Which utilities want your load — and on what terms
A perfect site still dies on the utility. This is how 87 utilities that matter for large load treat a datacenter: their posture, the MW threshold where special terms begin, and — for the 20 with a public large-load tariff or order — the minimum take, contract term and collateral that follow. Every site page and vet shows the entry for the utility that serves the point; Watchtower emails when an entry changes. As of 2026-09-18.
| Utility | Posture | Speed | Terms from | Min take | Term | Tariff / order |
|---|---|---|---|---|---|---|
AEP Texas / TNMP (ERCOT) ERCOT connect-and-manage; SB 6 obligations above 75 MW. South Texas 138 kV corridor is the most-congested part of ERCOT — captive power sits here. | favorable | fast | 75 MW | — | — | SB 6 large-load provisions (≥75 MW) interconnection cost-sharing; curtailment acceptance Texas SB 6 (2025) · statute · verify |
AES Indiana Indianapolis; IURC-approved large-load terms; Indiana DC incentives. | favorable | medium | 100 MW | — | — | no public large-load tariff on record — state posture applies |
Alabama Power Southern Co. subsidiary; supportive PSC, fast vertically integrated interconnection. | favorable | fast | 100 MW | — | — | no public large-load tariff on record — state posture applies |
Alliant Energy (WI / IA) Supportive; Iowa large-load contracts (Meta Altoona, Google Council Bluffs via MidAmerican). | favorable | medium | 100 MW | — | — | no public large-load tariff on record — state posture applies |
Big Rivers co-ops (KY) Western Kentucky; Big Rivers G&T marketing surplus capacity to large loads. | favorable | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Black Hills Energy (SD / WY / CO) Wyoming and South Dakota supportive; small system, capacity additions needed for large loads. | favorable | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
CenterPoint Houston (ERCOT) ERCOT connect-and-manage; SB 6 obligations above 75 MW; Houston-area 138/345 kV capacity is being built out for large load. | favorable | fast | 75 MW | — | — | SB 6 large-load provisions (≥75 MW) interconnection cost-sharing; curtailment acceptance Texas SB 6 (2025) · statute · verify |
City Utilities of Springfield (MO) Municipal with own generation; SPP; supportive. | favorable | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Cleco (LA) Louisiana supportive (Meta Richland precedent); MISO South. | favorable | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Consumers Energy (MI) Michigan 2025 DC sales/use-tax exemption; large-load contracts with minimum take; MISO. | favorable | medium | 100 MW | — | 15 yr | Large-load contract terms; MI DC sales/use-tax exemption (2025) contract-specific · exit: contract-specific MPSC U-21585 (2025) · approved · verify |
CPS Energy (San Antonio) Municipal ERCOT utility actively contracting large load; SB 6 applies above 75 MW. | favorable | fast | 75 MW | — | — | no public large-load tariff on record — state posture applies |
Dominion Energy South Carolina SC PSC supportive; SERC interconnection. | favorable | medium | 100 MW | — | — | no public large-load tariff on record — state posture applies |
DTE Electric (MI) Michigan DC tax exemption; DTE contracting multi-GW hyperscale (Saline Township); MISO. | favorable | medium | 100 MW | — | 15 yr | Large-load contract terms; MI DC tax exemption (2025) contract-specific · exit: contract-specific MPSC U-21860 (2025) · approved · verify |
Duke Energy Indiana Indiana courting DCs (Amazon New Carlisle, Google Fort Wayne); IURC large-load contract terms. | favorable | medium | 100 MW | — | — | no public large-load tariff on record — state posture applies |
Duquesne Light (Pittsburgh) Pittsburgh region courting DCs (Homer City redevelopment nearby); PJM queue is the constraint. | favorable | slow | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Entergy (AR / MS / TX) Vertically integrated, courting hyperscale (AWS Mississippi, Google Arkansas); MISO South interconnection. | favorable | fast | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Entergy Louisiana Meta Richland Parish (2+ GW) approved with dedicated gas generation; LPSC supportive; large-load contracts carry minimum bills. | favorable | fast | 50 MW | — | 15 yr | Large-load contracts with dedicated generation (Meta Richland Parish) minimum bills covering new generation · exit: contract-specific LPSC U-37425 (Aug 2025) · approved · verify |
