Rock has 100 scored datacenter candidate sites averaging 56.5/100 DC Readiness, with a catalogued aggregate of 4,450 MW. FEMA rates local natural-hazard risk as "Relatively Low". The county has a datacenter tax incentive on record.

At a glance

Rock, Wisconsin has 100 scored datacenter candidate sites averaging 56.5/100 DC Readiness, roughly in line with the Wisconsin average of 55.4. It ranks 5th of 72 Wisconsin counties by number of sites and 13th by average score. The top-scoring site is KITTYHAWK at 64.6/100.

100
Candidate sites
56.5/100
Avg DC Readiness
4,450 MW
Catalogued capacity
theoretical aggregate
Relatively Low
Hazard rating
◆ Loading map…
≥ 7560–7540–60≤ 40
Top 25 in Rock

Site-selection context for Rock

Yessales_tax_exemption
Datacenter tax incentive
11.93¢/kWh
Commercial electricity
7.76¢/kWh
Industrial electricity
16
Fiber providers
Low
Water stress
$8,459
Land price / acre
600
Cooling degree days
7,200
Heating degree days
44°F
Mean annual temp

Incentive detail: Enterprise Zone tax credits; TIF available for DC construction in eligible areas.

How does Rock compare with other counties in Wisconsin?

By number of scored sites, Rock ranks 5th of the 72 Wisconsin counties with a county page, holding 3.0% of the state's 3,340 sites. Its average DC Readiness of 56.5/100 ranks 13th in the state and is roughly in line with the national average of 53.0. Nationally it has the 322nd-largest site inventory of 2,964 counties with five or more sites. 0 sites score 70 or higher and 65 score 55 or higher.

What types of datacenter sites are in Rock?

Substation-Adjacent sites are the most common (47, 47% of the county's inventory), followed by greenfield (23) and industrial (14). Site type reflects how the parcel was identified — next to a substation, on a former mine or brownfield, on industrial or federal excess land — and is scored on the same 14 factors either way.

What are power cost, hazard, water and fiber conditions in Rock?

Industrial electricity averages 7.76¢/kWh and commercial 11.93¢/kWh. FEMA's National Risk Index rates the county "Relatively Low" (22). WRI water stress is low. 16 fiber providers report service in the county. The climate runs 600 cooling degree days a year with a mean temperature of 44°F. Land is valued around $8,459 an acre.

By site type

Top datacenter sites in Rock

Top datacenter sites in Rock
SiteTypeVoltageCapacityQueue waitScore
KITTYHAWKSubstation-Adjacent345 kV600 MW4.3 yrs64.6
PADDOCKSubstation-Adjacent345 kV600 MW4.3 yrs64.4
EC Near SheepskinGreenfield——4.3 yrs62.9
EC Near SheepskinGreenfield——4.3 yrs62.2
ROCK RIVERSubstation-Adjacent138 kV100 MW4.3 yrs61.4
EC Near SheepskinGreenfield——4.3 yrs60.7
EC Near Rock RiverGreenfield——4.3 yrs60.0
EC Near SheepskinGreenfield——4.3 yrs60.0
EC Near SheepskinGreenfield——4.3 yrs59.8
EC Near SheepskinGreenfield——4.3 yrs59.7
EC Near SheepskinGreenfield——4.3 yrs59.7
WILCOXSubstation-Adjacent138 kV100 MW4.3 yrs59.6
EC Near Rock RiverGreenfield——4.3 yrs59.5
REC BRADFORDSubstation-Adjacent138 kV100 MW4.3 yrs59.4
BLACKHAWK SW YDSubstation-Adjacent138 kV100 MW4.3 yrs59.4
RUSSELLSubstation-Adjacent138 kV100 MW4.3 yrs59.3
UNKNOWN136972Substation-Adjacent138 kV100 MW4.3 yrs59.3
BASS CREEKSubstation-Adjacent138 kV100 MW4.3 yrs59.2
EC Near BlackhawkGreenfield——4.7 yrs59.1
EC Near Rock RiverGreenfield——4.3 yrs59.1
EC Near Rock RiverGreenfield——4.3 yrs59.0
JANESVILLE GENERALSubstation-Adjacent138 kV100 MW4.3 yrs59.0
REC LAPRAIRIESubstation-Adjacent138 kV100 MW4.3 yrs58.9
EAST BELOITSubstation-Adjacent138 kV100 MW4.3 yrs58.9
JANESVILLE GENERAL SW YDSubstation-Adjacent138 kV100 MW4.3 yrs58.9

Every scored site in Rock

All 100 sites, best first.

Rock datacenter FAQ

How many datacenter sites are in Rock?

100 scored datacenter candidate sites, averaging 56.5/100 DC Readiness. That is the 5th-most of 72 Wisconsin counties with five or more sites.

What is the highest-scoring datacenter site in Rock?

KITTYHAWK scores 64.6/100 DC Readiness, the highest of the 100 scored sites in Rock (a substation-adjacent site).

Does Rock offer datacenter tax incentives?

Enterprise Zone tax credits; TIF available for DC construction in eligible areas.

What is the natural-hazard risk in Rock?

FEMA's National Risk Index rates Rock as "Relatively Low" (score 22).

What are industrial electricity rates in Rock?

Average industrial electricity is 7.76¢/kWh and commercial is 11.93¢/kWh in Rock.

More in Wisconsin

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published November 13, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Datacenter candidate sites in Rock, Wisconsin”, https://gridcensus.com/datacenter-sites/wisconsin/rock (data as of November 13, 2026).

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

Every site and score for Rock, Wisconsin is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.