Datacenter Sites in Hinds, Mississippi
Hinds has 206 scored datacenter candidate sites averaging 49.3/100 DC Readiness, with a catalogued aggregate of 11,600 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
206
Candidate sites
49.3/100
Avg DC Readiness
11,600 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Hinds
Yessales_tax_exemption
Datacenter tax incentive
12.56¢/kWh
Commercial electricity
7.85¢/kWh
Industrial electricity
6
Fiber providers
Low
Water stress
$3,474
Land price / acre
2,400
Cooling degree days
2,400
Heating degree days
64°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment for $50M+ investments; fee-in-lieu of property tax.
By site type
Top datacenter sites in Hinds
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| LAKEOVER | Substation-Adjacent | 500 kV | 1,000 MW | 1.4 yrs | 74.7 |
| LAKEOVER | Substation-Adjacent | 500 kV | 1,000 MW | 1.4 yrs | 74.4 |
| RAY BRASWELL | Substation-Adjacent | 500 kV | 1,000 MW | 1.4 yrs | 73.9 |
| TINNIN ROAD | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 70.6 |
| UNKNOWN110121 | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 70.5 |
| NORTHSIDE DRIVE | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 70.4 |
| ROBINSON ROAD | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 70.1 |
| SOUTHWEST JACKSON | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 69.5 |
| TINNIN ROAD | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 67.8 |
| MIAMI | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 67.3 |
| Greenfield (RAY BRASWELL - LAKEOVER) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 67.1 |
| Greenfield (RAY BRASWELL - BAXTER WILSON) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 67.1 |
| Greenfield (FRANKLIN - RAY BRASWELL) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 66.8 |
| Greenfield (FRANKLIN - RAY BRASWELL) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 66.7 |
| UNKNOWN110155 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 66.2 |
| SPRING RIDGE ROAD | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 65.4 |
| WEST JACKSON | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 65.1 |
| UNKNOWN110186 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 64.7 |
| UNKNOWN110185 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 64.5 |
| CLINTON | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 63.7 |
| TAP145961 | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 63.5 |
| Greenfield (BOZEMAN ROAD - TINNIN ROAD) | Greenfield | 230 kV | 300 MW | 1.4 yrs | 63.4 |
| TAP146080 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 63.0 |
| REX BROWN 230KV | Substation-Adjacent | 230 kV | 300 MW | 1.4 yrs | 62.7 |
| UNKNOWN110153 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 62.2 |
Hinds datacenter FAQ
- How many datacenter sites are in Hinds?
- 206 scored datacenter candidate sites, averaging 49.3/100 DC Readiness.
- Does Hinds offer datacenter tax incentives?
- Sales tax exemption on DC equipment for $50M+ investments; fee-in-lieu of property tax.
- What is the natural-hazard risk in Hinds?
- FEMA's National Risk Index rates Hinds as "Relatively High" (score 45).
- What are industrial electricity rates in Hinds?
- Average industrial electricity is 7.85¢/kWh and commercial is 12.56¢/kWh in Hinds.
Dataset updated . Screening estimates derived from public data sources.