UAMPS Carbon Free Power Plant

Brownfield

Bonneville County, Idaho · WECC

DC Readiness
63.4
Good / 100

UAMPS Carbon Free Power Plant is a brownfield datacenter candidate site in Bonneville County, Idaho, interconnecting through WECC. It screens at 63.4/100 DC Readiness with a catalogued 762 MW of candidate capacity and a 2.0 yrs average interconnection-queue wait.

Power & interconnection

Substation distance34.3 mi
Substation voltage115 kV
Available capacity762 MW
Utility commercial rate0.09¢/kWh

Speed to power

ISO / RTO regionWECC
Queue depth74
Avg queue wait2.0 yrs
Recent queue wait1.9 yrs
Completion rate30%
Withdrawal rate70%

Connectivity

Nearest IXPMontana Opticom
IXP distance154.7 mi
Fiber providers12
Fiber coverage80.7%
Nearest cloud providerGCP
Nearest cloud regionus-west3
Cloud region distance190.8 mi

Site characteristics

Site typeBrownfield
Parcel ownerBatelle Facility Owner Lc
Parcel APNRPA0271001007O
Land owner typeprivate
Buildability100.0/100
Land cover (NLCD)Developed, High Intensity
Former usenuclear
Existing capacity762 MW

Risk & environment

Flood zoneZone X
Water stress (WRI)2.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteUS DOE INL UNIVERSITY BLDG 3
Hazard sub-score75/100
Construction cost index75.7 (avg 100)

Location context

Nearest datacenterVentureData
DC distance24.9 mi
Nearest rail0.6 mi
Nearest gas pipeline49.4 mi
Nearest fiber route166.0 mi
County hazard (FEMA NRI)Relatively Low (15)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity8.53¢/kWh
Industrial electricity6.75¢/kWh
Cooling degree days500
Heating degree days6,400
Land price / acre$4,884

Incentive detail: Personal property tax exemption on computer equipment.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
29
Speed to power15%
55
Fiber connectivity12%
72
Energy cost10%
100
Water risk8%
58
Natural hazard8%
75
Buildability7%
100
Labor market4%
50
DC cluster4%
60
Land / acreage3%
71
Construction cost3%
87
Gas pipeline2%
0
Tax incentive2%
100
Climate / cooling2%
100

Nearby comparable sites

Other scored datacenter candidate sites in Bonneville County, ranked by DC Readiness.

Sites near UAMPS Carbon Free Power Plant
SiteTypeVoltageCapacityQueue waitScore
AMMONSubstation-Adjacent161 kV100 MW2.0 yrs69.5
TAP204670Substation-Adjacent161 kV100 MW2.0 yrs68.6
WASHINGTONSubstation-Adjacent161 kV100 MW2.0 yrs68.3
JOLLY HILLSubstation-Adjacent161 kV100 MW2.0 yrs67.5
MEADOW CREEK PROJECT COMPANYSubstation-Adjacent161 kV100 MW2.0 yrs66.5
TAP204671Substation-Adjacent161 kV100 MW2.0 yrs66.3
HORSE BUTTE WIND I, LLCSubstation-Adjacent115 kV100 MW2.0 yrs64.7
Greenfield (GOSHEN - 3 MILE KNOLL)Greenfield345 kV600 MW2.0 yrs63.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UAMPS Carbon Free Power Plant, Bonneville County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.