ERCOT grid congestion & captive power

When a transmission line binds, generation on the trapped side gets curtailed — that underutilized “captive” power is exactly what a co-located datacenter can absorb, often with a faster interconnection than a greenfield build (the constraint relief a new load provides is already valued). These are the 78 most-constrained points in the ERCOT grid, ranked by how often they bind and how expensive relief gets, from 8,820 priced SCED intervals.

How to read this: a high binding count means the pinch point recurs; a high shadow price ($/MW to relieve) means it's expensive, i.e. severely constrained. Most sit on 138 kV lines in South & West Texas (the Rio Grande / Laredo corridor) — the parts of ERCOT where trapped generation is most concentrated today.
#ConstraintCorridorBindsMax $/MWAvg $/MW
1FORTMA_YELWJC1_1YELWJCKTFORTMA138 kV413$881$146
2LARDVN_LOBO2_1LOBOLARDVNTH138 kV766$422$115
3587__AARGYLLWSVH138 kV339$942$377
4BRUNI_69_1BRUNIBRUNI138 kV119$2,600$723
5ASHERT_CATARI1_1ASHERTONCATARINA138 kV332$905$106
6BR_HOC09_ABRHOC138 kV302$920$112
7943__BENWSWSHKSW138 kV50$3,500$289
8HAINE__LA_PAL1_1LA_PALMAHAINE_DR138 kV368$419$151
93180__AFCRSWCDHSW138 kV83$1,311$461
10ATSO_SONR1_1SONRATSO69 kV442$245$115
11FREER_LOBO1_1LOBOFREER69 kV114$936$285
12HON_DEVI_1HONDOCKDEVINESW69 kV139$545$245
13651__BCMNSWCMNTP138 kV211$348$72
14THWZEN71_AZENTHW345 kV478$131$44
156965__ALNGSWPRLSW345 kV283$181$106
16CELANE_KLEBER1_1CELANEBIKLEBERG138 kV183$245$83
1735055__ASAMSWVENSW345 kV174$235$113
18GREENL_WEAVER1_1WEAVERRDGREENLK69 kV13$2,728$393
19MADDUX_SAPOWE1_1MADDUXSAPOWER138 kV236$134$44
20UVALDE503$56$14
21HHGTOM_1HHGTOMEGA345 kV279$83$59
22SOLSTICE_PST1SOLSTICESOLSTICE138 kV119$195$38
23NELRIO381$59$13
24VAN_VNDB_1VANBLTSSVANBLT6969 kV74$301$91
25NE_LOB445$45$18
26PALOUS_WOLFCA1_1PALOUSEWOLFCAMP138 kV84$233$73
27BLESSING_1382BLESSINGBLESSING345 kV144$133$34
28450__ASNDSWAUSTRO345 kV198$89$23
29122T122_1COMFORRAYBAR138 kV10$1,541$1,138
30NLARSW_PILONC1_1PILONCILNLARSW138 kV51$291$92
31I_KALO125$86$30
32E_PASP55$109$48
33I_DUPS_RESNIK1_1I_DUPSWRESNIK138 kV99$56$14
3440T189_1FERGUSWIRTZ138 kV149$37$10
356325__DLTVSBGRDPR138 kV8$433$195
3635065__AFVLSWFTSSW345 kV67$46$35
37MAXWEL_WHITIN1_1MAXWELLWHITING138 kV47$66$23
38BALLIN_PAINTR1_1BALLINGEPAINTROC69 kV2$1,566$1,509
39HEC_NEDIN2_1HECNEDIN138 kV166$18$7
4035045__ASAMSWFVLSW345 kV64$46$13
41109__AEXCSWRNKSW345 kV48$59$32
42BAKRFLD_CEDCAN_1CEDACABAKESW345 kV40$55$18
43BLASCOFE_RC_1BLASWCOFESSRC138 kV26$83$7
44PANTER_WESMER1_1WESMERPANTERA138 kV17$122$101
45SND_ORAN_1ORNGROVSNDIEGS69 kV12$177$135
46MLB_SLR_TLINE_1MLB_SLRQUASAR345 kV36$57$44
47E_PATA16$113$40
48MCCAMY65$24$3
49VERTRE_WESLAU1_1WESLAUVERTREES138 kV13$112$91
506945__AMGSESCATSW345 kV18$82$31

Dataset updated . Screening estimates derived from public data sources.

Derived from ERCOT SCED binding-constraint disclosures (shadow prices & overloaded elements). Station codes are ERCOT electrical buses; precise site-level mapping and non-ERCOT ISOs (CAISO, SPP) are on the roadmap. A screening signal of where captive power sits — confirm deliverable capacity with an interconnection study. Statewide ERCOT.