Ely Energy Center
BrownfieldEly, White Pine, Nevada · Nevada Power Co
Ely Energy Center is a coal plant in Ely, White Pine, Nevada. Retired generation sites are among the most attractive datacenter redevelopment targets: the existing interconnection was sized for roughly 1,500 MW of generation, so the grid hookup, transmission rights, and often cooling-water access are already in place — collapsing the speed-to-power timeline versus a greenfield build.
Former use & capacity
Grid hookup & remediation
Nearby datacenter candidate sites
Scored candidate sites near Ely Energy Center, ranked by DC Readiness.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| ROBINSON | Substation-Adjacent | NV | White Pine County | 500 kV | 1,000 MW | 5.8 yrs | 61.2 |
| GONDER | Substation-Adjacent | NV | White Pine County | 345 kV | 600 MW | 5.8 yrs | 59.1 |
| Ely Energy Center | Brownfield | NV | White Pine County | 345 kV | 1,500 MW | 5.8 yrs | 56.9 |
| Greenfield (TAP307893 - ROBINSON) | Greenfield | NV | White Pine County | 500 kV | 1,000 MW | 5.8 yrs | 55.9 |
| Greenfield (ROBINSON - FALCON) | Greenfield | NV | White Pine County | 345 kV | 600 MW | 5.8 yrs | 54.3 |
| Greenfield (TAP307893 - ROBINSON) | Greenfield | NV | White Pine County | 500 kV | 1,000 MW | 5.8 yrs | 53.6 |
| Greenfield (INTERMOUNTAIN - GONDER) | Greenfield | NV | White Pine County | 230 kV | 300 MW | 5.8 yrs | 53.2 |
| Greenfield (GONDER - ROBINSON) | Greenfield | NV | White Pine County | 345 kV | 600 MW | 5.8 yrs | 53.0 |
See all datacenter sites in Nevada →
Dataset updated . Screening estimates derived from public data sources.
Brownfield attributes are derived from EIA retired-generator and EPA public data. Existing capacity reflects the retired plant's historical nameplate, not deliverable interconnection for a new load. Confirm reusable interconnection rights, remediation status, and site availability with the utility, ISO, and current owner.