Datacenter Sites in Andrew County, Missouri
Andrew County has 17 scored datacenter candidate sites averaging 56.6/100 DC Readiness, with a catalogued aggregate of 4,200 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
17
Candidate sites
56.6/100
Avg DC Readiness
4,200 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Andrew County
Yessales_tax_exemption
Datacenter tax incentive
9.57¢/kWh
Commercial electricity
6.88¢/kWh
Industrial electricity
3
Fiber providers
Low
Water stress
$5,070
Land price / acre
1,500
Cooling degree days
4,700
Heating degree days
56°F
Mean annual temp
Incentive detail: Qualified data center sales tax exemption (2019 law); state income tax credits.
By site type
Top datacenter sites in Andrew County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| HAWTHORNE | Substation-Adjacent | 345 kV | 600 MW | 3.5 yrs | 74.2 |
| UNKNOWN117698 | Substation-Adjacent | 161 kV | 100 MW | 3.5 yrs | 67.2 |
| UNKNOWN118628 | Substation-Adjacent | 161 kV | 100 MW | 3.5 yrs | 65.5 |
| Greenfield (COOPER - SAINT JOSEPH) | Greenfield | 345 kV | 600 MW | 3.5 yrs | 64.8 |
| Greenfield (COOPER - FAIRPORT) | Greenfield | 345 kV | 600 MW | 3.5 yrs | 62.9 |
| Greenfield (COOPER - SAINT JOSEPH) | Greenfield | 345 kV | 600 MW | 3.5 yrs | 61.6 |
| Greenfield (FAIRPORT - SAINT JOSEPH) | Greenfield | 345 kV | 600 MW | 3.5 yrs | 61.3 |
| Greenfield (UNKNOWN118628 - SAINT JOSEPH) | Greenfield | 161 kV | 100 MW | 3.5 yrs | 61.0 |
| Greenfield (COOPER - FAIRPORT) | Greenfield | 345 kV | 600 MW | 3.5 yrs | 61.0 |
| Greenfield (UNKNOWN118625 - UNKNOWN118628) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 58.0 |
| Greenfield (UNKNOWN118628 - SAINT JOSEPH) | Greenfield | 161 kV | 100 MW | 3.5 yrs | 58.0 |
| Greenfield (UNKNOWN118628 - SAINT JOSEPH) | Greenfield | 161 kV | 100 MW | 3.5 yrs | 54.7 |
| ST. JOSEPH, MISSOURI | Federal Excess | — | — | — | 42.7 |
| Mine Site | Former Mine | — | — | — | 42.5 |
| Mine Site | Former Mine | — | — | — | 42.5 |
| Mine Site | Former Mine | — | — | — | 42.4 |
| Mine Site | Former Mine | — | — | — | 42.4 |
Andrew County datacenter FAQ
- How many datacenter sites are in Andrew County?
- 17 scored datacenter candidate sites, averaging 56.6/100 DC Readiness.
- Does Andrew County offer datacenter tax incentives?
- Qualified data center sales tax exemption (2019 law); state income tax credits.
- What is the natural-hazard risk in Andrew County?
- FEMA's National Risk Index rates Andrew County as "Relatively High" (score 38).
- What are industrial electricity rates in Andrew County?
- Average industrial electricity is 6.88¢/kWh and commercial is 9.57¢/kWh in Andrew County.
Dataset updated . Screening estimates derived from public data sources.