power Transformer Asset Renewal
AMERICAN TRANSMISSION COMPANY138$11.2M2027-12m1 - proposed
11 Miles of transmission line between the Bass Lake and Wolfe Lake substations.
WOLVERINE POWER SUPPLY COOPERATIVE, INC69$11.0M2029-12m1 - proposed
10 miles of single-circuit steel poles with 795 ACSS
WOLVERINE POWER SUPPLY COOPERATIVE, INC69$10.5M2029-12m1 - proposed
Install new 69/34.5kV Bucktown station to replace Buchanan Hydro station. Install new 69/34.5kV transformer with (2) 34.5kV line breakers and a (4) 69kV breaker ring bus.
AEP69$10.4M2028-01engineering & procurement
Rebuild sections of the Batavia – Dorrance #1 & #2 circuits between Structure 124D100 to Batavia (~4.1mi) with 954 ACSR conductor and OPGW..
METC138$10.3M2029-12m1 - proposed
ATC shall construct a 138 kV line interconnection substation to accommodate the generating facility’s collector station to the power system. The new J1750 Substation will be arranged in a three breake
AMERICAN TRANSMISSION COMPANY138$10.1M2029-03m1 - proposed
Cook - Palisades - Construct a 5 breaker 345kV ring bus at circuits
AEP345$10.0M2012-03Active
Construct New Hudson as a new 4-breaker ring bus configuration, 120 kV station and allow enough space for future breaker and a half station configuration once DTE’s future positions are needed. All ne
ITC120$10.0M2028-03m1 - proposed
Missouri128 projects · $2.2B priced · 40 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
New 65 mile double circuit 345 kV line from Barnett to Clinton
AMEREN TRANSMISSION COMPANY OF ILLINOIS345$260M2030-12m1 - proposed
North Branson - Monett 345 kV Ckt 1 New Line
EDE345$214M2030-12delay - mitigation
New 50 mile double circuit 345 kV line from Clinton to LaCygne.
AMEREN TRANSMISSION COMPANY OF ILLINOIS345$205M2030-12m1 - proposed
Delaware - Monett 345 kV Ckt 1 New Line (EDE)
EDE345$164M2030-06delay - mitigation
Convert existing 38 mile 345 and 161 kV double circuit line from Overton to Barnett.
AMEREN TRANSMISSION COMPANY OF ILLINOIS345$107M2030-12m1 - proposed
New 345 kV line
AMEREN MISSOURI345$84.0M2030-12m1 - proposed
Rebuild 35.5 miles of the 345 kV McCredie-Overton
AMEREN MISSOURI345$63.1M2031-06m1 - proposed
Forsythe North - Ozark South 161 kV Ckt 1 Voltage Conversion
EDE161$55.7M—delay - mitigation
Rebuild the existing Overton 161kV straight bus as a breaker-and-a-half (BAAH) station.
AMEREN MISSOURI161$46.0M2027-12m1 - proposed
Sibley - Nashua 345 kV
EM345$44.0M—identified
North Branson 345 kV New Substation
EDE345$42.7M2030-12delay - mitigation
Aurora - Reeds Spring 161 kV Ckt 1 Rebuild
EDE161$41.1M2029-09delay - mitigation
Rebuild 20.7 miles of the Bland-Miller 138 kV transmission line between Belle and Meta
AMEREN MISSOURI138$39.7M2030-12m1 - proposed
North Branson 161 kV New Substation
EDE161$36.9M2030-12delay - mitigation
Overton 345kV switchyard will be converted to four (4) position ring bus and a second 345 / 161 kV transformer rated for 560 MVA will be installed.
AMEREN MISSOURI345$31.0M2027-12m1 - proposed
Rebuild Montgomery-Burns-5481 345kV line to be 3000 Amps summer emergency rated. This is approximately 30 miles of line from the Montgomery 345 kV substation to the new Burns 345 kV substation
AMEREN MISSOURI345$31.0M2027-12m1 - proposed
Monett 345 kV New Substation
EDE345$28.3M2030-12delay - mitigation
Rebuild 11 miles of the Bland-Miller 138 kV transmission line between Miller and Meta.
AMEREN MISSOURI138$28.2M2030-12m1 - proposed
Nashua 345/161 kV Terminal Equipment (345 kV)
EM345$28.0M2028-06delay - mitigation
Sibley - Hawthorn 345 kV CKT 2
TBD345$25.4M—identified
Midway - Avenue City Tap 161 kV Ckt 1 Rebuild
EMW161$24.3M2030-06delay - mitigation
North Branson 345/161 kV Transformer Ckt 1 (161 kV)
EDE345$24.1M2030-12delay - mitigation
Stilwell 345kV GEN-2017-229 Interconnection (Non-Shared NU) (KCPL)
KCPL345$23.7M—identified
Maryville - Midway 161 kV Ckt 1 Rebuild
EMW161$23.5M2030-06delay - mitigation
Aurora H.T. - Monett 161 kV Ckt 1 Rebuild
EDE161$23.2M2028-08delay - mitigation
Wisconsin117 projects · $1.8B priced · 26 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
- Construct new 345/138 kV Mill Road SS, with one 500 MVA 345/138 kV transformer, - Loop in Granville – Arcadian 345 kV line and Cypress – Arcadian 345 kV line to new Mill Road 345 SS, Rebuild Mill Ro
AMERICAN TRANSMISSION COMPANY345$424M2027-10m2 - appendix a approved
Install a new 345/138 kV breaker-and-a half substation with 4 –500 MVA 345/138 kV transformers, +/- 350 Mvar STATCOM, 138 kV capacitor banks, 4 – 345 kV line terminal.
AMERICAN TRANSMISSION COMPANY345$295M2027-01m3 - under construction
Install a new 345/138 kV breaker-and-a half substation with 4 –500 MVA 345/138 kV transformers, 138 kV capacitor banks, and 4 – 345 kV line terminals, and 1 – 138 kV line terminals with a series react
AMERICAN TRANSMISSION COMPANY345$195M2028-04m1 - proposed
Construct two new 345 kV double circuit lines from the existing Arcadian – Pleasant Prairie (PLPL81)/Arcadian – Paris (W-30) 345 kV double circuit line to loop in and out of the Jupiter and Mount Plea
AMERICAN TRANSMISSION COMPANY345$124M2027-01m2 - appendix a approved
Mount Pleasant +/- 350 Mvar STATCOM. WO 605957
AMERICAN TRANSMISSION COMPANY138$83.0M2025-12m3 - under construction
A new 138/24.9 kV breaker-and-a-half substation named Stratus, 138 kV capacitor banks, and construct short transmission lines to cut into the Mount Pleasant-Nimbus 138 kV lines (X-171, X-172) and loop
AMERICAN TRANSMISSION COMPANY138$68.5M2026-07m3 - under construction
The Sun Prairie Area Reliability Project provides additional sources in the Sun Prairie Area to prevent thermal overloads due to multiple contingencies. Sun Prairie Area Reliability Project scope is
AMERICAN TRANSMISSION COMPANY138$61.5M2029-06m1 - proposed
See project description.
AMERICAN TRANSMISSION COMPANY345$45.0M2031-03m1 - proposed
• ATC will construct ~9.6 miles of single circuit 138 kV transmission line to interconnect the proposed distribution substation. • ATC will construct a 138 kV loop-through straight bus with three lin
AMERICAN TRANSMISSION COMPANY138$35.9M2028-12m1 - proposed
1) Construct new 138kV line between City Limits – Northside 2) Rebuild a 138kV line section of 50632 (From STR132131 - City Limits), 3) Rebuild a 138kV line section of 43025 (From STR132131 - Northsid
AMERICAN TRANSMISSION COMPANY138$35.7M2029-05m1 - proposed
Rebuild X-55 North Lake Geneva - Elkhorn 138 kV line per ATC T-Line design standards to achieve minimum 1342 Amps (321 MVA) normal and 1822 Amps (436 MVA) emergency ratings for all seasons. Missing ea
AMERICAN TRANSMISSION COMPANY138$23.9M2026-08m2 - appendix a approved
Mount Pleasant Expansion for Western Feed & 138 kV capacitor banks. WO 606270
AMERICAN TRANSMISSION COMPANY345$20.0M2027-01m3 - under construction
See project description.
