Datacenter Sites in Douglas County, Washington
Douglas County has 122 scored datacenter candidate sites averaging 53.1/100 DC Readiness, with a catalogued aggregate of 39,000 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.
122
Candidate sites
53.1/100
Avg DC Readiness
39,000 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
Site-selection context for Douglas County
Yessales_tax_exemption
Datacenter tax incentive
4.83¢/kWh
Commercial electricity
3.97¢/kWh
Industrial electricity
5
Fiber providers
Low-Medium
Water stress
$2,784
Land price / acre
300
Cooling degree days
5,000
Heating degree days
48°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment and construction for eligible facilities; no state income tax.
By site type
Top datacenter sites in Douglas County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| GRAND COULEE 500KV | Substation-Adjacent | 500 kV | 1,000 MW | 1.7 yrs | 69.6 |
| GRAND COULEE 230KV | Substation-Adjacent | 500 kV | 1,000 MW | 1.7 yrs | 69.4 |
| GRAND COULEE | Substation-Adjacent | 500 kV | 1,000 MW | 1.7 yrs | 68.8 |
| Greenfield (SCHULTZ - SICKLER) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 68.6 |
| CHIEF JOSEPH | Substation-Adjacent | 500 kV | 1,000 MW | 1.7 yrs | 67.7 |
| Greenfield (CHIEF JOSEPH - SICKLER) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 66.4 |
| FOSTER CREEK | Substation-Adjacent | 230 kV | 300 MW | 1.7 yrs | 66.0 |
| WELLS | Substation-Adjacent | 230 kV | 300 MW | 1.7 yrs | 65.6 |
| Greenfield (CHIEF JOSEPH - MONROE) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 65.3 |
| Greenfield (CHIEF JOSEPH - MONROE) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 64.8 |
| SAINT ANDREWS | Substation-Adjacent | 230 kV | 300 MW | 1.7 yrs | 64.8 |
| TAP206318 | Substation-Adjacent | 115 kV | 100 MW | 1.7 yrs | 64.4 |
| Greenfield (CHIEF JOSEPH - SICKLER) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 64.2 |
| Greenfield (ROCKY REACH - MAPLE VALLEY) | Greenfield | 345 kV | 600 MW | 1.7 yrs | 63.9 |
| Greenfield (GRAND COULEE 500KV - HANFORD) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 63.9 |
| COULEE CITY | Substation-Adjacent | 138 kV | 100 MW | 1.7 yrs | 63.7 |
| Greenfield (CHIEF JOSEPH - SICKLER) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 63.5 |
| Greenfield (GRAND COULEE 500KV - HANFORD) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 63.4 |
| Greenfield (CHIEF JOSEPH - SICKLER) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 63.3 |
| Greenfield (GRAND COULEE 500KV - HANFORD) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 63.2 |
| Greenfield (GRAND COULEE 500KV - CHIEF JOS) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 63.0 |
| Greenfield (GRAND COULEE 500KV - COLUMBIA) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 63.0 |
| Greenfield (GRAND COULEE 500KV - COLUMBIA) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 62.9 |
| Greenfield (GRAND COULEE 500KV - COLUMBIA) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 62.8 |
| Greenfield (GRAND COULEE 500KV - COLUMBIA) | Greenfield | 500 kV | 1,000 MW | 1.7 yrs | 62.6 |
Douglas County datacenter FAQ
- How many datacenter sites are in Douglas County?
- 122 scored datacenter candidate sites, averaging 53.1/100 DC Readiness.
- Does Douglas County offer datacenter tax incentives?
- Sales tax exemption on DC equipment and construction for eligible facilities; no state income tax.
- What is the natural-hazard risk in Douglas County?
- FEMA's National Risk Index rates Douglas County as "Relatively Moderate" (score 28).
- What are industrial electricity rates in Douglas County?
- Average industrial electricity is 3.97¢/kWh and commercial is 4.83¢/kWh in Douglas County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Douglas County, Washington. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.