Datacenter Sites in Catawba, North Carolina
Catawba has 71 scored datacenter candidate sites averaging 55.8/100 DC Readiness, with a catalogued aggregate of 3,661 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
71
Candidate sites
55.8/100
Avg DC Readiness
3,661 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Catawba
Yessales_tax_exemption
Datacenter tax incentive
10.38¢/kWh
Commercial electricity
7.12¢/kWh
Industrial electricity
9
Fiber providers
Low
Water stress
$7,785
Land price / acre
1,600
Cooling degree days
3,300
Heating degree days
59°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment and electricity for $75M+ investments; property tax abatement.
By site type
Top datacenter sites in Catawba
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| EC Near Apple Data Center - Fuel Cell 1&2 | Greenfield | — | — | 4.3 yrs | 59.3 |
| LONGVIEW | Substation-Adjacent | 230 kV | 300 MW | 3.8 yrs | 58.5 |
| EC Near Maiden Finger Street | Greenfield | — | — | 4.3 yrs | 58.4 |
| MARSHALL STEAM STATION | Substation-Adjacent | 230 kV | 300 MW | 3.8 yrs | 56.7 |
| EC Near Maiden Finger Street | Greenfield | — | — | 4.3 yrs | 56.6 |
| EC Near Maiden Finger Street | Greenfield | — | — | 4.3 yrs | 56.5 |
| EC Near Maiden Finger Street | Greenfield | — | — | 4.3 yrs | 56.1 |
| EC Near Apple Data Center - Fuel Cell 1&2 | Greenfield | — | — | 4.3 yrs | 56.0 |
| EC Near Apple Data Center - Fuel Cell 1&2 | Greenfield | — | — | 4.3 yrs | 56.0 |
| OZ Catawba | Greenfield | — | — | 4.3 yrs | 55.3 |
| EC Near Maiden Finger Street | Greenfield | — | — | 4.3 yrs | 55.1 |
| EC Near Apple Data Center - Fuel Cell 1&2 | Greenfield | — | — | 4.3 yrs | 54.9 |
| EC Near Maiden Finger Street | Greenfield | — | — | 4.3 yrs | 53.9 |
| UNKNOWN111147 | Substation-Adjacent | 100 kV | 50 MW | 3.8 yrs | 53.0 |
| EC Near Apple Data Center - Fuel Cell 1&2 | Greenfield | — | — | 4.3 yrs | 53.0 |
| TAP152520 | Substation-Adjacent | 100 kV | 50 MW | 3.8 yrs | 52.9 |
| EC Near Apple Data Center - Fuel Cell 1&2 | Greenfield | — | — | 4.3 yrs | 52.7 |
| UNKNOWN110944 | Substation-Adjacent | 100 kV | 50 MW | 3.8 yrs | 52.6 |
| UNKNOWN110974 | Substation-Adjacent | 100 kV | 50 MW | 3.8 yrs | 52.5 |
| UNKNOWN152552 | Substation-Adjacent | 100 kV | 50 MW | 3.8 yrs | 52.4 |
| UNKNOWN110948 | Substation-Adjacent | 100 kV | 50 MW | 3.8 yrs | 52.3 |
| UNKNOWN110949 | Substation-Adjacent | 100 kV | 50 MW | 3.8 yrs | 52.1 |
| UNKNOWN110975 | Substation-Adjacent | 100 kV | 50 MW | 3.8 yrs | 52.0 |
| UNKNOWN110951 | Substation-Adjacent | 100 kV | 50 MW | 3.8 yrs | 51.8 |
| UNKNOWN110947 | Substation-Adjacent | 100 kV | 50 MW | 3.8 yrs | 51.6 |
Catawba datacenter FAQ
- How many datacenter sites are in Catawba?
- 71 scored datacenter candidate sites, averaging 55.8/100 DC Readiness.
- Does Catawba offer datacenter tax incentives?
- Sales tax exemption on DC equipment and electricity for $75M+ investments; property tax abatement.
- What is the natural-hazard risk in Catawba?
- FEMA's National Risk Index rates Catawba as "Relatively High" (score 42).
- What are industrial electricity rates in Catawba?
- Average industrial electricity is 7.12¢/kWh and commercial is 10.38¢/kWh in Catawba.
Dataset updated . Screening estimates derived from public data sources.