Western Electricity Coordinating Council

WECC spans the entire western interconnection outside California's ISO, from the Rockies to the Pacific Northwest. Abundant hydro and renewables pair with rapidly growing load and long transmission distances.

21,799
Candidate sites
51.3/100
Avg DC Readiness
883.8k MW
Catalogued capacity
theoretical aggregate
6.7 yrs
Avg queue wait

Average sub-score profile

Power availability
37.5
Speed-to-power
42.8
Fiber
64.4
Water
43.8
Hazard resilience
78.0

Top 25 datacenter sites in WECC

Top datacenter sites in WECC
SiteTypeStateCountyVoltageCapacityQueue waitScore
UAMPS Carbon Free Power PlantBrownfieldIDBonneville County46 kV762 MW2.0 yrs73.2
KEELERSubstation-AdjacentORWashington County500 kV1,000 MW6.9 yrs71.5
PEARLSubstation-AdjacentORWashington County500 kV1,000 MW6.9 yrs70.8
BPA TROUTDALESubstation-AdjacentORMultnomah County500 kV1,000 MW6.9 yrs70.2
COLUMBIASubstation-AdjacentWAGrant County500 kV1,000 MW6.9 yrs69.5
Warren AFB WindBrownfieldWYLaramie35 kV3 MW6.9 yrs69.4
Chevron Casper Wind FarmBrownfieldWYNatrona115 kV17 MW6.9 yrs69.2
OSTRANDERSubstation-AdjacentORMultnomah County500 kV1,000 MW6.9 yrs69.2
ALVEYSubstation-AdjacentORLane County500 kV1,000 MW6.9 yrs69.0
MAPLE VALLEYSubstation-AdjacentWAKing County500 kV1,000 MW6.9 yrs68.9
SNO-KINGSubstation-AdjacentWAKitsap County500 kV1,000 MW6.9 yrs68.7
LANESubstation-AdjacentORLane County500 kV1,000 MW6.9 yrs68.7
COVINGTONSubstation-AdjacentWAKing County500 kV1,000 MW6.9 yrs68.6
TAP200917Substation-AdjacentWASnohomish County500 kV1,000 MW6.9 yrs68.5
BELLSubstation-AdjacentWASpokane County500 kV1,000 MW6.9 yrs68.5
WanapumBrownfieldWAGrant County500 kV1,038 MW6.9 yrs68.3
MONROESubstation-AdjacentWASnohomish County500 kV1,000 MW6.9 yrs68.3
MERIDIANSubstation-AdjacentORJackson County500 kV1,000 MW6.9 yrs68.2
MCNARYSubstation-AdjacentORBenton County500 kV1,000 MW6.9 yrs68.1
EC Coal Sheridan CountyGreenfieldWYSheridan County1.7 yrs68.0
SACAJAWEASubstation-AdjacentWAWalla Walla County500 kV1,000 MW6.9 yrs67.9
ECHO LAKESubstation-AdjacentWAKing County500 kV1,000 MW6.9 yrs67.8
SICKLERSubstation-AdjacentWAChelan County500 kV1,000 MW6.9 yrs67.8
UNKNOWN201455Substation-AdjacentWAThurston County500 kV1,000 MW6.9 yrs67.8
EC Coal Sheridan CountyGreenfieldWYSheridan County1.7 yrs67.8

WECC FAQ

What is WECC?
Western Electricity Coordinating Council (WECC) WECC spans the entire western interconnection outside California's ISO, from the Rockies to the Pacific Northwest. Abundant hydro and renewables pair with rapidly growing load and long transmission distances.
How many datacenter sites are in the WECC region?
GridCensus catalogs 21,799 scored datacenter candidate sites in WECC, averaging 51.3/100 DC Readiness.
What is the average interconnection-queue wait in WECC?
Candidate sites in WECC average a 6.7 yrs queue wait with an average queue depth of 35 projects.