Datacenter Sites in Franklin County, Missouri

Franklin County has 16 scored datacenter candidate sites averaging 52.3/100 DC Readiness, with a catalogued aggregate of 1,600 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.

At a glance

Franklin County, Missouri has 16 scored datacenter candidate sites averaging 52.3/100 DC Readiness, roughly in line with the Missouri average of 55.7. It ranks 54th of 110 Missouri counties by number of sites and 93rd by average score. The top-scoring site is LABADIE at 62.8/100.

16
Candidate sites
52.3/100
Avg DC Readiness
1,600 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
◆ Loading map…
≥ 7560–7540–60≤ 40
Top 16 in Franklin County

Site-selection context for Franklin County

Yessales_tax_exemption
Datacenter tax incentive
10.39¢/kWh
Commercial electricity
7.71¢/kWh
Industrial electricity
7
Fiber providers
Low
Water stress
$5,647
Land price / acre
1,500
Cooling degree days
4,700
Heating degree days
56°F
Mean annual temp

Incentive detail: Qualified data center sales tax exemption (2019 law); state income tax credits.

How does Franklin County compare with other counties in Missouri?

By number of scored sites, Franklin County ranks 54th of the 110 Missouri counties with a county page, holding 0.5% of the state's 3,413 sites. Its average DC Readiness of 52.3/100 ranks 93rd in the state and is roughly in line with the national average of 53.0. Nationally it has the 1960th-largest site inventory of 2,964 counties with five or more sites. 0 sites score 70 or higher and 4 score 55 or higher.

What types of datacenter sites are in Franklin County?

Substation-Adjacent sites are the most common (6, 38% of the county's inventory), followed by industrial (5) and former mine (4). Site type reflects how the parcel was identified — next to a substation, on a former mine or brownfield, on industrial or federal excess land — and is scored on the same 14 factors either way.

What are power cost, hazard, water and fiber conditions in Franklin County?

Industrial electricity averages 7.71¢/kWh and commercial 10.39¢/kWh. FEMA's National Risk Index rates the county "Relatively High" (38). WRI water stress is low. 7 fiber providers report service in the county. The climate runs 1,500 cooling degree days a year with a mean temperature of 56°F. Land is valued around $5,647 an acre.

By site type

Top datacenter sites in Franklin County

Top datacenter sites in Franklin County
SiteTypeVoltageCapacityQueue waitScore
LABADIESubstation-Adjacent345 kV600 MW4.3 yrs62.8
GRAY SUMMITSubstation-Adjacent345 kV600 MW4.3 yrs62.4
UNKNOWN117772Substation-Adjacent138 kV100 MW4.3 yrs55.3
TAP140565Substation-Adjacent138 kV100 MW4.3 yrs55.1
UNKNOWN121661Substation-Adjacent69 kV50 MW4.3 yrs52.9
UNKNOWN121662Substation-Adjacent69 kV50 MW4.3 yrs52.7
Mine SiteFormer Mine——3.9 yrs50.9
Ahrens Sales and ServiceIndustrial——3.9 yrs50.9
Mine SiteFormer Mine——4.3 yrs50.7
Greenfield (UNKNOWN117887 - GRAY SUMMIT (1)Greenfield138 kV100 MW4.3 yrs50.4
Union Corporate Lot 13-2Industrial——4.3 yrs48.9
Mitchell BuildingIndustrial——4.3 yrs48.8
Mine SiteFormer Mine——4.3 yrs48.8
North Building, Kellwood, American Recreation ProdIndustrial——4.3 yrs48.8
Mine SiteFormer Mine——4.3 yrs48.5
Zero BuildingIndustrial——4.3 yrs48.2

Every scored site in Franklin County

All 16 sites, best first.

Franklin County datacenter FAQ

How many datacenter sites are in Franklin County?

16 scored datacenter candidate sites, averaging 52.3/100 DC Readiness. That is the 54th-most of 110 Missouri counties with five or more sites.

What is the highest-scoring datacenter site in Franklin County?

LABADIE scores 62.8/100 DC Readiness, the highest of the 16 scored sites in Franklin County (a substation-adjacent site).

Does Franklin County offer datacenter tax incentives?

Qualified data center sales tax exemption (2019 law); state income tax credits.

What is the natural-hazard risk in Franklin County?

FEMA's National Risk Index rates Franklin County as "Relatively High" (score 38).

What are industrial electricity rates in Franklin County?

Average industrial electricity is 7.71¢/kWh and commercial is 10.39¢/kWh in Franklin County.

More in Missouri

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published November 12, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Datacenter candidate sites in Franklin County, Missouri”, https://gridcensus.com/datacenter-sites/missouri/franklin-county (data as of November 12, 2026).

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

Every site and score for Franklin County, Missouri is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.