AMERICAN TRANSMISSION COMPANY345$19.0M2027-12m1 - proposed
Build a greenfield 69 kV switching station near the location of the Birnamwood tap. The station will be a 6-position straight bus with three breakered line terminals, one for the line segment to Deer
AMERICAN TRANSMISSION COMPANY69$17.5M2028-12m1 - proposed
This project resolves thermal overloads under single contingency conditions on either the X-13 or X-20 lines between Portage and Columbia.
AMERICAN TRANSMISSION COMPANY138$17.3M2027-06m1 - proposed
The new J1629 Interconnection Switching Station will be arranged in a three-breaker ring bus configuration with one generation position and two-line positions. The station will be capable of future ex
AMERICAN TRANSMISSION COMPANY345$16.8M2030-09m1 - proposed
The TO’s new 345kV Interconnection Switching Station is arranged as follows: • in an initial three (3) position, • ultimate four (4) position, • three (3) 345kV circuit breaker ring bus with: o a si
AMERICAN TRANSMISSION COMPANY345$16.1M2028-06m1 - proposed
The X-55 138 kV Transmission Line Partial Rebuild project will consist of installing approximately 8 miles of T2-477 26/7 ACSR Hawk conductor per ATC design standards to achieve a minimum 1229 Amps (2
AMERICAN TRANSMISSION COMPANY138$15.5M2029-06m1 - proposed
High level scope is to install Wi-Fi AP’s & Rogue Detection at various substations and remove Inverter equipment at various substations to complete the Wireless connectivity and Cyber Security fortifi
AMERICAN TRANSMISSION COMPANY—$11.7M2026-12m1 - proposed
The proposed 138kV Interconnection Switching Station is arranged in an initial three (3) position, future four (4) position ultimate ring bus configuration with a single (1) Generator Lead Line positi
AMERICAN TRANSMISSION COMPANY138$11.6M2028-05m1 - proposed
Ellinwood SS T1 Power Transformer Asset Renewal
AMERICAN TRANSMISSION COMPANY138$9.9M2028-12m1 - proposed
Arpin SS T21 Power Transformer Asset Renewal
AMERICAN TRANSMISSION COMPANY345$9.8M2028-12m1 - proposed
Uprate low rated segments of the Arcadian to Pleasant Prairie 345 kV line (PLPL81) and the Arcadian to Paris 345 kV line (W-30).
AMERICAN TRANSMISSION COMPANY345$9.5M2027-01m1 - proposed
Create a new Highland - Hill Valley 138 kV line by: - Converting 6.25 miles of the existing Highland - Eden 69 kV line Y-207 to 138 kV. Along the 69 kV corridor, new easements will be required. - Con
AMERICAN TRANSMISSION COMPANY138$9.5M2026-09m1 - proposed
See project description.
AMERICAN TRANSMISSION COMPANY345$9.0M2026-12m1 - proposed
South Dakota114 projects · $863M priced · 29 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
St. Germaine - Fox Ridge 345 kV Ckt 1 New Line
BEPC345$217M2034-10ntc - commitment window
Groton Tap - Groton 345 kV
WAPA345$32.9M—identified
Broadland - Groton 345 kV
WAPA345$32.9M—identified
Ft. Thompson 345 kV Substation Expansion or Rebuild
WAPA345$19.5M2034-12delay - mitigation
Aurora 115 kV Substation Expansion or Rebuild
WAPA115$18.6M2031-12delay - mitigation
Ft. Thompson 345/230 kV Ckt 3 Transformer
WAPA345$16.5M2034-12delay - mitigation
Twin Brooks 3 to Ellendale 3 345 kV Tap (OTP)
TBD345$16.5M—identified
Twin Brooks 3 to Ellendale 3 345 kV Tap
MDU345$16.5M—identified
St. Germaine 345/230 kV Transformer Ckt 1 (230 kV)
BEPC345$16.4M2034-10delay - mitigation
St. Germaine 345 kV New Substation
BEPC345$16.2M2034-10delay - mitigation
Fox Ridge 345/230 kV Transformer Ckt 1 (230 kV)
BEPC345$16.1M2034-10delay - mitigation
Fox Ridge 345 kV New Substation
BEPC345$15.4M2034-10delay - mitigation
Convert Cliff Avenue 69kV substation to 115kV.
NORTHERN STATES POWER COMPANY115$15.0M2029-06m1 - proposed
Convert Lincoln 69kV substation to 115kV
NORTHERN STATES POWER COMPANY115$15.0M2029-06m1 - proposed
Aurora - White 115 kV Ckt 1 New Line (2)
WAPA115$14.4M2031-12delay - mitigation
Manchester - Carpenter 115 kV Ckt 1 New Line
EREC115$13.3M2026-04delay - mitigation
Install new distribution substation to meet load growth in area
NORTHERN STATES POWER COMPANY115$13.0M2027-06m1 - proposed
Fox Ridge 345 kV Ckt 1 Terminal Upgrade
BEPC345$11.7M2034-10delay - mitigation
Laramie River 345 kV Ckt 1 Terminal Upgrade (BEPC)
BEPC345$11.6M2034-10on schedule < 4
White 345/115 kV Ckt 2 Transformer
WAPA345$10.9M2035-06delay - mitigation
St. Germaine 345 kV Ckt 1 Terminal Upgrade #2
BEPC345$10.6M2034-10delay - mitigation
Fox Ridge 345 kV Ckt 1 Terminal Upgrade #1
BEPC345$10.1M2034-10delay - mitigation
Broadland 345/230kV Transformer Replacement (DISIS-2017-001)
BEPC345$10.1M2025-05closed out
Arlington - Kingsbury County 115 kV Ckt 1 New Line
EREC115$10.0M2026-04delay - mitigation
Belfield 345/230 kV Transformer Ckt 1
WAPA345$10.0M2034-11delay - mitigation
New Mexico111 projects · $5.0B priced · 47 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Crossroads - Bandit 765 kV Ckt 1 New Line
SPS765$2.1B2031-05delay - mitigation
Tecovas - Crossroads 765 kV Ckt 1 New Line
SPS765$937M2031-05delay - mitigation
New 765 kV Substation at Crossroads
SPS765$164M2031-05delay - mitigation
New 765 kV Substation at Bandit
SPS765$156M2031-05delay - mitigation
Moore County 230/115 kV Transformer Ckt 2
SPS230$86.6M2029-05delay - mitigation
Moore County - Xit 230 kV Ckt 1 New Line
SPS230$77.1M2028-12delay - mitigation
Crossroads 765/345 kV Transformer Ckt 1 (345 kV)
SPS765$74.3M2031-05delay - mitigation
Bandit 765/345 kV Transformer Ckt 1 (345 kV)
SPS765$73.7M2031-05delay - mitigation
Crossroads 765 kV Reactor 2
SPS765$69.9M2031-05delay - mitigation
Crossroads 765/345 kV Transformer Ckt 3 (345 kV)
SPS765$63.1M2031-05delay - mitigation
Crossroads 765/345 kV Transformer Ckt 2 (345 kV)
SPS765$63.1M2031-05delay - mitigation
Bandit 765 kV Reactor 1
SPS765$62.6M2031-05delay - mitigation
Bandit 765/345 kV Transformer Ckt 2 (345 kV)
SPS765$62.2M2031-05delay - mitigation
Bandit 765/345 kV Transformer Ckt 3 (345 kV)
SPS765$62.2M2031-05delay - mitigation
Phantom 345 kV Substation Expansion
SPS345$57.4M2031-05delay - mitigation
Bandit 765 kV Line Reactors
SPS765$42.0M—ntc-c project estimate window
Phantom 345 kV Cap Bank
SPS345$37.3M2026-05on schedule < 4
Crossroads 765 kV Reactor 1
SPS765$37.2M2031-05delay - mitigation
Sand Dunes 115 kV Substation Expansion or Rebuild
SPS115$37.2M2029-12delay - mitigation
Lea National 345 kV New Substation
SPS345$26.1M2029-12delay - mitigation
Hobbs 345 kV ckts 1 & 2 Terminal Equipment #1
SPS345$24.7M2025-11closed out
XFR - Roadrunner 345/115 kV #3
SPS345$24.5M2029-03delay - mitigation
Bandit 765 kV Ckt 1 Terminal Upgrade toward Crawfish Draw 765 kV
SPS765$24.4M—ntc-c project estimate window
Lea National 115 kV Substation Expansion or Rebuild
SPS115$24.4M2029-12delay - mitigation
Battle Axe 115 kV Substation Expansion or Rebuild
SPS115$22.9M—delay - mitigation
North Dakota110 projects · $2.3B priced · 54 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Belfield 2 - Fox Ridge 345 kV Ckt 1 New Line
BEPC345$413M2034-10delay - mitigation
Dawson County - Williston 230 kV Ckt 1 New Line
BEPC230$238M2032-12delay - mitigation
Leland Olds - Finstad - 345 kV New Line
BEPC345$213M2026-11delay - mitigation
Belfield - Roundup 345 kV Ckt 1 New Line
BEPC345$156M—ntc-c project estimate window
Logan - Crane Creek 345 kV Ckt 1 New Line
BEPC345$149M2032-11on schedule < 4
Patent Gate - Pioneer 345 kV Ckt 1 New Line
BEPC345$131M2030-11delay - mitigation
Logan - Leland Olds 345 kV Ckt 1 Voltage Conversion
BEPC345$109M2032-11on schedule < 4
Finstad - Tande 345 kV New Line
BEPC345$86.6M2026-11delay - mitigation
North Dakota/Saskatchewan Border (Tableland) - Tande 230 kV Ckt 1
BEPC230$82.7M2027-10on schedule < 4
North Dakota/Saskatchewan Border (Tableland) - Wheelock 230 kV Ckt 1
BEPC230$78.7M2027-10on schedule < 4
Springbrook - Twelve Mile 345 kV Ckt 1 New Line
BEPC345$41.0M2032-03on schedule > 4
Marley 345 kV New Substation
BEPC345$24.2M—delay - mitigation
Belfield 2 345 kV Ckt 1 Terminal Upgrade
WAPA345$23.0M2034-11delay - mitigation
Build a new 115/69/41.6 kV substation with the rebuild of the Hettinger-Elgin line to 115 kV.