Evergy (KS / MO) Large Load Power Service tariff (≥75 MW) approved 2025; Kansas/Missouri incentives; Meta Kansas City. | favorable | medium | 75 MW | 80% | 12 yr | Large Load Power Service (LLPS, ≥75 MW) security proportional to contract demand · exit: minimum bill through term KCC 25-EKCE-207-TAR / MO PSC (2025) · approved · verify |
Florida Power & Light Large-load contract service tariff (2025) for ≥50 MW with minimum bills; FL PSC supportive; fast build-out. | favorable | fast | 50 MW | 90% | 20 yr | Large Load Contract Service (LLCS, ≥50 MW) security for stranded-cost protection · exit: minimum bill through term FL PSC 20250011-EI (2025 rate case) · approved · verify |
Georgia Power Actively courting large load; PSC 2025 rules let ≥100 MW customers carry their own generation/transmission costs under long-term contracts. Fast vertically integrated interconnection. | favorable | fast | 100 MW | — | 15 yr | PSC large-load rules (≥100 MW): direct-pay contracts customer bears generation/transmission cost under contract · exit: contract-specific GA PSC Docket 55378 (Jan 2025 rules) · approved · verify |
Grand River Dam Authority (OK) State authority serving Google Pryor; actively courting large load. | favorable | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Grant County PUD (WA) Hydro-rich public utility; Quincy DC cluster; large-load rate schedule with new-load surcharge. | favorable | medium | 20 MW | — | — | no public large-load tariff on record — state posture applies |
Idaho Power Large-load Schedule 20 (≥20 MW) with contract terms; Meta Kuna; cheap hydro. | favorable | medium | 20 MW | — | — | Schedule 20 (≥20 MW speculative high-density load) security; curtailment provisions IPUC IPC-E-24-07 (2025) · approved · verify |
JEA (Jacksonville) Municipal; Jacksonville courting DCs; large-load contracts with minimum bills. | favorable | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
MidAmerican Energy (IA) Berkshire utility with deep wind; long history with Google/Meta/Microsoft in Iowa. | favorable | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Mississippi Power Southern Co.; SERC; supportive. | favorable | fast | 100 MW | — | — | no public large-load tariff on record — state posture applies |
Montana-Dakota Utilities (ND / SD / MT) North Dakota actively courting DCs (Applied Digital); MISO/SPP seams; cheap power, cold climate. | favorable | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Nebraska public power All-public-power state; OPPD/NPPD serve Meta, Google, Microsoft in the Omaha corridor; SPP. | favorable | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
NIPSCO GenCo structure to serve data centers with dedicated generation; northern Indiana is an active hyperscale cluster. | favorable | medium | 100 MW | — | — | no public large-load tariff on record — state posture applies |
NorthWestern Energy (MT / SD) Montana courting DCs (2025 tax law) and NorthWestern has proposed large-load tariffs; cold climate, cheap land; transmission is the limit. | favorable | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
NV Energy Clean Transition Tariff for large loads; northern Nevada (Reno/TRIC) actively developed. | favorable | medium | 100 MW | — | — | Clean Transition Tariff (large loads) contract-specific · exit: contract-specific PUCN 24-05007 (2025) · approved · verify |
Oncor (ERCOT) ERCOT connect-and-manage; ~1.5–3 yr to energize. SB 6 (2025): ≥75 MW loads accept emergency curtailment and interconnection cost-sharing; Oncor reports 100+ GW of large-load requests. | favorable | fast | 75 MW | — | — | ERCOT connect-and-manage + SB 6 large-load provisions (≥75 MW) interconnection cost-sharing; ERCOT emergency curtailment acceptance Texas SB 6 (2025); PUCT rulemaking 2026 · statute · verify |
PPL Electric (PA) Pennsylvania courting DCs (Amazon Susquehanna); PPL has 10+ GW of large-load requests; PJM queue is the constraint. | favorable | slow | 100 MW | — | — | Large-load tariff proposal (≥100 MW): minimum take, collateral proposed · exit: proposed PA PUC (2025–26 large-load proceeding) · pending · verify |
