Datacenter Sites in Chesterfield, Virginia

Chesterfield has 111 scored datacenter candidate sites averaging 55.9/100 DC Readiness, with a catalogued aggregate of 3,600 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.

111
Candidate sites
55.9/100
Avg DC Readiness
3,600 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
◆ Loading map…
≥ 7560–7540–60≤ 40
Top 25 in Chesterfield

Site-selection context for Chesterfield

Yessales_tax_exemption
Datacenter tax incentive
5.78¢/kWh
Commercial electricity
4.85¢/kWh
Industrial electricity
2
Fiber providers
Low
Water stress
$8,136
Land price / acre
1,300
Cooling degree days
4,000
Heating degree days
55°F
Mean annual temp

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

By site type

Top datacenter sites in Chesterfield

Top datacenter sites in Chesterfield
SiteTypeVoltageCapacityQueue waitScore
MIDLOTHIANSubstation-Adjacent500 kV1,000 MW3.8 yrs67.1
EC Near Park 500 Philip Morris USAGreenfield3.1 yrs64.1
EC Coal Chesterfield CountyGreenfield3.1 yrs64.0
OZ ChesterfieldGreenfield3.1 yrs63.9
IRON BRIDGESubstation-Adjacent230 kV300 MW3.8 yrs63.0
TAP146381Substation-Adjacent230 kV300 MW3.8 yrs63.0
HULL STREET ROADSubstation-Adjacent230 kV300 MW3.8 yrs63.0
OZ ChesterfieldGreenfield3.1 yrs62.8
UNKNOWN116246Substation-Adjacent230 kV300 MW3.8 yrs62.8
EC Near Park 500 Philip Morris USAGreenfield3.1 yrs62.7
EC Coal Chesterfield CountyGreenfield3.1 yrs62.3
EC Near ChesterfieldGreenfield3.1 yrs62.1
WINTERPOCKSubstation-Adjacent230 kV300 MW3.8 yrs61.0
EC Near ChesterfieldGreenfield3.1 yrs60.9
EC Near ChesterfieldGreenfield3.1 yrs60.8
EC Near Park 500 Philip Morris USAGreenfield3.1 yrs60.6
EC Coal Chesterfield CountyGreenfield3.1 yrs60.5
CENTRALIASubstation-Adjacent115 kV100 MW3.8 yrs58.9
EC Near ChesterfieldGreenfield3.1 yrs58.2
EC Coal Chesterfield CountyGreenfield3.1 yrs58.2
EC Near ChesterfieldGreenfield3.1 yrs57.2
UNKNOWN161687Substation-Adjacent115 kV100 MW3.8 yrs56.9
Meadowville Technology ParkShovel-Ready3.8 yrs55.8
EC Near ChesterfieldGreenfield3.1 yrs55.8
2701 Bermuda Hundred RdShovel-Ready3.8 yrs55.7

Chesterfield datacenter FAQ

How many datacenter sites are in Chesterfield?
111 scored datacenter candidate sites, averaging 55.9/100 DC Readiness.
Does Chesterfield offer datacenter tax incentives?
Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.
What is the natural-hazard risk in Chesterfield?
FEMA's National Risk Index rates Chesterfield as "Relatively Moderate" (score 30).
What are industrial electricity rates in Chesterfield?
Average industrial electricity is 4.85¢/kWh and commercial is 5.78¢/kWh in Chesterfield.

Dataset updated . Screening estimates derived from public data sources.