Datacenter Sites in Will, Illinois
Will has 111 scored datacenter candidate sites averaging 61.8/100 DC Readiness, with a catalogued aggregate of 23,744 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
111
Candidate sites
61.8/100
Avg DC Readiness
23,744 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Will
Yessales_tax_exemption
Datacenter tax incentive
8.86¢/kWh
Commercial electricity
5.29¢/kWh
Industrial electricity
13
Fiber providers
Low
Water stress
$10,259
Land price / acre
1,100
Cooling degree days
5,600
Heating degree days
52°F
Mean annual temp
Incentive detail: Enterprise Zone sales tax exemption; High Impact Business designation for $12M+ DC investments.
By site type
Top datacenter sites in Will
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| TAP138173 | Substation-Adjacent | 345 kV | 600 MW | 3.8 yrs | 66.0 |
| UNKNOWN124429 | Substation-Adjacent | 345 kV | 600 MW | 3.8 yrs | 65.9 |
| JOLIET | Substation-Adjacent | 345 kV | 600 MW | 3.8 yrs | 64.8 |
| GOODINGS GROVE | Substation-Adjacent | 345 kV | 600 MW | 3.8 yrs | 64.7 |
| LOCKPORT | Substation-Adjacent | 345 kV | 600 MW | 3.8 yrs | 64.3 |
| EAST FRANKFORT | Substation-Adjacent | 345 kV | 600 MW | 3.8 yrs | 64.2 |
| WILTON | Substation-Adjacent | 765 kV | 1,000 MW | 3.8 yrs | 64.0 |
| TAP138156 | Substation-Adjacent | 345 kV | 600 MW | 3.8 yrs | 63.5 |
| Greene Valley Gas Recovery | Brownfield | 138 kV | 3 MW | 3.8 yrs | 63.1 |
| EC Near Will County | Greenfield | — | — | 4.6 yrs | 62.8 |
| EC Coal Will County | Greenfield | — | — | 4.6 yrs | 62.3 |
| OZ Will | Greenfield | — | — | 4.6 yrs | 62.0 |
| EC Near Joliet 29 | Greenfield | — | — | 4.6 yrs | 61.8 |
| UNKNOWN122306 | Substation-Adjacent | 138 kV | 100 MW | 3.8 yrs | 61.5 |
| ELWOOD | Substation-Adjacent | 345 kV | 600 MW | 3.8 yrs | 61.0 |
| EC Coal Will County | Greenfield | — | — | 4.6 yrs | 60.9 |
| EC Coal Will County | Greenfield | — | — | 4.6 yrs | 60.5 |
| UNKNOWN124428 | Substation-Adjacent | 138 kV | 100 MW | 3.8 yrs | 60.2 |
| EC Coal Will County | Greenfield | — | — | 4.6 yrs | 60.2 |
| EC FFE Will County | Greenfield | — | — | 4.6 yrs | 59.9 |
| DEADEND167148 | Substation-Adjacent | 138 kV | 100 MW | 3.8 yrs | 59.7 |
| UNKNOWN156629 | Substation-Adjacent | 138 kV | 100 MW | 3.8 yrs | 59.7 |
| EC Near Joliet 29 | Greenfield | — | — | 4.6 yrs | 59.6 |
| EC Coal Will County | Greenfield | — | — | 4.6 yrs | 59.5 |
| UNKNOWN121987 | Substation-Adjacent | 138 kV | 100 MW | 3.8 yrs | 59.4 |
Will datacenter FAQ
- How many datacenter sites are in Will?
- 111 scored datacenter candidate sites, averaging 61.8/100 DC Readiness.
- Does Will offer datacenter tax incentives?
- Enterprise Zone sales tax exemption; High Impact Business designation for $12M+ DC investments.
- What is the natural-hazard risk in Will?
- FEMA's National Risk Index rates Will as "Relatively High" (score 35).
- What are industrial electricity rates in Will?
- Average industrial electricity is 5.29¢/kWh and commercial is 8.86¢/kWh in Will.
Dataset updated . Screening estimates derived from public data sources.