Datacenter Sites in Levy County, Florida
Levy County has 12 scored datacenter candidate sites averaging 55.8/100 DC Readiness, with a catalogued aggregate of 1,500 MW. FEMA rates local natural-hazard risk as "Very High". The county has a datacenter tax incentive on record.
12
Candidate sites
55.8/100
Avg DC Readiness
1,500 MW
Catalogued capacity
theoretical aggregate
Very High
Hazard rating
Site-selection context for Levy County
Yessales_tax_exemption
Datacenter tax incentive
12.36¢/kWh
Commercial electricity
8.90¢/kWh
Industrial electricity
8
Fiber providers
Low-Medium
Water stress
$6,275
Land price / acre
3,500
Cooling degree days
700
Heating degree days
72°F
Mean annual temp
Incentive detail: Sales tax exemption on manufacturing machinery including servers; no state income tax.
By site type
Top datacenter sites in Levy County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| BRONSON | Substation-Adjacent | 230 kV | 300 MW | 1.0 yrs | 59.7 |
| OZ Levy | Greenfield | — | — | 3.6 yrs | 59.3 |
| EC Coal Levy County | Greenfield | — | — | 3.6 yrs | 55.9 |
| TAP154672 | Substation-Adjacent | 69 kV | 50 MW | 1.0 yrs | 52.5 |
| UNKNOWN120450 | Substation-Adjacent | 69 kV | 50 MW | 1.0 yrs | 52.5 |
| TAP154671 | Substation-Adjacent | 69 kV | 50 MW | 1.0 yrs | 52.5 |
| TAP154670 | Substation-Adjacent | 69 kV | 50 MW | 1.0 yrs | 52.5 |
| UNKNOWN154652 | Substation-Adjacent | 69 kV | 50 MW | 1.0 yrs | 52.5 |
| UNKNOWN108156 | Substation-Adjacent | 69 kV | 50 MW | 1.0 yrs | 52.5 |
| Mine Site | Former Mine | — | — | 1.0 yrs | 51.8 |
| UNKNOWN120446 | Substation-Adjacent | 69 kV | 50 MW | 1.0 yrs | 51.3 |
| UNKNOWN108164 | Substation-Adjacent | 69 kV | 50 MW | 1.0 yrs | 51.3 |
| Mine Site | Former Mine | — | — | 1.0 yrs | 50.8 |
| Mine Site | Former Mine | — | — | 3.8 yrs | 48.0 |
| Mine Site | Former Mine | — | — | 3.8 yrs | 46.5 |
| Mine Site | Former Mine | — | — | 3.8 yrs | 46.4 |
Levy County datacenter FAQ
- How many datacenter sites are in Levy County?
- 12 scored datacenter candidate sites, averaging 55.8/100 DC Readiness.
- Does Levy County offer datacenter tax incentives?
- Sales tax exemption on manufacturing machinery including servers; no state income tax.
- What is the natural-hazard risk in Levy County?
- FEMA's National Risk Index rates Levy County as "Very High" (score 55).
- What are industrial electricity rates in Levy County?
- Average industrial electricity is 8.90¢/kWh and commercial is 12.36¢/kWh in Levy County.
Dataset updated . Screening estimates derived from public data sources.