Datacenter Sites in Bedford County, Virginia

Bedford County has 52 scored datacenter candidate sites averaging 52.2/100 DC Readiness, with a catalogued aggregate of 800 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.

At a glance

Bedford County, Virginia has 52 scored datacenter candidate sites averaging 52.2/100 DC Readiness, roughly in line with the Virginia average of 52.2. It ranks 32nd of 122 Virginia counties by number of sites and 60th by average score. The top-scoring site is Substation-Adjacent site · 89bf3c02 at 57.8/100.

52
Candidate sites
52.2/100
Avg DC Readiness
800 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
◆ Loading map…
≥ 7560–7540–60≤ 40
Top 25 in Bedford County

Site-selection context for Bedford County

Yessales_tax_exemption
Datacenter tax incentive
7.94¢/kWh
Commercial electricity
5.89¢/kWh
Industrial electricity
6
Fiber providers
Low
Water stress
$5,539
Land price / acre
1,300
Cooling degree days
4,000
Heating degree days
55°F
Mean annual temp

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

How does Bedford County compare with other counties in Virginia?

By number of scored sites, Bedford County ranks 32nd of the 122 Virginia counties with a county page, holding 0.9% of the state's 5,871 sites. Its average DC Readiness of 52.2/100 ranks 60th in the state and is roughly in line with the national average of 53.0. Nationally it has the 726th-largest site inventory of 2,964 counties with five or more sites. 0 sites score 70 or higher and 9 score 55 or higher.

What types of datacenter sites are in Bedford County?

Manufacturing sites are the most common (22, 42% of the county's inventory), followed by shovel-ready (12) and industrial (8). Site type reflects how the parcel was identified — next to a substation, on a former mine or brownfield, on industrial or federal excess land — and is scored on the same 14 factors either way.

What are power cost, hazard, water and fiber conditions in Bedford County?

Industrial electricity averages 5.89¢/kWh and commercial 7.94¢/kWh. FEMA's National Risk Index rates the county "Relatively Moderate" (30). WRI water stress is low. 6 fiber providers report service in the county. The climate runs 1,300 cooling degree days a year with a mean temperature of 55°F. Land is valued around $5,539 an acre.

By site type

Top datacenter sites in Bedford County

Top datacenter sites in Bedford County
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN147624Substation-Adjacent138 kV100 MW5.1 yrs57.8
UNKNOWN162227Substation-Adjacent138 kV100 MW5.1 yrs57.2
CENTERVILLESubstation-Adjacent138 kV100 MW5.1 yrs57.2
MOSELEYSubstation-Adjacent138 kV100 MW5.1 yrs57.2
MONETASubstation-Adjacent138 kV100 MW5.1 yrs57.2
ROCKCASTLESubstation-Adjacent138 kV100 MW5.1 yrs57.0
UNKNOWN121376Substation-Adjacent138 kV100 MW5.1 yrs57.0
OZ BedfordGreenfield——5.1 yrs56.5
UNKNOWN121375Substation-Adjacent138 kV100 MW5.1 yrs56.2
New London Business and Technology CenterShovel-Ready——5.1 yrs52.0
Lot 16 - New London Business and Technology CenterShovel-Ready——5.1 yrs51.8
PERMAGRAIN PRODUCTS, INC. (NOT AVAILABLE)Manufacturing——5.1 yrs51.7
ATCO PRODUCTS, INC. (GASKET, PACKING, AND SEALING DEVICE MANUFACTURING)Manufacturing——5.1 yrs51.7
SECKMAN PRINTING (OTHER COMMERCIAL PRINTING)Manufacturing——5.1 yrs51.7
GEORGIA-PACIFIC CORP. (ALL OTHER CONVERTED PAPER PRODUCT MANUFACTURING)Manufacturing——5.1 yrs51.7
AUTOMATED INDUSTRIAL TECHNOLOGIES, INC. (MACHINE SHOPS)Manufacturing——5.1 yrs51.7
INTERCON, INC. (OTHER ELECTRONIC COMPONENT MANUFACTURING)Manufacturing——5.1 yrs51.7
SCOTT'S CABINET, INC. (WOOD KITCHEN CABINET AND COUNTERTOP MANUFACTURING)Manufacturing——5.1 yrs51.7
FORESTRY EQUIPMENT OF VIRGINIA, INC. (CONSTRUCTION MACHINERY MANUFACTURING)Manufacturing——5.1 yrs51.7
MAIL AMERICA COMMUNICATION, INC. (COMMERCIAL LITHOGRAPHIC PRINTING)Manufacturing——5.1 yrs51.7
GAMMAPAR, LLC (NOT AVAILABLE)Manufacturing——5.1 yrs51.7
SENTRY EQUIPMENT ERECTORS, INC. (CONVEYOR AND CONVEYING EQUIPMENT MANUFACTURING)Manufacturing——5.1 yrs51.6
ANDREW CORP. (RADIO AND TELEVISION BROADCASTING AND WIRELESS COMMUNICATIONS EQUIPMENT MANUFACTURING)Manufacturing——5.1 yrs51.6
INNOVATIVE MACHINING, INC. (MACHINE SHOPS)Manufacturing——5.1 yrs51.6
FERGUSON ENTERPRISES, INC. (FABRICATED PIPE AND PIPE FITTING MANUFACTURING)Manufacturing——5.1 yrs51.6

Every scored site in Bedford County

All 52 sites, best first.

Bedford County datacenter FAQ

How many datacenter sites are in Bedford County?

52 scored datacenter candidate sites, averaging 52.2/100 DC Readiness. That is the 32nd-most of 122 Virginia counties with five or more sites.

What is the highest-scoring datacenter site in Bedford County?

Substation-Adjacent site · 89bf3c02 scores 57.8/100 DC Readiness, the highest of the 52 scored sites in Bedford County (a substation-adjacent site).

Does Bedford County offer datacenter tax incentives?

Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

What is the natural-hazard risk in Bedford County?

FEMA's National Risk Index rates Bedford County as "Relatively Moderate" (score 30).

What are industrial electricity rates in Bedford County?

Average industrial electricity is 5.89¢/kWh and commercial is 7.94¢/kWh in Bedford County.

More in Virginia

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published November 12, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Datacenter candidate sites in Bedford County, Virginia”, https://gridcensus.com/datacenter-sites/virginia/bedford-county (data as of November 12, 2026).

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

Every site and score for Bedford County, Virginia is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.