Datacenter Sites in California
California has 9,645 scored datacenter candidate sites averaging 46.2/100 DC Readiness. Federal Excess parcels lead the inventory (3,212 sites). Most sites interconnect through CAISO. The state's candidate sites carry a catalogued aggregate of 1.0M MW and average a 5.7 yrs interconnection-queue wait.
By site type
- Federal Excess3,212
- Greenfield2,626
- Industrial2,201
- Substation-Adjacent992
- Former Mine451
- Brownfield154
- Military BRAC9
Average sub-score profile
How California's candidate sites score on each DC Readiness dimension (0–100 average).
Top 25 datacenter sites in California
Ranked by DC Readiness.
| Site | Type | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|
| TESLA Power Project | Brownfield | Alameda County | 500 kV | 1,322 MW | 5.7 yrs | 64.6 |
| Greenfield (JEFFERSON - GREENTOWN) | Greenfield | Hamilton County | 765 kV | 1,000 MW | 8.2 yrs | 62.1 |
| Broadway (CA) | Brownfield | Los Angeles County | 66 kV | 167 MW | 5.7 yrs | 61.3 |
| Greenfield (WILSON - PIN HOOK) | Greenfield | Wilson County | 500 kV | 1,000 MW | 8.2 yrs | 61.2 |
| STATION E (TOLUCA) | Substation-Adjacent | Los Angeles County | 500 kV | 1,000 MW | 8.2 yrs | 60.1 |
| Greenfield (MONTGOMERY - DAVIDSON) | Greenfield | Cheatham County | 500 kV | 1,000 MW | 8.2 yrs | 60.0 |
| STATION L (SCATTERGOOD) | Substation-Adjacent | Los Angeles County | 230 kV | 300 MW | 8.2 yrs | 59.9 |
| VALLEY | Substation-Adjacent | Orange County | 500 kV | 1,000 MW | 8.2 yrs | 59.7 |
| INLAND EMPIRE | Substation-Adjacent | Orange County | 500 kV | 1,000 MW | 8.2 yrs | 59.6 |
| METCALF 1 | Substation-Adjacent | Santa Clara County | 500 kV | 1,000 MW | 8.2 yrs | 59.6 |
| Hunters Point | Brownfield | San Mateo County | 115 kV | 427 MW | 5.7 yrs | 59.5 |
| Greenfield (MONTGOMERY - WILSON) | Greenfield | Sumner County | 500 kV | 1,000 MW | 8.2 yrs | 59.4 |
| Greenfield (MONTGOMERY - WILSON) | Greenfield | Robertson County | 500 kV | 1,000 MW | 8.2 yrs | 59.1 |
| AIRWAY | Substation-Adjacent | Los Angeles County | 230 kV | 300 MW | 8.2 yrs | 58.7 |
| STATION M(VALLEY) | Substation-Adjacent | Los Angeles County | 230 kV | 300 MW | 8.2 yrs | 58.3 |
| UCLA So Campus Cogen Project | Brownfield | Los Angeles County | 230 kV | 15 MW | 5.7 yrs | 58.2 |
| Paramount Refinery | Brownfield | Los Angeles County | 66 kV | 7 MW | 5.7 yrs | 58.2 |
| Anaheim GT | Brownfield | Orange County | 66 kV | 49 MW | 5.7 yrs | 58.1 |
| Greenfield (MONTGOMERY - DAVIDSON) | Greenfield | Montgomery County | 500 kV | 1,000 MW | 8.2 yrs | 57.7 |
| Greenfield (CLARKSVILLE - EAST WINDSOR) | Greenfield | Mercer County | 230 kV | 300 MW | 8.2 yrs | 57.7 |
| Magnolia | Brownfield | Los Angeles County | 66 kV | 88 MW | 5.7 yrs | 57.6 |
| Greenfield (MIDDLETOWN - CONCORD) | Greenfield | Delaware County | 230 kV | 300 MW | 8.2 yrs | 57.6 |
| EMBARCADERO | Substation-Adjacent | Contra Costa County | 230 kV | 300 MW | 8.2 yrs | 57.5 |
| Greenfield (SOMERSET - NIAGARA) | Greenfield | Niagara County | 345 kV | 600 MW | 8.2 yrs | 57.4 |
| NEWARK DISTRIBUTION | Substation-Adjacent | Alameda County | 230 kV | 300 MW | 8.2 yrs | 57.4 |
Counties in California
58 counties with five or more scored sites.
California datacenter site selection FAQ
- How many datacenter sites are in California?
- GridCensus catalogs 9,645 scored datacenter candidate sites in California, with an average DC Readiness score of 46.2/100.
- What is the average interconnection-queue wait in California?
- Candidate sites in California average a 5.7 yrs interconnection-queue wait, with an average queue depth of 290 projects.
- What kind of datacenter sites are most common in California?
- Federal Excess sites are the most common category in California (3,212 sites), and most sites fall within the CAISO grid region.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for California. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.