PSO / OG&E (Oklahoma) SPP; Oklahoma courting DCs (Google Pryor, Stillwater); large-load contracts. | favorable | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Rocky Mountain Power (PacifiCorp UT / WY / ID) Utah 2025 large-load law lets DCs contract directly for generation; Wyoming supportive. | favorable | medium | 100 MW | — | — | no public large-load tariff on record — state posture applies |
Santee Cooper State-owned; actively marketing large-load capacity. | favorable | fast | 100 MW | — | — | no public large-load tariff on record — state posture applies |
Tampa Electric / Duke Florida Supportive PSC; large-load provisions with minimum bills. | favorable | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Texas co-ops (ERCOT) ERCOT connect-and-manage applies through the co-op's TSP; SB 6 above 75 MW; several (Pedernales, CoServ) sit in fast-growing corridors. | favorable | fast | 75 MW | — | — | no public large-load tariff on record — state posture applies |
TVA Federal power authority courting DCs (xAI Memphis); large loads pay infrastructure costs above 50 MW; fast. | favorable | fast | 50 MW | — | — | no public large-load tariff on record — state posture applies |
TVA distributors (TN co-ops & munis) TVA large-load provisions apply; TVA distributors host xAI, Meta and Google projects. | favorable | fast | 50 MW | — | — | no public large-load tariff on record — state posture applies |
TVA local power companies TVA distributors; TVA large-load provisions apply. | favorable | fast | 50 MW | — | — | no public large-load tariff on record — state posture applies |
We Energies (WI) Microsoft Mount Pleasant; very-large-customer tariff with minimum bills; MISO. | favorable | medium | 100 MW | — | 10 yr | Very Large Customer (VLC) tariff security + minimum bills · exit: minimum bill through term PSCW 5-UR-110 (2025) · approved · verify |
WEC Energy (WPS / UPPCO) WEC subsidiaries; Wisconsin supportive (Microsoft, Meta); UP of Michigan less so. | favorable | medium | 100 MW | — | — | no public large-load tariff on record — state posture applies |
West Virginia (Black Diamond / Mon Power) West Virginia 2025 HB 2014 microgrid/DC law; supportive PSC; PJM interconnection is the constraint. | favorable | slow | 50 MW | — | — | no public large-load tariff on record — state posture applies |
AEP Ohio PUCO-approved data-center tariff: ≥25 MW loads pay for 85% of contracted demand for up to 12 years, with exit fees; incentive pause in 2026. | moderate | slow | 25 MW | 85% | 12 yr | Data Center Tariff (≥25 MW) proof of financial viability + exit fees · exit: up to remaining minimum charges PUCO 24-508-EL-ATA, approved July 2025 · approved · verify |
AES Ohio PJM; Ohio large-load tariff terms; Dayton/Central Ohio DC growth. | moderate | slow | 25 MW | — | — | no public large-load tariff on record — state posture applies |
Ameren Missouri Large primary service tariff with minimum demand for ≥100 MW; MISO interconnection. | moderate | medium | 100 MW | — | — | no public large-load tariff on record — state posture applies |
Appalachian Power (AEP, VA / WV) AEP large-load tariff model (minimum demand, exit fees); West Virginia 2025 microgrid/DC law is favorable. | moderate | slow | 70 MW | — | — | no public large-load tariff on record — state posture applies |
APS / SRP (Arizona) Massive Phoenix DC cluster; large-load tariffs and water scrutiny; 2026 legislative limits on exemptions. | moderate | medium | 100 MW | — | — | no public large-load tariff on record — state posture applies |
Austin Energy Municipal; ERCOT interconnection but city climate goals and rate design scrutiny for large loads. | moderate | fast | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Avangrid (CMP / Versant / NYSEG / RG&E) Avangrid/Iberdrola; NY and Maine large-load requests need PSC-supervised studies; Micron cluster is in National Grid territory, not here. | moderate | slow | 25 MW | — | — | no public large-load tariff on record — state posture applies |
Avista (WA / ID) Vertically integrated; Spokane-area interest; Washington CETA constraints; capacity-constrained but faster than the coast. | moderate | medium | 25 MW | — | — | no public large-load tariff on record — state posture applies |
