Federal Excess Datacenter Sites

At a glance

GridCensus scores 17,528 federal excess datacenter candidate sites across the US — 12% of all 147,272 scored sites and the 5th-largest of 9 site types. They average 47.5/100 on the DC Readiness Score, the 9th-highest of 9 types (national average 53.0). Washington has the most, with 3,676.

Surplus federal property released for civilian reuse. Federal excess parcels can carry existing infrastructure and favorable disposition terms, but acquisition timelines vary with the disposing agency.

17,528
Candidate sites
47.5/100
Avg DC Readiness
4.5 yrs
Avg queue wait

How do federal excess sites compare with other site types?

Federal Excess sites are the 5th-largest of 9 site types by count and the 9th-highest of 9 by average DC Readiness. Their 47.5 average is below the 53.0 average across all 147,272 sites. The average interconnection-queue wait in their markets, 4.5 yrs, is the 6th-shortest of 9. The federal excess category is strongest on hazard resilience, averaging 70.6 against a national average of 66.8; its weakest factor is water, at 46.0 versus 72.3 nationally.

Where are federal excess datacenter sites located?

The five states with the most are Washington (3,676, 21%), California (3,212, 18%), Arizona (1,616, 9%), Nebraska (1,057, 6%) and Oklahoma (991, 6%). Federal Excess sites appear in 35 states. By grid region, WECC holds 56%, SPP holds 21% and CAISO holds 17%.

Average sub-score profile

Power availability
30.0
Speed-to-power
50.3
Fiber
59.9
Water
46.0
Hazard resilience
70.6

Top 25 federal excess datacenter sites

Top Federal Excess datacenter sites
SiteTypeStateCountyVoltageCapacityQueue waitScore
Kansas City VA Medical CenterFederal ExcessMOJackson County——4.3 yrs57.7
BILLINGSFederal ExcessMTYellowstone County——1.1 yrs57.7
BOZEMAN FISH TECHNOLOGY CENTERFederal ExcessMTGallatin County——1.1 yrs57.6
MIAMI INT'L AIRPORTFederal ExcessFLMiami-Dade County——3.7 yrs57.5
FOREST PRODUCTS LABORATORYFederal ExcessWIDane County——4.3 yrs57.5
VAMC Wilmington, DEFederal ExcessDENew Castle County——1.5 yrs57.5
William S. Middleton-Memorial VHFederal ExcessWIDane County——4.3 yrs57.4
ROCHESTER FMCFederal ExcessMNOlmsted County——4.3 yrs57.4
MONTANA - LEASEFederal ExcessMTYellowstone County——1.1 yrs57.4
US NATIONAL POULTRY RES CTRFederal ExcessMIIngham County——2.2 yrs57.4
MANCHESTER ASR-5Federal ExcessNHRockingham County——4.3 yrs57.4
West Haven VA Connecticut Healthcare SystemFederal ExcessCTSouth Central Connecticut County——4.3 yrs57.4
ANN ARBOR MUNICIPAL AIRPORTFederal ExcessMIWashtenaw County——2.2 yrs57.4
FOREST PRODUCTS LABORATORYFederal ExcessWIDane County——4.3 yrs57.3
BOZEMAN FISH TECHNOLOGY CENTERFederal ExcessMTGallatin County——1.1 yrs57.3
John D. Dingell VA Medical CenterFederal ExcessMIWayne County——2.2 yrs57.3
CHESTER, NHFederal ExcessNHRockingham County——4.3 yrs57.3
BROOKLYN PARK, MN (GEP)Federal ExcessMNHennepin County——4.3 yrs57.3
USDA DAIRY FORAGE RESEARCH CTRFederal ExcessWIWood County——4.3 yrs57.3
HUBERT H HUMPHREYFederal ExcessMNRamsey County——4.3 yrs57.2
Wood National CemeteryFederal ExcessWIMilwaukee County——4.3 yrs57.2
HuntleyFederal ExcessMTYellowstone County——1.1 yrs57.2
BOZEMAN FISH TECHNOLOGY CENTERFederal ExcessMTGallatin County——1.1 yrs57.2
Bruce W. Carter VA Medical CenterFederal ExcessFLMiami-Dade County——3.7 yrs57.1
NATIONAL WILDLIFE HEALTH CTRFederal ExcessWIDane County——4.3 yrs57.1

What do the top-scoring federal excess sites have in common?

The top 25 federal excess sites score between 57.1 and 57.7. 6 are in Montana, 6 are in Wisconsin and 3 are in Minnesota. Their counties have a median of 13 fixed fiber broadband providers in FCC data. The median distance to the nearest internet exchange facility is 2 km. The median interconnection-queue wait in their markets is 4.3 years. None of the 3 with a mapped FEMA flood zone sits in a high-risk (A or V) zone. 1 lies within 25 km of a binding transmission constraint.

Federal Excess site FAQ

What is a federal excess datacenter site?

Surplus federal property released for civilian reuse. Federal excess parcels can carry existing infrastructure and favorable disposition terms, but acquisition timelines vary with the disposing agency.

How many federal excess datacenter sites are there?

GridCensus catalogs 17,528 federal excess candidate sites nationwide, averaging 47.5/100 DC Readiness — 12% of all scored sites.

Which state has the most federal excess datacenter sites?

Washington leads with 3,676 federal excess candidate sites, followed by California with 3,212.

What is the highest-scoring federal excess datacenter site?

Kansas City VA Medical Center in Jackson County, Missouri has the highest DC Readiness Score of any federal excess site, at 57.7/100.

How long is the interconnection queue for federal excess sites?

Federal Excess candidate sites sit in markets with an average interconnection-queue wait of 4.5 yrs, the 6th-shortest of 9 site types.

Other datacenter site types

By grid region

Dataset updated . Screening estimates derived from public data sources.

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published November 12, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Federal Excess datacenter candidate sites”, https://gridcensus.com/site-types/federal-excess (data as of November 12, 2026).

Go deeper than the public screen

Every site and score for Federal Excess sites is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.