Substation-Adjacent site at 35.645, -81.250

Substation-Adjacent

Catawba, North Carolina · SERC

DC Readiness
56.4
Good / 100

At a glance

Substation-Adjacent site at 35.645, -81.250 is a substation-adjacent datacenter candidate site in Catawba, North Carolina, scoring 56.4/100 DC Readiness — 31st of 68 scored sites in the county. Its nearest substation is UNKNOWN110969 (0 mi, 100 kV). It sits in the SERC grid region and the DUKE ENERGY CAROLINAS, LLC service territory, where interconnection has averaged 5.3 years from request to operation. GridCensus catalogs 50 MW of candidate capacity here.

Power & interconnection

Nearest substationUNKNOWN110969
Substation distance0.0 mi
Substation voltage100 kV
Available capacity50 MW
UtilityDUKE ENERGY CAROLINAS, LLCinvestor ownedmoderate to large load · terms ≥ 100 MWLarge Load Customer terms (≥100 MW): minimum bills, contract demand · 10 yr

Speed to power

Interconnection outlookConstrained
≈ 5.3 yrs typical interconnection wait

Deep queue and long historical waits — plan for a multi-year interconnection timeline and engage the utility early.

ISO / RTO regionSERC
Queue depth177
Avg queue wait5.3 yrs
Recent queue wait5.3 yrs
Completion rate14%
Withdrawal rate86%

Connectivity

Nearest IXP801 Main Street - Lenoir
IXP distance25.3 mi
Fiber providers9
Fiber coverage29.2%

Site characteristics

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score58/100

Location context

Nearest datacenterDatacenter 00873137563
DC distance3.9 mi
County hazard (FEMA NRI)Relatively High (42)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.38¢/kWh
Industrial electricity7.12¢/kWh
Cooling degree days1,600
Heating degree days3,300
Land price / acre$7,785

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: Sales tax exemption on DC equipment and electricity for $75M+ investments; property tax abatement.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track UNKNOWN110969

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

How does Substation-Adjacent site at 35.645, -81.250 compare with other sites in Catawba?

Substation-Adjacent site at 35.645, -81.250 ranks 31st of 68 scored candidate sites in Catawba. Its 56.4/100 is roughly in line with the county average of 55.4. It is roughly in line with the North Carolina average of 55.1 and roughly in line with the national average of 53.2.

Against the North Carolina average, its strongest sub-score is power availability (49 vs 42) and its weakest is fiber connectivity (62 vs 70). Power and speed to power each carry 20% of the composite score, fiber 12%, water 7% and hazard 6%.

How close is Substation-Adjacent site at 35.645, -81.250 to power, fiber and other datacenters?

The nearest mapped substation, UNKNOWN110969, is about 0 miles away and operates at 100 kV. For connectivity, the nearest internet exchange facility is 801 Main Street - Lenoir at 25.3 miles. 9 fiber providers report service at the location in FCC broadband data. The closest operating datacenter on record is Datacenter 00873137563, 3.9 miles away.

What are the flood, water and hazard risks at Substation-Adjacent site at 35.645, -81.250?

At the county level, FEMA's National Risk Index rates Catawba "Relatively High".

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
49
Speed to power20%
55
Fiber connectivity12%
62
Energy cost10%
50
Water risk7%
84
Natural hazard6%
58
Buildability7%
60
Labor market4%
50
DC cluster4%
80
Land / acreage3%
46
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
45

Nearby comparable sites

Other scored datacenter candidate sites in Catawba, ranked by DC Readiness.

Sites near Substation-Adjacent site at 35.645, -81.250
SiteTypeVoltageCapacityQueue waitScore
LONGVIEWSubstation-Adjacent230 kV300 MW5.3 yrs63.4
MARSHALL STEAM STATIONSubstation-Adjacent230 kV300 MW5.3 yrs62.1
EC Near Apple Data Center - Fuel Cell 1&2Greenfield——5.3 yrs61.5
EC Near Maiden Finger StreetGreenfield——5.3 yrs60.6
EC Near Maiden Finger StreetGreenfield——5.3 yrs58.8
EC Near Maiden Finger StreetGreenfield——5.3 yrs58.8
EC Near Maiden Finger StreetGreenfield——5.3 yrs58.4
EC Near Apple Data Center - Fuel Cell 1&2Greenfield——5.3 yrs58.3

Substation-Adjacent site at 35.645, -81.250: common questions

What is the DC Readiness score of Substation-Adjacent site at 35.645, -81.250?

Substation-Adjacent site at 35.645, -81.250 scores 56.4/100 on the GridCensus DC Readiness scale, rated good. It ranks 31st of 68 scored sites in Catawba. The Catawba average is 55.4 and the North Carolina average is 55.1.

What is the nearest substation to Substation-Adjacent site at 35.645, -81.250?

The nearest mapped substation is UNKNOWN110969, about 0 miles away, at 100 kV. GridCensus catalogs 50 MW of candidate capacity for the site.

Which electric utility serves Substation-Adjacent site at 35.645, -81.250?

DUKE ENERGY CAROLINAS, LLC (investor owned) holds the retail service territory that contains the site; its holding company is DUKE ENERGY CORP.

What grid region is Substation-Adjacent site at 35.645, -81.250 in?

Substation-Adjacent site at 35.645, -81.250 is in the SERC region. Projects interconnecting there have averaged a 5.3-year wait from queue request to operation.

How far is Substation-Adjacent site at 35.645, -81.250 from an internet exchange?

The nearest internet exchange facility is 801 Main Street - Lenoir, about 25.3 miles away; 9 fiber providers report service at the location.

Related pages

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published October 10, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Substation-Adjacent site at 35.645, -81.250, Catawba, NC”, https://gridcensus.com/datacenter-sites/north-carolina/catawba/unknown110969-948b7c88 (data as of October 10, 2026).

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for Substation-Adjacent site at 35.645, -81.250, Catawba is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.