Hernando County has 49 scored datacenter candidate sites averaging 56.0/100 DC Readiness, with a catalogued aggregate of 4,800 MW. FEMA rates local natural-hazard risk as "Very High". The county has a datacenter tax incentive on record.

49
Candidate sites
56.0/100
Avg DC Readiness
4,800 MW
Catalogued capacity
theoretical aggregate
Very High
Hazard rating

Site-selection context for Hernando County

Yessales_tax_exemption
Datacenter tax incentive
11.64¢/kWh
Commercial electricity
7.27¢/kWh
Industrial electricity
9
Fiber providers
Low-Medium
Water stress
$11,831
Land price / acre
3,500
Cooling degree days
700
Heating degree days
72°F
Mean annual temp

Incentive detail: Sales tax exemption on manufacturing machinery including servers; no state income tax.

By site type

Top datacenter sites in Hernando County

Top datacenter sites in Hernando County
SiteTypeVoltageCapacityQueue waitScore
BROOKRIDGESubstation-Adjacent500 kV1,000 MW3.6 yrs75.5
BROOKSVILLE WESTSubstation-Adjacent230 kV300 MW3.6 yrs72.7
TAP154528Substation-Adjacent230 kV300 MW3.6 yrs72.3
UNKNOWN108687Substation-Adjacent115 kV100 MW3.6 yrs68.6
UNKNOWN120186Substation-Adjacent115 kV100 MW3.6 yrs68.4
TAP151117Substation-Adjacent115 kV100 MW3.6 yrs68.2
TAP143147Substation-Adjacent115 kV100 MW3.6 yrs67.3
TWIN COUNTY RANCHSubstation-Adjacent115 kV100 MW3.6 yrs67.0
Greenfield (BROOKRIDGE - CRYSTAL RIVER)Greenfield500 kV1,000 MW3.6 yrs66.0
TAP143153Substation-Adjacent115 kV100 MW3.6 yrs65.9
UNKNOWN123520Substation-Adjacent115 kV100 MW3.6 yrs65.9
Greenfield (BROOKRIDGE - UNKNOWN156846)Greenfield230 kV300 MW3.6 yrs64.9
UNKNOWN124101Substation-Adjacent115 kV100 MW3.6 yrs62.9
TAP151116Substation-Adjacent115 kV100 MW3.6 yrs62.9
UNKNOWN120184Substation-Adjacent115 kV100 MW3.6 yrs62.6
FLORIDA POWER DEVELOPMENTSubstation-Adjacent115 kV100 MW3.6 yrs62.5
UNKNOWN121683Substation-Adjacent115 kV100 MW3.6 yrs62.4
TAP169003Substation-Adjacent115 kV100 MW3.6 yrs62.2
TAP143151Substation-Adjacent115 kV100 MW3.6 yrs61.8
TAP169002Substation-Adjacent115 kV100 MW3.6 yrs61.6
UNKNOWN123521Substation-Adjacent115 kV100 MW3.6 yrs61.4
Greenfield (BROOKRIDGE - TAP169003)Greenfield115 kV100 MW3.6 yrs61.2
TAP143154Substation-Adjacent115 kV100 MW3.6 yrs60.7
UNKNOWN108315Substation-Adjacent115 kV100 MW3.6 yrs59.4
OZ HernandoGreenfield3.6 yrs57.3

Hernando County datacenter FAQ

How many datacenter sites are in Hernando County?
49 scored datacenter candidate sites, averaging 56.0/100 DC Readiness.
Does Hernando County offer datacenter tax incentives?
Sales tax exemption on manufacturing machinery including servers; no state income tax.
What is the natural-hazard risk in Hernando County?
FEMA's National Risk Index rates Hernando County as "Very High" (score 55).
What are industrial electricity rates in Hernando County?
Average industrial electricity is 7.27¢/kWh and commercial is 11.64¢/kWh in Hernando County.

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Hernando County, Florida. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.