Datacenter Sites in Nevada, California

Nevada has 73 scored datacenter candidate sites averaging 41.8/100 DC Readiness, with a catalogued aggregate of 500 MW. FEMA rates local natural-hazard risk as "Relatively High".

73
Candidate sites
41.8/100
Avg DC Readiness
500 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
◆ Loading map…
≥ 7560–7540–60≤ 40
Top 25 in Nevada

Site-selection context for Nevada

No
Datacenter tax incentive
29.25¢/kWh
Commercial electricity
22.93¢/kWh
Industrial electricity
6
Fiber providers
High
Water stress
$8,650
Land price / acre
1,000
Cooling degree days
2,500
Heating degree days
59°F
Mean annual temp

By site type

Top datacenter sites in Nevada

Top datacenter sites in Nevada
SiteTypeVoltageCapacityQueue waitScore
BONNIE NOOKSubstation-Adjacent115 kV100 MW8.2 yrs47.6
DRUMSubstation-Adjacent115 kV100 MW8.2 yrs46.7
CISCO GROVESubstation-Adjacent69 kV50 MW8.2 yrs44.8
TAMARACKSubstation-Adjacent69 kV50 MW8.2 yrs44.8
UNKNOWN300195Substation-Adjacent69 kV50 MW8.2 yrs44.8
BRUNSWICKSubstation-Adjacent69 kV50 MW8.2 yrs44.8
PIKE CITYSubstation-Adjacent69 kV50 MW8.2 yrs44.5
ALLEGHANYSubstation-Adjacent69 kV50 MW8.2 yrs44.3
EC FFE Nevada CountyGreenfield5.7 yrs43.8
Washoe ProjectFederal Excess8.2 yrs43.3
Washoe ProjectFederal Excess8.2 yrs43.2
Truckee Storage ProjectFederal Excess8.2 yrs43.2
Washoe ProjectFederal Excess8.2 yrs43.2
Truckee Storage ProjectFederal Excess8.2 yrs43.1
Washoe ProjectFederal Excess8.2 yrs43.0
Washoe ProjectFederal Excess8.2 yrs42.9
Washoe ProjectFederal Excess8.2 yrs42.9
Mine SiteFormer Mine8.2 yrs42.8
Washoe ProjectFederal Excess8.2 yrs42.7
OZ NevadaGreenfield5.7 yrs42.6
Truckee Storage ProjectFederal Excess8.2 yrs42.3
Washoe ProjectFederal Excess8.2 yrs42.1
Mine SiteFormer Mine8.2 yrs41.8
Former Bear River Mill, EastIndustrial8.2 yrs41.5
Washoe ProjectFederal Excess8.2 yrs41.5

Nevada datacenter FAQ

How many datacenter sites are in Nevada?
73 scored datacenter candidate sites, averaging 41.8/100 DC Readiness.
Does Nevada offer datacenter tax incentives?
No datacenter-specific tax incentive is on record for Nevada in our dataset.
What is the natural-hazard risk in Nevada?
FEMA's National Risk Index rates Nevada as "Relatively High" (score 48).
What are industrial electricity rates in Nevada?
Average industrial electricity is 22.93¢/kWh and commercial is 29.25¢/kWh in Nevada.

Dataset updated . Screening estimates derived from public data sources.