CenterPoint Indiana (SIGECO) Evansville area; MISO; large-load contract terms with minimum bills. | moderate | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Central Hudson (NY) Hudson Valley; NYISO; PSC-supervised large-load studies. | moderate | slow | 25 MW | — | — | no public large-load tariff on record — state posture applies |
Colorado Springs Utilities Municipal; WECC; large-load contracts case by case. | moderate | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
ComEd / Ameren Illinois Illinois DC sales-tax exemption; ComEd (PJM) capacity prices and PJM queue slow large-load energization. | moderate | slow | 100 MW | — | — | no public large-load tariff on record — state posture applies |
Dominion Energy Virginia GS-5 large-load rate (≥25 MW): ~14-year contract, minimum demand charges and collateral; largest DC market in the world but PJM interconnection is the slowest in the US and Dominion has a multi-GW connection backlog. | moderate | slow | 25 MW | 85% | 14 yr | Schedule GS-5 (large general service, ≥25 MW) ~$1.5M/MW security or equivalent · exit: minimum-demand charges survive early termination VA SCC PUR-2024-00187 (2025 biennial review); effective 2027 · approved · verify |
Duke Energy Carolinas / Progress Large-load tariff with minimum-take and contract terms; NC/SC PSCs supportive but Duke's interconnection queue for load is growing fast. | moderate | medium | 100 MW | — | 10 yr | Large Load Customer terms (≥100 MW): minimum bills, contract demand contract-specific security · exit: contract-specific NCUC E-7/E-2 large-load provisions (2025) · approved · verify |
Duke Energy Ohio / Kentucky Cincinnati region; PJM; Ohio large-load tariff terms comparable to AEP Ohio. | moderate | slow | 25 MW | — | — | no public large-load tariff on record — state posture applies |
El Paso Electric / PNM WECC; New Mexico DC projects growing; water and transmission constraints. | moderate | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Eversource (CT / MA / NH) ISO-NE; high rates and capacity prices; Connecticut and Massachusetts offer DC incentives (CT 2024 law) but interconnection is study-heavy. | moderate | slow | 50 MW | — | — | no public large-load tariff on record — state posture applies |
EWEB (OR) Municipal; Oregon POWER Act large-load class applies. | moderate | medium | 20 MW | — | — | no public large-load tariff on record — state posture applies |
Exelon Maryland / DC (BGE, Pepco, Delmarva) PJM; Maryland Next Generation Energy Act (2025) adds large-load obligations; Frederick/Quantum Loophole cluster. | moderate | slow | 25 MW | — | — | Next Generation Energy Act large-load provisions per statute · exit: per statute MD HB 1035 (2025) · statute · verify |
FirstEnergy (OH / PA / WV / MD) PJM; Ohio data-center tariff obligations mirror AEP Ohio; Pennsylvania/West Virginia legs supportive. | moderate | slow | 25 MW | — | — | no public large-load tariff on record — state posture applies |
Green Mountain Power (VT) Small system, ISO-NE, renewable mandates; limited large-load headroom. | moderate | slow | 25 MW | — | — | no public large-load tariff on record — state posture applies |
Imperial Irrigation District (CA) Own balancing authority outside CAISO; geothermal/solar; limited transmission headroom. | moderate | medium | 25 MW | — | — | no public large-load tariff on record — state posture applies |
Indiana Michigan Power (AEP) Large-load tariff (≥70 MW): 80% minimum demand for 12 years, exit fees — the AEP Ohio model. | moderate | medium | 70 MW | 80% | 12 yr | Large Load / Industrial Power tariff (≥70 MW) financial security keyed to contract demand · exit: 3-year exit notice + remaining minimums IURC 45925 (settlement approved Feb 2025) · approved · verify |
LG&E / KU (Kentucky) Kentucky 2025 DC incentives; large-load contracts; SERC. | moderate | medium | 100 MW | — | — | no public large-load tariff on record — state posture applies |
Minnesota Power Northern Minnesota; MISO; industrial base; Minnesota large-load statute applies. | moderate | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
National Grid (upstate NY) Upstate NY hydro and Micron cluster; NYISO interconnection and state siting rules; statewide moratorium proposal pending. | moderate | slow | 20 MW | — | — | no public large-load tariff on record — state posture applies |