MONTANA-DAKOTA UTILITIES CO.115$23.0M2029-12m1 - proposed
W Bank South 345 kV New Substation
BEPC345$22.6M2031-12on schedule > 4
Kummer Ridge 345 kV Capacitor Bank
BEPC345$20.0M—identified
Finstad 345 kV New Substation
BEPC345$19.2M2026-11delay - mitigation
Logan 345/230 kV Transformer Ckt 2 (230 kV) #1
BEPC345$17.0M2032-11on schedule < 4
Twelve Mile 345 kV New Substation
BEPC345$16.9M2032-03on schedule > 4
Logan 345/230 kV Transformer Ckt 1 (230 kV)
BEPC345$16.8M2032-11on schedule < 4
Marley 345/115 kV Ckt 2 Transformer
BEPC345$16.2M—delay - mitigation
Marley 345/115 kV Ckt 1 Transformer
BEPC345$15.9M—delay - mitigation
Logan 345 kV New Substation
BEPC345$15.7M2032-11delay - mitigation
Crane Creek - Satterthwaite115 kV Ckt 1 New Line
MWE115$14.5M2027-12on schedule < 4
Belfield 345 kV Substation Expansion or Rebuild
WAPA345$14.0M2033-07ntc-c project estimate window
Minnesota104 projects · $1.0B priced · 15 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
New 345kV line Split Rock-Chanarambie
NORTHERN STATES POWER COMPANY345$125M2033-06m1 - proposed
Install new facilities to meet load growth in the area.
GREAT RIVER ENERGY345$120M2030-12m1 - proposed
Installing a +/- 300 MVAR STATCOM at the Riverton 230 kV Substation
MINNESOTA POWER INC.230$70.0M2028-03m1 - proposed
Age and Condition rebuild of davit arms for Lyon County to Helena (inclusive of line segments extending from Lyon County to MN Valley, and Cedar Mountain to Franklin).
NORTHERN STATES POWER COMPANY345$57.1M2030-09m1 - proposed
Add 2x50 MVA Transformers Add breakers Extend feeders
NORTHERN STATES POWER COMPANY115$35.1M2028-12m1 - proposed
Upgrade 115kV line Split Rock-Pipestone-Chanarambie.
NORTHERN STATES POWER COMPANY115$25.0M2033-06m1 - proposed
Build new Substation in Northwest Maple Grove to accommodate load growth
NORTHERN STATES POWER COMPANY115$25.0M2028-09m1 - proposed
Install new facilities to meet load growth in the area.
GREAT RIVER ENERGY115$25.0M2026-12m1 - proposed
Rebuild SP line. Soderville Substation to #152. Line length is approx. 10 miles
GREAT RIVER ENERGY69$21.3M2031-03m1 - proposed
Upgrade Byron - Pleasant Valley 161kV Line
NORTHERN STATES POWER COMPANY161$20.0M2029-06m1 - proposed
Condition replacement of cracked Davit Arms on Brookings County- Hawks Nest Lake - Lyon County and Brookings County - Steep Bank Lake - Lyon County and Hampton Helena 345kV line structures.
NORTHERN STATES POWER COMPANY345$18.1M2030-09m1 - proposed
Rebuild BE line from SS2505 to Bena Substation. Line length is approx. 15 miles. Enbridge plans to remove Line 3 which is located roughly 15ft north of GRE’s BE line between Bena Sub and Str 158 nea
GREAT RIVER ENERGY69$17.5M2029-11m1 - proposed
Like-for-like age and condition replacement of select davit arms on Hampton - Helena 345kV line
NORTHERN STATES POWER COMPANY345$16.7M2030-09m1 - proposed
Substation upgrades to accommodate new reactor at Prairie including retirement of 3 capacitor banks.
NORTHERN STATES POWER COMPANY230$15.5M2029-01m1 - proposed
Install new Stewart distribution transformer 2 to meet load growth in area
NORTHERN STATES POWER COMPANY69$15.0M2027-12m1 - proposed
Upgrade 69 kV lines Fort Ridgley-GRE Schilling Tap, Lafayette-GRE Lafayette, GRE Schilling Tap-GRE Lafayette Tap, and Winthrop-Lafayette
NORTHERN STATES POWER COMPANY69$14.0M2029-01m1 - proposed
Rebuild 0735 St Bonifacius to Mound and add OPGW
NORTHERN STATES POWER COMPANY69$13.2M2026-12m1 - proposed
Rebuild 0737 Gleason Lake to Mound and install OPGW.
NORTHERN STATES POWER COMPANY69$13.0M2028-03m1 - proposed
Rebuild SH line. SS306 to Green Lake Sub to Hawick Sub. Line length is approx. 13.7 miles
GREAT RIVER ENERGY69$12.8M2030-04m1 - proposed
Like-for-like age and condition replacement of select steel davit arms on line 0973 - Quarry to Monticello.
