Datacenter Sites in Ripley County, Missouri

Ripley County has 12 scored datacenter candidate sites averaging 51.4/100 DC Readiness, with a catalogued aggregate of 400 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.

At a glance

Ripley County, Missouri has 12 scored datacenter candidate sites averaging 51.4/100 DC Readiness, roughly in line with the Missouri average of 55.7. It ranks 66th of 110 Missouri counties by number of sites and 102nd by average score. The top-scoring site is OZ Ripley at 57.7/100.

12
Candidate sites
51.4/100
Avg DC Readiness
400 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
◆ Loading map…
≥ 7560–7540–60≤ 40
Top 12 in Ripley County

Site-selection context for Ripley County

Yessales_tax_exemption
Datacenter tax incentive
11.16¢/kWh
Commercial electricity
8.74¢/kWh
Industrial electricity
2
Fiber providers
Low
Water stress
$2,855
Land price / acre
1,500
Cooling degree days
4,700
Heating degree days
56°F
Mean annual temp

Incentive detail: Qualified data center sales tax exemption (2019 law); state income tax credits.

How does Ripley County compare with other counties in Missouri?

By number of scored sites, Ripley County ranks 66th of the 110 Missouri counties with a county page, holding 0.4% of the state's 3,413 sites. Its average DC Readiness of 51.4/100 ranks 102nd in the state and is roughly in line with the national average of 53.0. Nationally it has the 2244th-largest site inventory of 2,964 counties with five or more sites. 0 sites score 70 or higher and 2 score 55 or higher.

What types of datacenter sites are in Ripley County?

Substation-Adjacent sites are the most common (7, 58% of the county's inventory), followed by former mine (3) and federal excess (1). Site type reflects how the parcel was identified — next to a substation, on a former mine or brownfield, on industrial or federal excess land — and is scored on the same 14 factors either way.

What are power cost, hazard, water and fiber conditions in Ripley County?

Industrial electricity averages 8.74¢/kWh and commercial 11.16¢/kWh. FEMA's National Risk Index rates the county "Relatively High" (38). WRI water stress is low. 2 fiber providers report service in the county. The climate runs 1,500 cooling degree days a year with a mean temperature of 56°F. Land is valued around $2,855 an acre.

By site type

Top datacenter sites in Ripley County

Top datacenter sites in Ripley County
SiteTypeVoltageCapacityQueue waitScore
OZ RipleyGreenfield——3.9 yrs57.7
UNKNOWN117758Substation-Adjacent161 kV100 MW3.9 yrs55.0
TAP168445Substation-Adjacent69 kV50 MW3.9 yrs52.6
UNKNOWN168448Substation-Adjacent69 kV50 MW3.9 yrs52.4
UNKNOWN154721Substation-Adjacent69 kV50 MW3.9 yrs52.3
TAP168447Substation-Adjacent69 kV50 MW3.9 yrs52.3
TAP168449Substation-Adjacent69 kV50 MW3.9 yrs52.3
UNKNOWN168446Substation-Adjacent69 kV50 MW3.9 yrs52.1
JonesboroFederal Excess——3.9 yrs47.9
Mine SiteFormer Mine——3.9 yrs47.9
Mine SiteFormer Mine——3.9 yrs47.5
Mine SiteFormer Mine——3.9 yrs46.7

Every scored site in Ripley County

All 12 sites, best first.

Ripley County datacenter FAQ

How many datacenter sites are in Ripley County?

12 scored datacenter candidate sites, averaging 51.4/100 DC Readiness. That is the 66th-most of 110 Missouri counties with five or more sites.

What is the highest-scoring datacenter site in Ripley County?

OZ Ripley scores 57.7/100 DC Readiness, the highest of the 12 scored sites in Ripley County (a greenfield site).

Does Ripley County offer datacenter tax incentives?

Qualified data center sales tax exemption (2019 law); state income tax credits.

What is the natural-hazard risk in Ripley County?

FEMA's National Risk Index rates Ripley County as "Relatively High" (score 38).

What are industrial electricity rates in Ripley County?

Average industrial electricity is 8.74¢/kWh and commercial is 11.16¢/kWh in Ripley County.

More in Missouri

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published November 13, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Datacenter candidate sites in Ripley County, Missouri”, https://gridcensus.com/datacenter-sites/missouri/ripley-county (data as of November 13, 2026).

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

Every site and score for Ripley County, Missouri is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.