New Jersey IOUs (PSE&G / JCP&L / ACE) PJM capacity-price shock drove 2025 rate hikes; BPU scrutiny of large loads; NJ DC incentive program. | moderate | slow | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Old Dominion co-ops (NOVEC / REC / Choptank) NOVEC serves part of Loudoun's DC corridor; ODEC-supplied co-ops; PJM/Dominion transmission is the constraint. | moderate | slow | 25 MW | — | — | no public large-load tariff on record — state posture applies |
PacifiCorp (OR / UT / WY) Oregon POWER Act (2025) puts large loads in their own rate class; Utah and Wyoming supportive. | moderate | medium | 100 MW | — | — | no public large-load tariff on record — state posture applies |
PECO (PA) PJM; Philadelphia-area capacity tight; large-load provisions. | moderate | slow | 100 MW | — | — | no public large-load tariff on record — state posture applies |
Portland General Electric Oregon POWER Act: large-load customers pay full cost; Hillsboro cluster capacity-constrained. | moderate | slow | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Puget Sound Energy Washington CETA obligations; large-load tariff in development; Quincy/Grant County PUD is the DC hub instead. | moderate | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
SMUD Municipal; lower rates than PG&E; Sacramento-area DCs exist; 2030 zero-carbon goal shapes terms. | moderate | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Southern California Edison CAISO; Inland Empire cluster; large-load studies and CPUC oversight slow energization; strong incentives absent. | moderate | slow | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Tucson Electric / UNS Arizona; Tucson-area DC projects (Project Blue) drew local opposition and water scrutiny in 2025. | moderate | medium | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Washington PUDs & munis Cheap hydro but large-load caps and new-load rate schedules (Chelan, Douglas, Grant); BPA transmission is the constraint; CETA obligations. | moderate | medium | 20 MW | — | — | no public large-load tariff on record — state posture applies |
Xcel Energy (MN / WI / TX-NM via SPS) Minnesota 2025 large-load law: DCs pay their own way, no cost shift; Xcel building for Meta/Microsoft. | moderate | medium | 100 MW | — | — | Minnesota large-load statute (2025): DCs pay own costs, no cross-subsidy per-contract · exit: per-contract MN HF 16 (2025 special session) · statute · verify |
Xcel Energy Colorado Large-load tariff filed; WECC vertically integrated; water and clean-energy mandates shape terms. | moderate | medium | 100 MW | — | — | no public large-load tariff on record — state posture applies |
Con Edison (NYC) NYISO Zone J: constrained transmission, highest delivery rates in the US, and New York's DC moratorium bill; captive power exists but siting is hard. | restrictive | slow | 20 MW | — | — | Standby / large-load service; NYISO Zone J n/a NY PSC; statewide DC moratorium bill pending (2026) · pending · verify |
Hawaiian Electric Islanded grid, highest US rates; no large-load headroom. | restrictive | slow | 10 MW | — | — | no public large-load tariff on record — state posture applies |
LADWP Municipal, capacity-constrained, long interconnection lead times. | restrictive | slow | 25 MW | — | — | no public large-load tariff on record — state posture applies |
Pacific Gas & Electric (CA) CAISO permitting friction, Rule 30 large-load interconnection with long lead times, high delivery rates; PG&E has a multi-GW data-center pipeline but energization dates run 2028+. | restrictive | slow | 50 MW | — | — | no public large-load tariff on record — state posture applies |
San Diego Gas & Electric Highest retail rates in the continental US; little large-load headroom. | restrictive | slow | 50 MW | — | — | no public large-load tariff on record — state posture applies |
Co-ops, municipals and public power — state defaults
Where no utility above serves a site, the co-op, municipal or public-power district inherits the state's transmission reality and the generation-and-transmission cooperative that supplies most of them. Coarser than a curated entry and shown as “state default” on the site; add a named entry when a specific utility matters.