NORTHERN STATES POWER COMPANY345$12.5M2030-09m1 - proposed
Rebuild 0868 from Le Sauk to Fisher Hills to St. Stephens
NORTHERN STATES POWER COMPANY115$12.2M2029-01m1 - proposed
Rebuild CP line. CPX Line to the CPT Line. Line length is approx. 11 miles. Rebuild RLT Line. Line length is approx. 0.1 miles Rebuild CPT Line. SS2984 to SS2555. Line length is approx. 1.5 miles
GREAT RIVER ENERGY69$11.8M2029-08m1 - proposed
The transmission line has had conductor failures over the last few years. A recent failure caused a grass fire. The line was planned to be rebuilt due to age/condition starting in 2027 and due to th
GREAT RIVER ENERGY69$11.4M2026-12m1 - proposed
2nd 161/69kV Transformer 45/60/75 MVA
Central Minnesota Municipal Power Agency161$11.2M2026-12m1 - proposed
Construct a new 69 kV line from the Pennock distribution substation to a new breaker station at the point of interconnection of the GRE owned WS 69 kV line and the WMUC 69 kV line (St. Johns breaker s
GREAT RIVER ENERGY69$11.0M2029-12m1 - proposed
Kansas96 projects · $2.1B priced · 26 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Holcomb - Sidney 345 kV Ckt 1 New Line (SEPC)
SEPC345$541M2030-10delay - mitigation
Holcomb - Sidney 345 kV Ckt 1 New Line (TSGT)
TSGT345$515M2030-12delay - mitigation
Buffalo Flats - Delaware 345 kV Ckt 1 New Line (EKC)
EKC345$363M2029-12delay - mitigation
S3771 - Hoyt 345 kV Ckt 1 New Line (EKC)
EKC345$162M2032-09delay - mitigation
Smoky Hills - Summit 230 kV Ckt 1 Rebuild (2) (EKC)
EKC230$45.8M2029-12delay - mitigation
Smoky Hills - Summit 230 kV Ckt 1 Rebuild (2) (MIDW)
MIDW230$44.2M2029-12delay - mitigation
Sibley 345 kV Bus Reconfiguration
EMW345$43.7M2032-09delay - mitigation
West Gardner 345kV Interconnection Expansion (DISIS-2017-002)
EMW345$43.5M2030-11on schedule < 4
Reno - Summit 345kV GEN-2016-111 Interconnection (Non-Shared NU) (WERE)
EKC345$21.4M2028-12on schedule < 4
Sidney 345 kV Ckt 1 Terminal Upgrade
BEPC345$21.1M2030-12delay - mitigation
Holcomb 345 kV Ckt 1 Terminal Upgrade
SEPC345$20.2M2030-10delay - mitigation
Farber - Sumner County No. 10 Belle Plain 138 kV Ckt 1 Rebuild
EKC138$19.2M2029-06delay - mitigation
North Hays - Chetolah Creek 115 kV Ckt 1 New Line
MIDW115$16.6M2028-06delay - mitigation
Altamont Tap - Katy 69 kV Ckt 1 Rebuild
EKC69$15.4M2029-06delay - mitigation
Build the HOLCOMB7 to HOLCOMB3 345kV Transformer 2
SEPC345$15.0M—identified
Rebuild the SEWARD 3 to ST-JOHN3 115kV Line 1
SEPC115$14.7M—identified
Katy 69 kV New Substation
EKC69$14.0M2027-12delay - mitigation
Butler South - Tallgrass 138 kV Ckt 1 Rebuild #1
EKC138$14.0M2029-06delay - mitigation
Elm Creek - Summit 345 kV GEN-2017-004 Interconnection (Non-Shared NU) (ITCGP)
ITCGP345$13.9M2027-07on schedule < 4
Weaver - Tallgrass 138 kV Ckt 1 Rebuild #1
EKC138$13.0M2029-12delay - mitigation
Replace the SIBLEY 7 to SIBLEY 5 345kV Transformer 1
GMO345$12.2M—identified
Chisholm - Maize 138 kV Ckt 1 Rebuild
EKC138$10.6M2031-12on schedule > 4
Franklin 161/69 kV Transformer Ckt 2
EKC161$9.3M2026-05delay - mitigation
Butler - Midian 138 kV Ckt 1 Rebuild
EKC138$9.2M2028-12delay - mitigation
Craig - Lenexa 161 kV Ckt 2 Rebuild (2)
EM161$8.9M2029-12delay - mitigation
Nebraska85 projects · $2.0B priced · 34 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Cherry Co. - Holt Co. 345 kV Ckt 1
NPPD345$357M2028-09delay - mitigation
Raun - S3452 345 kV Ckt 1 New Line
OPPD345$305M2032-11delay - mitigation
Cherry Co. - Gentleman 345 kV Ckt 1
NPPD345$297M2028-09delay - mitigation
S3454 - S3740 345 kV New Line
OPPD345$139M2026-12delay - mitigation window
S3771 - Hoyt 345 kV Ckt 1 New Line (OPPD)
OPPD345$131M2032-10delay - mitigation
Elm Creek - Tobias 345 kV Ckt 1 New Line (NPPD)
NPPD345$124M2030-12delay - mitigation
S3458 - S3740 345 kV Ckt 2 New Line
OPPD345$97.4M2030-12delay - mitigation
S3771 345 kV New Substation
OPPD345$73.0M2032-10delay - mitigation
Antelope - Holt County 345 kV Ckt 1 New Line
NPPD345$69.2M2029-12on schedule < 4
S3452 345 kV New Substation
OPPD345$60.7M2032-11delay - mitigation
Sub 1209 - Sub 1250 161 kV Ckt 2 Rebuild
OPPD161$32.3M2027-05on schedule < 4
Ainsworth Wind - Bassett 115 kV Ckt 1 New Line
NPPD115$31.0M2029-06on schedule < 4
Aurora - Central City 115 kV Ckt 1 New Line
NPPD115$22.4M2028-12delay - mitigation
Axtell 345 kV Ckt 2 Terminal Upgrade toward Axtell 115 kV
NPPD345$16.4M2030-12on schedule < 4
Axtell 115/345 kV Ckt 2 Transformer
NPPD115$15.5M2030-12on schedule < 4
Cherry Co. Substation 345 kV
NPPD345$15.5M2028-09delay - mitigation
Norfolk - Stanton North 115 kV line
NPPD115$14.4M2026-11on schedule < 4
Cooper - Moore 345 kV Line Tap
NPPD345$13.7M2032-10delay - mitigation
Spalding to North Loup 115kV GEN-2017-234 Interconnection (Non-Shared NU) (NPPD)
NPPD115$12.5M2028-06on schedule < 4
W Bank South 345/115 kV Transformer Ckt 1 (115 kV)
BEPC345$12.2M2031-12on schedule > 4
Hoskins 230/115 kV Transformer
NPPD230$11.6M2026-11on schedule < 4
Tobias 345 kV Ckt 1 Terminal Upgrade
NPPD345$11.4M2030-12delay - mitigation
Raun - Tekamah 161 kV Rebuild (OPPD)
OPPD161$10.3M2032-11delay - mitigation
Thedford 345/115 kV Transformer
NPPD345$9.9M2027-12delay - mitigation window
McCool 345kV GEN-2017-210 Interconnection (Non-Shared NU) (NPPD)
NPPD345$9.9M2026-10on schedule < 4
Iowa84 projects · $731M priced · 34 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Construct new Beverly - Hills 345 kV line to support Phase 1 load addition at Big Cedar, a portion of the line to be located on new ROW and a portion of the line to overbuild existing 161 kV line betw
ITC MIDWEST345$160M2027-09m2 - appendix a approved
Install additional reactive compensation (a new +500 MVAR SCU is being initially proposed) to support the additional load at Big Cedar.
ITC MIDWEST345$150M2028-09m2 - appendix a approved
Expand Substation 91 by converting the 345 kV yard to a ring bus configuration and by installing a second 345-161 kV transformer.
MIDAMERICAN ENERGY CO.345$58.0M2028-12m1 - proposed
Replace aging and outdated equipment on a cycle that will ensure each system is replaced near its expected end of life. Modern equipment can improve reliability, use state of the art technology, and w
ITC MIDWEST345$53.9M2027-12m1 - proposed
ITC will be expanding the Rock Creek 345 kV substation to accommodate two additional 345 kV lines. The substation will be expanded to a Breaker and a Half configuration. All new substation equipment w
ITC MIDWEST345$23.7M2028-12m1 - proposed
Expand Big Cedar 345 kV Switching Station to accommodate two new 345 kV lines to serve a new customer owned substation and a new 2nd 345 kV line between Big Cedar and Morgan Valley.
ITC MIDWEST345$14.6M2027-09m2 - appendix a approved
Replace substation equipment because of condition and/or to improve reliability at various substations
MIDAMERICAN ENERGY CO.345$14.5M2028-12m1 - proposed
Network Upgrades for J1532 Generator (69 kV Interconnection Sub)
MIDAMERICAN ENERGY CO.69$12.9M2027-09m1 - proposed
Network Upgrades for J1530 Generator (69 kV Interconnection Sub)
MIDAMERICAN ENERGY CO.69$12.8M2026-09m1 - proposed
Network Upgrades for J1529 Generator (69 kV Interconnection Sub)
MIDAMERICAN ENERGY CO.69$12.8M2027-09m1 - proposed
Add new 345 kV line terminal at Hills to accommodate the new ITCM Hills-Beverly 345 kV line
MIDAMERICAN ENERGY CO.345$12.0M2027-09m2 - appendix a approved
Add reactive compensation at Big Cedar to support Phase 1 load addition
ITC MIDWEST345$12.0M2027-09m2 - appendix a approved
Rebuild the Clarion-Latimer 69 kV line sections.
