DC Readiness
54.3
Fair / 100

UNKNOWN169001 is a substation-adjacent datacenter candidate site in Hernando County, Florida, interconnecting through SERC. It screens at 54.3/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN169001
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW

Speed to power

ISO / RTO regionSERC
Queue depth1
Avg queue wait1.0 yrs

Connectivity

Nearest IXPFlexential - Tampa/North (TPA03)
IXP distance39.9 mi
Fiber providers8
Fiber coverage69.4%

Site characteristics

Risk & environment

Water stress (WRI)Low-Medium
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score45/100

Location context

Nearest datacenterFlexential Tampa - North
DC distance39.9 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.64¢/kWh
Industrial electricity7.27¢/kWh
Cooling degree days3,500
Heating degree days700
Land price / acre$11,831

Incentive detail: Sales tax exemption on manufacturing machinery including servers; no state income tax.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
75
Fiber connectivity12%
37
Energy cost10%
50
Water risk8%
76
Natural hazard8%
45
Buildability7%
60
Labor market4%
50
DC cluster4%
40
Land / acreage3%
40
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
0

Nearby comparable sites

Other scored datacenter candidate sites in Hernando County, ranked by DC Readiness.

Sites near UNKNOWN169001
SiteTypeVoltageCapacityQueue waitScore
BROOKRIDGESubstation-Adjacent500 kV1,000 MW1.0 yrs63.1
BROOKSVILLE WESTSubstation-Adjacent230 kV300 MW1.0 yrs58.7
OZ HernandoGreenfield3.6 yrs57.5
OZ HernandoGreenfield3.6 yrs57.5
UNKNOWN120169Substation-Adjacent115 kV100 MW1.0 yrs55.8
TAP151117Substation-Adjacent115 kV100 MW1.0 yrs55.7
TAP143153Substation-Adjacent115 kV100 MW1.0 yrs55.6
OZ HernandoGreenfield3.6 yrs55.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN169001, Hernando County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.