| State | Utility type | Posture | Speed | Why |
|---|---|---|---|---|
| AK | cooperative | restrictive | slow | Railbelt and village co-ops; islanded, high cost. |
| AL | cooperative | favorable | fast | PowerSouth / TVA supplied; supportive state. |
| AR | cooperative | favorable | medium | Arkansas Electric Cooperative Corp; supportive state (Google). |
| AZ | cooperative | moderate | medium | AEPCO members; water and transmission limits. |
| CA | cooperative | moderate | slow | Small California co-ops; CAISO. |
| CA | municipal | moderate | medium | California munis (Anaheim, Riverside, Pasadena): lower rates than IOUs, limited headroom. |
| CA | political subdivision | moderate | medium | California irrigation/utility districts; outside CAISO in places. |
| CO | cooperative | moderate | slow | Tri-State G&T members; contract and exit-fee friction; WECC transmission constrained. |
| FL | cooperative | favorable | medium | Seminole Electric members; supportive state. |
| FL | municipal | favorable | medium | FMPA munis; supportive. |
| GA | cooperative | favorable | fast | Oglethorpe/Georgia Transmission EMCs; GA PSC large-load rules apply. |
| IA | cooperative | favorable | medium | Iowa co-ops (CIPCO, Corn Belt); supportive state. |
| ID | cooperative | favorable | medium | Idaho supportive; BPA/Idaho Power supplied. |
| IL | cooperative | moderate | medium | Downstate co-ops (Southern Illinois Power, Prairie Power) in MISO; Illinois DC tax exemption. |
| IN | cooperative | favorable | medium | Hoosier / Wabash Valley members; supportive state. |
| KS | cooperative | favorable | medium | Sunflower / KEPCo; SPP; Kansas incentives. |
| KY | cooperative | moderate | medium | East Kentucky Power Cooperative members; Kentucky 2025 DC incentives; limited transmission in the east. |
| LA | cooperative | favorable | medium | Louisiana supportive; MISO South. |
| MD | cooperative | moderate | slow | SMECO / Choptank; PJM; Maryland Next Generation Energy Act. |
| MI | cooperative | favorable | medium | Wolverine members; Michigan DC tax exemption. |
| MN | cooperative | moderate | medium | Great River Energy / Minnkota members; Minnesota large-load statute. |
| MO | cooperative | favorable | medium | Associated Electric Cooperative members; supportive state. |
| MS | cooperative | favorable | medium | Cooperative Energy / TVA supplied; supportive state (AWS). |
| MT | cooperative | favorable | medium | Basin members; Montana 2025 DC law. |
| MT | not available | favorable | medium | Montana; supportive state. |
| NC | cooperative | moderate | medium | NC EMCs supplied by Duke; large-load contracts case by case. |
| ND | cooperative | favorable | medium | Basin Electric / Minnkota; North Dakota courting DCs. |
| NE | not available | favorable | medium | Nebraska public power; supportive. |
| NE | political subdivision | favorable | medium | Public power districts supplied by NPPD; supportive state. |
| NM | cooperative | moderate | slow | Tri-State members; sparse transmission. |
| NV | political subdivision | favorable | medium | Nevada supportive; power districts supplied via NV Energy/CRC. |
| NY | municipal | moderate | slow | NYPA-allocated munis; NYISO constraints. |
| OH | cooperative | moderate | slow | Buckeye Power members; Ohio large-load tariff climate; PJM. |
| OK | cooperative | favorable | medium | Western Farmers / KAMO; SPP; supportive state. |
| OR | cooperative | moderate | medium | BPA-supplied; Oregon POWER Act. |
| PA | cooperative | moderate | slow | Allegheny Electric Cooperative members; PJM queue; rural. |
| SC | cooperative | favorable | medium | Central Electric / Santee Cooper supplied; supportive. |
| SD | cooperative | favorable | medium | East River / Basin; supportive. |
| TN | cooperative | favorable | fast | TVA distributors; TVA large-load provisions. |
| TN | municipal | favorable | fast | TVA distributors; TVA large-load provisions. |
| TX | cooperative | favorable | fast | ERCOT connect-and-manage through the co-op's TSP (Oncor/AEP/CenterPoint); SB 6 above 75 MW. Panhandle co-ops are SPP. |
| TX | municipal | favorable | fast | ERCOT municipal; SB 6 above 75 MW. |
| UT | cooperative | favorable | medium | Utah 2025 large-load law; Deseret members. |
| VA | cooperative | moderate | slow | ODEC members; PJM/Dominion transmission constraint. |
| WA | cooperative | moderate | medium | BPA-supplied co-ops; capacity limited. |
| WA | political subdivision | moderate | medium | PUDs: cheap hydro, large-load caps, BPA transmission. |
| WI | cooperative | favorable | medium | Dairyland members; supportive state. |
| WV | cooperative | favorable | slow | West Virginia supportive law; PJM. |
| WY | cooperative | favorable | medium | Wyoming supportive (crypto/DC laws); Basin Electric / Tri-State supply. |
Curated from public tariff filings, commission orders and utility statements; a screening signal, not legal advice. Service territories from HIFLD / EIA-861; a site's utility is the investor-owned utility whose territory contains it, else the largest co-op or municipal. Utilities not listed inherit their state's posture.