MIDAMERICAN ENERGY CO.69$11.5M2028-06m1 - proposed
Rebuild 13.34 miles of 69kV line to T2-477 ACSR with 69 kV standard between Hayward and County Line
ITC MIDWEST69$10.7M2028-12m1 - proposed
Expand 88th St Substation steel to ring bus and add a third 161-13 kV transformer
MIDAMERICAN ENERGY CO.161$9.0M2027-12m1 - proposed
Expand Big Cedar 345 kV Switching Station to accommodate two new 345 kV lines to serve a new customer owned substation and a new terminal for phase 2 reactive compensation.
ITC MIDWEST345$7.6M2028-09m2 - appendix a approved
Network Upgrades for J1529 Generator (69 kV line rebuild)
MIDAMERICAN ENERGY CO.69$7.5M2027-12m1 - proposed
Add 2nd Big Cedar - Morgan Valley 345 kV line on existing structures
ITC MIDWEST345$7.0M2027-09m2 - appendix a approved
ITCM will build the 161 kV 2 row 4 position breaker and a half substation with 2 line positions and 2 transformer positions.
ITC MIDWEST161$6.7M2026-06m1 - proposed
Reconductor existing Quad Cities - Rock Creek 345 kV line to 3000 amp nominal conductor.
ITC MIDWEST345$6.4M2028-12m1 - proposed
Add 2nd Quad Cities - Rock Creek 345 kV line on existing spare position on existing structures. New line to be rated 3000 amps nominal.
ITC MIDWEST345$6.4M2028-12m1 - proposed
Rebuild portion of Bertram - Rose Hollow 161 kV that is overbuilt by new Beverly - Johnson 345 kV line
ITC MIDWEST161$6.0M2027-09m2 - appendix a approved
Rebuild 5.71 miles of 69kV line to T2-477 ACSR with 69kV standards
ITC MIDWEST69$5.2M2028-12m1 - proposed
Move Rock Creek - Bryant 345kV line to terminate from rebuilt Rock Creek
ITC MIDWEST345$5.1M2028-12m1 - proposed
ITCMW will build the 69 kV portion of the Spirit Lake Anchor substation
ITC MIDWEST69$4.5M2028-12m1 - proposed
Louisiana50 projects · $5.7B priced · 32 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Cargas 500 kV station will be cut into the Perryville to Sterlington 500 kV lines 1 and 2 and Perryville to Baxter Wilson 500 kV line.
ENTERGY SERVICES, LLC.500$1.2B2026-12m2 - appendix a approved
Construct a new ~145-mile 500 kV line from Babel to Webre 500 kV line.
ENTERGY SERVICES, LLC.500$1.1B2030-06m1 - proposed
Southwest Shreveport - Seminole 765 kV Ckt 1 New Line (AEP)
AEP765$911M—ntc-c project estimate window
Southwest Shreveport - Seminole 765 kV Ckt 1 New Line (OGE)
OGE765$911M—ntc-c project estimate window
Entergy is proposing to construct • Sarepta 500 kV station including a Sarepta 500-345 kV Autotransformer • New ~60 mile Mt Olive to Sarepta 500 kV line. • Upgrade existing Mt Olive 500-230 kV Autotra
ENTERGY SERVICES, LLC.500$470M2028-12m2 - appendix a approved
500 kV ring bus and 6 bay breaker and a half 230 kV station
ENTERGY SERVICES, LLC.500$284M2028-08m2 - appendix a approved
Address aging and failing equipment such as structures, breakers, relay panels, RTU's, arresters, circuit switchers, etc
ENTERGY SERVICES, LLC.500$83.3M2026-12m1 - proposed
Southwest Shreveport 345/765 kV Ckt 1 Transformer
AEP345$61.5M—ntc-c project estimate window
Southwest Shreveport 345/765 kV Ckt 3 Transformer
AEP345$61.5M—ntc-c project estimate window
Southwest Shreveport 345/765 kV Ckt 2 Transformer
AEP345$61.5M—ntc-c project estimate window
Stanley - Huxley 69 kV Ckt 1 New Line
ETEC69$60.2M—delay - mitigation
Entergy is proposing to construct a new 230 kV four breaker ring bus station named Bluepoint to serve a new customer cut into the new Commodore to Waterford 230 kV line (~10.4 miles in and out) near D
ENTERGY SERVICES, LLC.230$59.6M2027-08m2 - appendix a approved
Install 223.90 MVAR reactive support (2-SVCs) at Little Prairie 230 kV station
ENTERGY SERVICES, LLC.230$54.3M2031-10m1 - proposed
Construct a 230 kV Benoit Station on the Mud Lake to Big Lake line.
ENTERGY SERVICES, LLC.230$51.8M2027-07m2 - appendix a approved
Southwest Shreveport 345 kV STATCOM Ckt 1
AEP345$47.0M—ntc-c project estimate window
Southwest Shreveport 345 kV STATCOM Ckt 2
AEP345$47.0M—ntc-c project estimate window
Entergy is proposing to construct a new 115 kV station named Riparian to serve a new customer cut into the existing Alliance to Happy Jack 115 kV line in Point Celeste, LA.
ENTERGY SERVICES, LLC.115$38.2M2026-12m2 - appendix a approved
Welsh 345 kV Bus Reconfiguration
AEP345$27.2M—on schedule < 4
Southwest Shreveport 765 kV New Substation
AEP765$27.0M—ntc-c project estimate window
Substation including breakers and Capacitor bank
ENTERGY SERVICES, LLC.138$24.1M2027-12m2 - appendix a approved
Southwest Shreveport 765 kV Ckt 1 Terminal Upgrade toward Seminole 765 kV
AEP765$18.0M—ntc-c project estimate window
Southwest Shreveport 765 kV Line Reactor
AEP765$15.7M—ntc-c project estimate window
Southwest Shreveport 765 kV Reactor
AEP765$15.0M—ntc-c project estimate window
Upgrade Harelson to Jone Creek 69 kV line
ENTERGY SERVICES, LLC.69$14.7M2027-06m1 - proposed
Southwest Shreveport 345/138 kV Ckt 1 Transformer
AEP345$10.8M—ntc-c project estimate window
Delaware42 projects · $503M priced · 2 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Rebuild Riverside 115kV station as 12 position GIS Breaker and Half Substation on existing BGE owned property. Install 115 kV, 4000A, 63kA interrupting current equipment. Install Relay and Control Pan
BGE115$99.4M2029-07engineering & procurement
Rebuild line #23076 from Milf230 to Steele with 1590 ACSR 125 C
DPL230$44.0M2016-06Active
Rebuild Line #23033 Cartanza to Mil 230 kV
DPL230$39.8M2016-06Active
Rebuild Line #22085 from Edgemr5_Linwood to dual 1590 ACSR
DPL230$38.3M2016-06Active
Rebuild existing Sharptown-Laurel 69 kV circuit utilizing 954 ACSR "Rail" 45/7 conductor.
DPL69$36.5M2030-05planned
Rebuild line #13703 INDRV 2&3 to NELSON and replace substation bus
DPL138$31.5M2016-06Active
Construct new 138 kV feed (approx. 4 mi) out of Townsend substation, utilizing an open terminal position, to a new 4-breaker ring bus adjacent to customer’s existing substation. De-energize remainder
DPL138$27.0M2029-01engineering & procurement
Rebuild the Darley – Naamans 69 kV circuit
DPL69$27.0M2027-06engineering & procurement
Rebuild the Silverside – Darley 69 kV circuit
DPL69$19.0M2026-12engineering & procurement
Rebuild line 13707 from Nelson to Vienna8 with 1590 ACSR
DPL138$17.5M2016-06Active
Build a 3-breaker ring 230 kV bus that would tie into the existing 23069 Milford - Cool Spring 230 kV line
DPL230$15.0M2030-12engineering & procurement
Rebuild Line 6705 _2 from sharptwn to vienn 69 kV with 1590 ASCR, upgrade all substation equipment to 2000 A
DPL69$12.5M2016-06Active
Rebuild the portion of the 6704-1 Church – New Meredith 69kV line exiting Church Substation to the proposed location of the AB2-135 tap with new poles, insulators and 954 ACSR Rail Conductor.
