Datacenter Sites in Storey County, Nevada
Storey County has 79 scored datacenter candidate sites averaging 54.6/100 DC Readiness, with a catalogued aggregate of 16,008 MW. FEMA rates local natural-hazard risk as "Very Low". The county has a datacenter tax incentive on record.
79
Candidate sites
54.6/100
Avg DC Readiness
16,008 MW
Catalogued capacity
theoretical aggregate
Very Low
Hazard rating
Site-selection context for Storey County
Yessales_tax_abatement
Datacenter tax incentive
5.83¢/kWh
Commercial electricity
5.01¢/kWh
Industrial electricity
2
Fiber providers
Extremely High
Water stress
$77,197
Land price / acre
2,000
Cooling degree days
3,700
Heating degree days
50°F
Mean annual temp
Incentive detail: Partial abatement of sales/use tax and personal property tax for $25M+ DC investments.
By site type
Top datacenter sites in Storey County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| NORTH VALLEY ROAD | Substation-Adjacent | 345 kV | 600 MW | 5.8 yrs | 70.0 |
| MIRA LOMA | Substation-Adjacent | 345 kV | 600 MW | 5.8 yrs | 67.1 |
| TRACY | Substation-Adjacent | 345 kV | 600 MW | 5.8 yrs | 65.6 |
| Galena 3 Geothermal Power Plant | Brownfield | — | 30 MW | — | 62.3 |
| WASHOE | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 62.3 |
| Steamboat 1 | Brownfield | — | 8 MW | — | 62.2 |
| STEAMBOAT | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 62.2 |
| MT. ROSE | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 62.0 |
| RENO | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 61.9 |
| SUGAR LOAF | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 61.5 |
| GREG ST/BELLA VISTA | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 61.3 |
| NORTHWEST TAP | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 61.2 |
| Greenfield (CELILO - SYLMAR EAST) | Greenfield | 1000 kV | 1,000 MW | 5.8 yrs | 61.0 |
| Steamboat 1A Power Plant | Brownfield | — | 2 MW | — | 60.0 |
| SPANISH SPRINGS | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 59.3 |
| CALIFORNIA | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 59.3 |
| Greenfield (VALMY - TRACY) | Greenfield | 345 kV | 600 MW | 5.8 yrs | 59.2 |
| Greenfield (TRACY - NORTH VALLEY ROAD) | Greenfield | 345 kV | 600 MW | 5.8 yrs | 59.1 |
| Greenfield (CELILO - SYLMAR EAST) | Greenfield | 1000 kV | 1,000 MW | 5.8 yrs | 59.0 |
| Greenfield (CELILO - SYLMAR EAST) | Greenfield | 1000 kV | 1,000 MW | 5.8 yrs | 59.0 |
| EC Near Tracy | Greenfield | — | — | 5.8 yrs | 58.8 |
| SILVER LAKE | Substation-Adjacent | 120 kV | 100 MW | 5.8 yrs | 58.7 |
| EC Near Tracy | Greenfield | — | — | 5.8 yrs | 58.6 |
| Greenfield (CELILO - SYLMAR EAST) | Greenfield | 1000 kV | 1,000 MW | 5.8 yrs | 58.4 |
| EC Near Tracy | Greenfield | — | — | 5.8 yrs | 58.3 |
Storey County datacenter FAQ
- How many datacenter sites are in Storey County?
- 79 scored datacenter candidate sites, averaging 54.6/100 DC Readiness.
- Does Storey County offer datacenter tax incentives?
- Partial abatement of sales/use tax and personal property tax for $25M+ DC investments.
- What is the natural-hazard risk in Storey County?
- FEMA's National Risk Index rates Storey County as "Very Low" (score 12).
- What are industrial electricity rates in Storey County?
- Average industrial electricity is 5.01¢/kWh and commercial is 5.83¢/kWh in Storey County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Storey County, Nevada. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.