Moretz Mill

Industrial

Catawba, North Carolina · SERC

DC Readiness
52.8
Fair / 100

Moretz Mill is an industrial datacenter candidate site in Catawba, North Carolina, interconnecting through SERC. It screens at 52.8/100 DC Readiness and a 5.3 yrs average interconnection-queue wait.

Power & interconnection

UtilityDUKE ENERGY CAROLINAS, LLCinvestor ownedmoderate to large load · terms ≥ 100 MWLarge Load Customer terms (≥100 MW): minimum bills, contract demand · 10 yr

Speed to power

Interconnection outlookConstrained
≈ 5.3 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionSERC
Queue depth177
Avg queue wait5.3 yrs
Recent queue wait5.3 yrs
Completion rate14%
Withdrawal rate86%

Connectivity

Nearest IXP801 Main Street - Lenoir
IXP distance17.8 mi
Fiber providers9
Fiber coverage29.2%

Site characteristics

Site typeIndustrial

Risk & environment

Environmental constraintNone (0/100)
Flood zoneZone X
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score58/100

Location context

Nearest datacenterDatacenter 00873137563
DC distance10.5 mi
County hazard (FEMA NRI)Relatively High (42)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.38¢/kWh
Industrial electricity7.12¢/kWh
Cooling degree days1,600
Heating degree days3,300
Land price / acre$7,785

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Sales tax exemption on DC equipment and electricity for $75M+ investments; property tax abatement.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track Moretz Mill

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
55
Fiber connectivity12%
69
Energy cost10%
50
Water risk7%
84
Natural hazard6%
58
Buildability7%
50
Labor market4%
50
DC cluster4%
80
Land / acreage3%
46
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
45

Nearby comparable sites

Other scored datacenter candidate sites in Catawba, ranked by DC Readiness.

Sites near Moretz Mill
SiteTypeVoltageCapacityQueue waitScore
LONGVIEWSubstation-Adjacent230 kV300 MW5.3 yrs63.4
MARSHALL STEAM STATIONSubstation-Adjacent230 kV300 MW5.3 yrs62.1
EC Near Apple Data Center - Fuel Cell 1&2Greenfield——5.3 yrs61.5
EC Near Maiden Finger StreetGreenfield——5.3 yrs60.6
EC Near Maiden Finger StreetGreenfield——5.3 yrs58.8
EC Near Maiden Finger StreetGreenfield——5.3 yrs58.8
EC Near Maiden Finger StreetGreenfield——5.3 yrs58.4
EC Near Apple Data Center - Fuel Cell 1&2Greenfield——5.3 yrs58.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Moretz Mill, Catawba is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.