DPL69$11.3M2016-06Active
Rebuild line 6705_1 from Sharptwnto AA1-142 Tap with 954 ACSR
DPL69$10.9M2016-06Active
Rebuild line 6705_1 from Laurel to AA1-142 Tap with 954 ACSR
DPL69$10.9M2016-06Active
Construct a new 3-breaker ring bus substation tying into to the Robinsonville – Rehoboth 138kV line with a terminal position dedicated to the customer
DPL138$10.5M2030-12engineering & procurement
Upgrade 138/69kV autotransformer, a 69kV breaker, two disconnects and move a takeoff structure at Reybold Substation. These upgrades will require a substation expansion to move the takeoff structure a
DPL138$9.5M2029-12engineering & procurement
Replace N. Seaford 138/69 kV Autotransformer #1
DPL138$8.0M2028-04engineering & procurement
Convert existing Preston 69 kV Substation to DPL’s current design standard of a 3-breaker ring bus.
DPL69$6.7M2029-05engineering & procurement
Red Lion - Hope Creek 500 kV - Replace four 500kV breakers and the stranded bus at Red Lion 500 kV substation
DPL500$6.0M2030-12engineering & procurement
Replace four (4) 1200 A disconnect switches with 2000 A disconnect switces. Replace existing 954 ACSR and 1272 MCM AL stranded bus with (2) 954 ACSR stranded bus. Reconfigure eight (8) CTs from 1200 A
DPL69$3.5M2027-11engineering & procurement
Rebuild line #13773 from Farmview to MILF_138 954 ACSR 125 C
DPL138$2.8M2016-06Active
Replace auto transformer 2 from Church _church 69
DPL138$2.8M2016-06Active
Replace three (3) existing 1200 A disconnect switches with 2000 A disconnect switches and install three (3) new 2000 A disconnect switches at Silverside 69 kV station
DPL69$2.4M2027-11engineering & procurement
Install (2) new 2000A 138 kV breakers on the Red Lion 138kV ring bus to create a position for the new transformer
DPL138$1.9M2025-12engineering & procurement
Arkansas36 projects · $1.5B priced · 15 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Ft. Smith - Thistle 345 kV CKT 1
TBD345$461M—identified
Flint Creek - Buffalo Flats 345 kV
TBD345$350M—identified
Ft Smith - Sooner 345 kV CKT 1
OGE345$291M—identified
Highway 59 Tap - Tahlequah 345 kV Ckt 1 Voltage Conversion
OGE345$110M2029-12delay - mitigation
Upgrade the existing 500/345kV autotransformers and associated equipment to 1200MVA.
ENTERGY ARKANSAS, LLC500$35.7M2028-12m2 - appendix a approved
Ft Smith 500/345 kV Transformer Ckt 2 Terminal Equipment (500 kV)
OGE500$30.7M2030-12delay - mitigation
Rebuild St Joe – Everton Rd along with any other station equipment to achieve a 1300 A through path rating.
ENTERGY ARKANSAS, LLC161$29.7M2028-07m1 - proposed
Compliance with NERC Reliability Standard TPL-001, R2.7. Increased reliability by updating aging infrastructure and increased line capacity for improved transmission system performance.
ENTERGY ARKANSAS, LLC161$20.1M2029-04m1 - proposed
Tuco-Oklaunion 345kV Line Tap (DISIS-2018-001)
SPS345$18.6M2027-06on schedule < 4
Ft Smith 500/345 kV Transformer Ckt 2 (345 kV)
OGE500$17.5M2029-12delay - mitigation
The asset renewal programs replace aged and/or degraded transmission line and transmission substation assets. Entergy continuously reviews asset health to prioritize those replacements and the specifi
ENTERGY ARKANSAS, LLC161$16.5M2026-12m1 - proposed
A member cooperative's new 230kV Helena Harbor station will be served on a new, approximately 6-mile 230kV radial line off Entergy's Ritchie 230kV station.
ARKANSAS ELECTRIC COOPERATIVE CORPORATION230$13.2M2028-12m2 - appendix a approved
Rebuild Hilltop – St Joe along with any other station equipment to achieve a 1300 A through path rating.
ENTERGY ARKANSAS, LLC161$12.4M2027-12m1 - proposed
New 3.5 mile transmission line from Wrightsville 115kV
ENTERGY ARKANSAS, LLC115$8.9M2027-04m1 - proposed
A new 3.5 mile 115kV transmission line from Wrightsville 115kV
ENTERGY ARKANSAS, LLC115$8.9M2027-04m1 - proposed
Substation that will serve existing Member Coop load. This substation will tap a new 14-mile line from the new Beebe North SS to the new Nelson SS.
ARKANSAS ELECTRIC COOPERATIVE CORPORATION115$8.0M2028-09m1 - proposed
Rebuild the ~3.1 mile line segment along with any other station equipment to achieve a 1300 A flow-through rating.
ENTERGY ARKANSAS, LLC115$7.9M2027-06m1 - proposed
New 115kV transmission line from the new Nelson SS to the new Sylvania substation.
ARKANSAS ELECTRIC COOPERATIVE CORPORATION115$7.5M2028-09m1 - proposed
New 115kV transmission line from the new Beebe North SS to the new Sylvania 115kV substation.
ARKANSAS ELECTRIC COOPERATIVE CORPORATION115$7.5M2028-09m1 - proposed
Switching Station that will tie into Member Coop's existing 115kV system.
ARKANSAS ELECTRIC COOPERATIVE CORPORATION115$7.0M2028-09m1 - proposed
Switching Station that will tap EAI's Beebe to Garner line.
ARKANSAS ELECTRIC COOPERATIVE CORPORATION115$7.0M2028-09m1 - proposed
Entergy is proposing to build the high-side portion of the substation. This will consist of (3) MOS switches, site, foundation, metering transformers, metering equipment and RTU. Metering, RTU and t
ENTERGY ARKANSAS, LLC161$5.7M2026-03m3 - under construction
Ft Smith 345 kV Ckt 2 Terminal Upgrade
OGE345$5.5M2028-12delay - mitigation
Turk 138/115 kV Transformer Ckt 1 (138 kV)
AEP138$5.3M2027-04delay - mitigation
Entergy will add a new 230kV position to their existing 230kV Ritchie station to accommodate a new radial line.
ARKANSAS ELECTRIC COOPERATIVE CORPORATION230$5.0M2028-12m2 - appendix a approved
North Carolina29 projects · $433M priced · 1 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Rebuild the entire 115kV Line #108 from Boykins to Tunis, approximately 26.5 miles, using current 115kV standard construction practices. The new conductor will have a minimum normal summer rating of 3
Dominion115$72.7M2026-12under construction
Rebuild 12.4 miles of 115 line #126 segment from Earleys to Kelford with a summer emergency rating of 262 MVA. Replace structures as needed to support the new conductor. Upgrade breaker switch 13668 a
Dominion115$50.7M2027-03under construction
Rebuild approximately 14.8 miles of Line 136 between Earleys and Tunis to current 115kV standards. The normal rating of the line conductor will be 393 MVA.
Dominion230,115$50.0M2028-12engineering & procurement
Rebuild approximately 28.9 miles of 230kV Line #2056 Hornertown to Hathaway with current 230kV standard construction practices. The new conductor will have a minimum normal summer rating of 1573 MVA.
Dominion230$49.1M2026-12under construction
Rebuild DEV portion 20.5 miles 2-636 ACSR and Rebuild 17.5 miles 2-636 ACSR between 6GREENVILE T - 6EVERETS 230.0 kV substations. Rating after the upgrade: 1047/1047/1204
Dominion230$39.9M2027-11engineering & procurement
This project serves to wreck and rebuild 115kV line 1031 from structure 1031/220 to structure 1031/329. The existing structures to be removed are primarily single circuit wood, steel or concrete monop
Dominion115$29.4M2029-06engineering & procurement
Rebuild approximately 15.7 miles of 115kV Line #105 Tarboro to normally open switch 96T105 with current 115kV standard construction practices. This includes replacing four COR-TEN® double circuit towe
Dominion115$28.6M2026-05under construction
Line #2114 Elk Run – Gainsville 230 kV: reconductor the line of 21 miles increase its line rating to 1203 MVA (normal), 1203 MVA (emergency), and 1383 MVA (load dump). It is estimated to cost $28,000,
Dominion230$28.0M2019-12Active
Rebuild 115kV Line #1001 (Battleboro – Chestnut) to current 115kV standards with a minimum summer rating of 261 MVA.
