Datacenter Sites in Phelps County, Missouri
Phelps County has 32 scored datacenter candidate sites averaging 51.0/100 DC Readiness, with a catalogued aggregate of 451 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
32
Candidate sites
51.0/100
Avg DC Readiness
451 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Phelps County
Yessales_tax_exemption
Datacenter tax incentive
10.96¢/kWh
Commercial electricity
7.82¢/kWh
Industrial electricity
9
Fiber providers
Low
Water stress
$3,912
Land price / acre
1,500
Cooling degree days
4,700
Heating degree days
56°F
Mean annual temp
Incentive detail: Qualified data center sales tax exemption (2019 law); state income tax credits.
By site type
Top datacenter sites in Phelps County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| Busy Bee's Laundry | Brownfield | — | 1 MW | 2.8 yrs | 62.0 |
| EC Coal Phelps County | Greenfield | — | — | 1.4 yrs | 59.9 |
| EC Coal Phelps County | Greenfield | — | — | 1.4 yrs | 56.7 |
| EC Coal Phelps County | Greenfield | — | — | 1.4 yrs | 55.7 |
| TAP138938 | Substation-Adjacent | 138 kV | 100 MW | 2.8 yrs | 55.1 |
| EC Coal Phelps County | Greenfield | — | — | 1.4 yrs | 54.5 |
| UNKNOWN117762 | Substation-Adjacent | 161 kV | 100 MW | 2.8 yrs | 54.4 |
| UNKNOWN117858 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.7 |
| UNKNOWN117888 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.6 |
| UNKNOWN117761 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.6 |
| UNKNOWN117907 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.6 |
| UNKNOWN117892 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.5 |
| EC Coal Phelps County | Greenfield | — | — | 1.4 yrs | 50.9 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 48.8 |
| Public Work Yard | Industrial | — | — | 2.8 yrs | 48.8 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 48.8 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 48.7 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 48.7 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 48.5 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 48.5 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 48.5 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 48.5 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 48.5 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 48.5 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 48.5 |
Phelps County datacenter FAQ
- How many datacenter sites are in Phelps County?
- 32 scored datacenter candidate sites, averaging 51.0/100 DC Readiness.
- Does Phelps County offer datacenter tax incentives?
- Qualified data center sales tax exemption (2019 law); state income tax credits.
- What is the natural-hazard risk in Phelps County?
- FEMA's National Risk Index rates Phelps County as "Relatively High" (score 38).
- What are industrial electricity rates in Phelps County?
- Average industrial electricity is 7.82¢/kWh and commercial is 10.96¢/kWh in Phelps County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Phelps County, Missouri. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.