Dominion115$14.0M2027-01under construction
Construct a new 230 kV Generation Interconnect Line into the Edgecombe Nug Station. This will involve a total demo and rebuild of the existing Edgecombe Nug Station
Dominion230$10.5M2029-09under construction
Trowbridge 230/115kV substation reconfiguration. 230kV Yard changes: Expand 230kV yard to accommodate additional rung of 230kV breakers. This will require relocation of existing 115kV equipment. Reloc
Dominion230$8.1M2021-06engineering & procurement
Build a three breaker AD1-056/AD1-057 230 kV switching station
Dominion230$7.2M2026-12engineering & procurement
This project provides for the initial construction of a new 230kV three breaker ring substation between transmission structures 2034/220 and 2034/221. The objective of this project is to build a 230kV
Dominion230$6.4M2019-06engineering & procurement
Build a three breaker 230 kV substation at the AD2-160 facility
Dominion230$6.2M2020-12engineering & procurement
Rebuild 115kV Line #1024 (Chestnut –South Justice Branch) to current 115kV standards with a minimum summer rating of 261 MVA.
Dominion115$5.1M2026-06under construction
Re-energize Line 229 and Line 2167 to interconnect Edgecombe 230 kV substation
Dominion230$4.1M2029-09under construction
Add two breakers in the Trowbridge 230 kV Substation to accommodate AD1-074/75/76
Dominion230$4.0M2028-03engineering & procurement
Re-arrange line #269 to loop into and out of the new three breaker AE1-072 230 kV switching station
Dominion230$3.9M2026-06engineering & procurement
Remote protection and communication work. Additional protection and communication work to be required at Cashie, Earleys, and Trowbridge 230 kV substations.
Dominion230$3.4M2019-06engineering & procurement
Re-arrange lines 167, 168, and 2126 and reroute lines 25 and 1020 at Trowbridge substation and route developer transmission line into Trowbridge substation
Dominion230$3.2M2028-03engineering & procurement
Modification of the existing EMC-EMC Mayo-Dunbar delivery point. The newly constructed DP will be adjacent to the existing Mayo-Dunbar DP. Would like to move the tap location one span over on the Domi
Dominion115$1.9M2026-05engineering & procurement
Re-arrange line #2056 to loop into and out of the new three breaker AD1-056/AD1-057 230 kV switching station
Dominion230$1.7M2026-12engineering & procurement
Expand Tar River Substation
Dominion13$1.5M2028-06engineering & procurement
Re-arrange line #2034 to loop into and out of the new three breaker AD1-022/023 230 kV switching station
Dominion230$1.4M2019-06engineering & procurement
Build a three breaker AE1-072 230 kV switching station
Dominion230$1.1M2022-06Active
Massachusetts21 projects · $201M priced · 6 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Separate N12/M13 DCT & reconductor N12 & M13 between Somerset and Bell Rock (~3.5 miles)
National Grid, USA—$101M2027-03planned
Extend the 115 kV 114 line from Eversource/National Grid border to Industrial Park Tap
Eversource115$34.3M2026-12planned
Extend Line 114 - Dartmouth town line (Eversource- NGRID border) to Bell Rock (~4.2 miles)
National Grid, USA—$22.6M2026-12planned
Install one 80 MVAR shunt reactor at the 115 kV Electric Avenue Substation
Eversource115$22.3M2028-12proposed
Replace six 115 kV circuit breakers at Barnstable substation
Eversource115$16.5M2027-11under construction
Protection systems modification associated with the Stoughton RAS at three 345 kV substations (Stoughton, West Walpole and Holbrook) and two 115 kV substations (Hyde Park and K-Street)
Eversource345$3.7M2027-03proposed
Install a POTT protection system on the D-4 line via the A1/B2 lines
National Grid, USA—$0.4M2029-03planned
Upgrade a line relay on 230kV Circuit 23058 (Ritchie – Oak Grove) at Oak Grove Substation
PEPCO230$0.4M2028-05engineering & procurement
Install a second 345/115 kV transformer at the West Barnstable substation
Eversource345—2029-12planned
Upgrade the West Barnstable 345 kV substation to a four bay GIS breaker-and-a-half design
Eversource345—2029-12planned
Construct a new Bourne 345 kV station as a breaker-and-a-half substation
Eversource345—2029-12planned
Install new duct bank, termination stanchions, disconnect switch, CCVTs and other associated station upgrades at the Mystic #250 345 kV substation
Eversource345—2028-05planned
Convert the planned 115 kV Mid-Cape line to 345 kV
Eversource345—2029-12under construction
Install a 115 kV tie line between the existing Mystic 9 Unit 93 terminal and the Mystic substation fence line
Eversource115—2028-03planned
Add a third 115 kV breaker at the 115 kV West Barnstable substation
Eversource115—2029-12planned
Install a new 115 kV three breaker ring bus substation, to be named Quaker St., on NEP’s R-144N line, between NEP’s Millbury Substation and RIE’s Woonsocket Substation, to interconnect QP1320
National Grid, USA115—2026-11under construction
Add a series breaker to the 115 kV Medway Ring #65 Substation
Eversource115—2027-02planned
Install one 115 kV circuit breaker, two 115 kV breaker disconnect switches and other associated substation upgrades at Chelsea #488 substation
Eversource115—2027-08planned
Reconductor the C129S 115 kV line from South Wrentham to Union Street and C181N/D182N 115 kV lines from South Wrentham to Berry Street
National Grid, USA115—2027-07planned
Convert the South Wrentham substation into a five breaker ring bus and upgrades of terminal equipment
National Grid, USA——2027-07planned
Add one bay with two breakers to the existing Electric Ave substation #315
Eversource——2028-05planned
Mississippi19 projects · $598M priced · 5 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
New Green Acres 500/230 kV station will cut in on Lakeover – Ray Braswell 500 kV and Lakeover - McAdams 500 kV lines.
ENTERGY SERVICES, LLC.500$240M2028-12m1 - proposed
New Oak Bend 230 kV station fed from Baxter Wilson 230 kV substation
ENTERGY SERVICES, LLC.230$150M2029-12m1 - proposed
New 230 kV substation fed from 3-230 lines from the Green Acres 500/230 substation
ENTERGY SERVICES, LLC.230$72.0M2029-12m1 - proposed
The asset renewal programs replace aged and/or degraded transmission line and transmission substation assets. Entergy continuously reviews asset health to prioritize those replacements
ENTERGY MISSISSIPPI, LLC.500$68.4M2026-12m1 - proposed
Expand existing 230 kV Andes Substation with three breaker bays with (3) 150 MVA 230/34.5 kV transformers.
ENTERGY SERVICES, LLC.230$40.0M2028-04m1 - proposed
A complete rebuild of Line 4B and line extension to the existing Decatur Substation (Lake – Decatur 69kV) is recommended. This project will increase reliability of the transmission system and provide
SOUTH MISSISSIPPI ELECTRIC POWER ASSOCIATION69$10.4M2027-03m1 - proposed
A complete rebuild of Line 5 and line extension to the existing Decatur Substation (Newton – Decatur 9.7 mi.) is recommended. This project will increase reliability of the transmission system and prov
SOUTH MISSISSIPPI ELECTRIC POWER ASSOCIATION69$6.0M2026-04m1 - proposed
Ensure the McAdams 500 kV station has redundant DC protection.
ENTERGY MISSISSIPPI, LLC.500$4.1M2026-06m1 - proposed
Tap Line 114A (Ellisville - NW Perry 69kV) with a 69kV GOAB and build a new transmission line to the delivery point.
SOUTH MISSISSIPPI ELECTRIC POWER ASSOCIATION69$2.0M2026-10m1 - proposed
Tap the Entergy owned 115kV line (Tylertown - Dexter) with a 115kV switching station and build a new transmission line to the delivery point.
SOUTH MISSISSIPPI ELECTRIC POWER ASSOCIATION115$1.9M2026-12m1 - proposed
Tap the Entergy owned 115kV line (Tylertown - Dexter) with a 115kV switching station.
SOUTH MISSISSIPPI ELECTRIC POWER ASSOCIATION115$0.9M2026-12m1 - proposed
A complete rebuild of Line 35A (Benndale – Benndale GT 69kV) is recommended at 161kV insulation with more reliable structural designs and OPGW. This project will increase reliability of the transmissi
SOUTH MISSISSIPPI ELECTRIC POWER ASSOCIATION69$0.9M2028-06m1 - proposed
A complete rebuild of Line 74B (Colonial Collins – Colonial Kola 0.77 mi.) is recommended at 161kV insulation with more reliable structural designs and OPGW.
SOUTH MISSISSIPPI ELECTRIC POWER ASSOCIATION69$0.9M2027-01m1 - proposed
A complete rebuild of Line 5 and line extension to the existing Decatur Substation (Newton – Decatur 9.7 mi.) is recommended. This project will increase reliability of the transmission system and prov
SOUTH MISSISSIPPI ELECTRIC POWER ASSOCIATION69$0.1M2026-04m1 - proposed
Tap Line 114A (Ellisville - NW Perry 69kV) with a 69kV GOAB.
SOUTH MISSISSIPPI ELECTRIC POWER ASSOCIATION69$0.1M2026-10m1 - proposed
2x 500/230 autotransformers at Baxter Wilson 500/230 station
ENTERGY SERVICES, LLC.500$0.0M2029-12m1 - proposed
2-500/230 Autotransformers install at new Green Acres 500/230 station.
ENTERGY SERVICES, LLC.500$0.0M2028-12m1 - proposed
new Baxter Wilson 230 kV station fed from existing Baxter Wilson 500 kV through 2-500/230 kV auto transformers.
ENTERGY MISSISSIPPI, LLC.230$0.0M2029-12m1 - proposed
3-230 kV lines connecting Green Acres - County line
ENTERGY SERVICES, LLC.230$0.0M2029-12m1 - proposed
Maine9 projects · $58.1M priced · 1 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Convert the Highland 115 kV substation to an eight breaker, breaker-and-a-half configuration with a bus connected 115/34.5 kV transformer
Central Maine Power Company115$26.3M2028-12planned
Install a +50/-25 MVAR synchronous condenser at Highland 115 kV substation
Central Maine Power Company115$17.5M2029-12planned
Replace six 115 kV circuit breakers at Larrabee Road substation
Central Maine Power Company115$5.5M2028-12planned
Install a 15 MVAR capacitor at Belfast 115 kV substation
Central Maine Power Company115$5.3M2029-12planned
Install a new 80 MVAR reactor, reconfigure the existing two reactors at the 345 kV Orrington substation
Versant Power345$3.5M2026-12under construction
Install a 115 kV three-breaker ring bus on CMP Section 80, approximately 2 miles from Highland Station
Central Maine Power Company115—2028-05planned
Install two static 10 MVAR, 115 kV shunt capacitor blocks, with necessary switchgear, at the Dogtown 115 kV bus.
Central Maine Power Company115—2029-11planned
Addition of a new 115 kV Three Rivers Switching Station on line 93 between Bull Hill and Deblois
Versant Power115—2026-08under construction
Replace structure to increase the Summer Long Time Emergency rating of the 6.5 mile 82-2 segment of 115 kV line Section 82, from Detroit to the Section 82A Tap
Central Maine Power Company115—2029-11planned
NA9 projects · $41.8M priced · 1 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Install a second 650 MVA TX at Nashua
KCPL—$22.8M2028-06on schedule > 4
Ren-Williston 115 kV Ckt 1 Rebuild
BEPC115$8.6M—on schedule < 4
Mark Moore 345/115 kV Transformer (DISIS-2017-002)
NPPD345$8.3M—on schedule > 4
SPA Brown to Brown 138 kV Terminal Equipment Upgrade (DISIS-2017-002)
SWPA138$0.8M—on schedule < 4
Rebuild the circuit from WAPA Denison to the new 69 kV tap station (WAPA)
WAPA69$0.8M—identified
Ren 115 kV Ckt 1 Terminal Upgrade
BEPC115$0.4M—on schedule < 4
Terminal upgrades on the Road Ridge to Nashua 161 kV line 1
KCPL161$0.1M—on schedule > 4
Terminal upgrades at Clinton (owned by AECI)
AECI———on schedule < 4
GEN-2016-087 Interconnection (Non-Shared NU) (WAPA)
WAPA——2026-08identified
Vermont7 projects · — priced · 3 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
New 1000 MW 320 kV HVDC Line, complete with two HVDC terminal stations, from a HQ station near Monteregie substation in Quebec to the VELCO 345/115 kV Coolidge substation in VT
Vermont Electric Power Company345—2027-12planned
Add two 345 kV circuit breakers at the Coolidge 345 kV substation
Vermont Electric Power Company345—2027-12planned
Reconductor VELCO's section of the 381 (Vernon - Northfield) 345 kV line
Vermont Electric Power Company345—2027-12planned
Reconductor the K27 (Williston - Tafts Corner) 115 kV line
Vermont Electric Power Company115—2027-12planned
Reconductor the K43 (New Haven - Williston) 115 kV line
Vermont Electric Power Company115—2027-12planned
Replace a line drop for the K30 (Middlebury - Florance) 115 kV line
Vermont Electric Power Company115—2027-12planned
Expand bus work and add a 115 kV breaker to connect QP 807 Solar PV project to the Vergennes 115 kV Substation.
Vermont Electric Power Company115—2028-10planned
Connecticut5 projects · $21.8M priced · 2 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Old Town 115/13.8 kV Substation Rebuild
United Illuminating Company—$21.8M2030-04under construction
Installation of a new 345 kV, 3-breaker ring bus switchyard in East Granby
Eversource345—2027-10planned
Installation of a new 345 kV, 3-breaker ring bus switchyard on the line 3419 in Ellington, CT
Eversource345—2028-10planned
Addition of a 115 kV 3-breaker ring-bus switchyard on the 1316 Line between Canterbury substation and Tunnel substation
Eversource115—2029-05planned
Addition of a 115 kV disconnect switch at Devon substation and other supporting substation equipment
Eversource115—2028-10planned
Nevada4 projects · — priced · 0 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Gamebird 230/138 kV Transformer Upgrade
VEA/GLW230——approved
Beatty 230 kV Project
VEA/GLW230—2028-05permitting, engineering and design
GLW/VEA area upgrades - revised scope
VEA/GLW——2028-06permitting, engineering and design
Tie line Phasor Measurement Units
VEA——2025-12in flight
New Hampshire3 projects · — priced · 1 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Reconductor ES's section of the 381 (Vernon - Northfield) 345 kV line. (NH portion)
Eversource345—2027-12planned
Uprate the N186 (Vernon Road Tap - Chestnut Hill) 115 kV line
Eversource115—2027-12planned
Uprate the A152 (Chestnut Hill - Westport - A152 Tap) 115 kV line
Eversource115—2027-12planned
VI3 projects · $1.6M priced · 0 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Upgrade the existing Berry Hill 138 kV Station
AEP138$1.4M—engineering & procurement
Review and update the line relay settings
AEP138$0.1M—engineering & procurement
Review and update the line relay settings Axton 138 kV Station
AEP138$0.1M—engineering & procurement
na3 projects · $63.4M priced · 0 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Build Second 345-115kV transformer at Antelope
NPPD115$33.5M—identified
Rebuild SWEETWT6 to CHISHOLM6 230 kV Line 1
AEP230$25.9M—identified
Rebuild Columbus SE to G19-039-TAP 115 kV
NPPD115$4.0M—identified
Rhode Island2 projects · — priced · 0 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Construct new 115 kV Switching Station in North Kingstown
Rhode Island Energy115—2028-12planned
Replace one 115 kV circuit breaker at the Woonsocket substation
Rhode Island Energy115—2026-06under construction
Tennessee2 projects · $8.7M priced · 0 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
At Hill station, replace existing 69 KV circuit breaker H with new 40 KA 3000A circuit breaker. Replace existing 69 KV circuit breaker E with new 40 KA 3000A circuit breaker for constructability flexi
AEP138$6.7M2027-10engineering & procurement
Remote end relaying work at Clinch River, Wolf Hills, Lovedale, Holston, West Kingsport.
AEP138$2.0M2027-11engineering & procurement
Montana1 projects · $4.0M priced · 0 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Williston 230 kV Ckt 1 Terminal Upgrade
BEPC230$4.0M2032-12delay - mitigation
Wyoming1 projects · $597M priced · 1 at 345 kV+
ProjectOwnerkVCostIn serviceStatus
Wyoming Border - St. Germaine 345 kV Ckt 1 New Line (BEPC)
BEPC345$597M2034-10on schedule < 4

Grid-operator plans list what transmission owners intend to build; dates slip and scopes change, so confirm a project's status with its owner. Interconnection network upgrades assigned to a specific new load are decided in that load's own study and are not in these plans.