Datacenter Sites in Prince William, Virginia
Prince William has 137 scored datacenter candidate sites averaging 57.7/100 DC Readiness, with a catalogued aggregate of 6,000 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.
137
Candidate sites
57.7/100
Avg DC Readiness
6,000 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
Site-selection context for Prince William
Yessales_tax_exemption
Datacenter tax incentive
5.55¢/kWh
Commercial electricity
5.41¢/kWh
Industrial electricity
7
Fiber providers
Low
Water stress
$12,336
Land price / acre
1,300
Cooling degree days
4,000
Heating degree days
55°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.
By site type
Top datacenter sites in Prince William
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| BRISTERS | Substation-Adjacent | 500 kV | 1,000 MW | 3.1 yrs | 75.2 |
| NOVEC SMOKETOWN | Substation-Adjacent | 230 kV | 300 MW | 3.1 yrs | 74.0 |
| DUMFRIES | Substation-Adjacent | 230 kV | 300 MW | 3.1 yrs | 73.9 |
| Greenfield (MOSBY - MORRISVILLE) | Greenfield | 500 kV | 1,000 MW | 3.1 yrs | 72.7 |
| Greenfield (MOSBY - MEADOW BROOK) | Greenfield | 500 kV | 1,000 MW | 3.0 yrs | 72.3 |
| SOWEGO DP | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 71.4 |
| UNKNOWN117020 | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 70.8 |
| TAP139197 | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 70.8 |
| TAP139196 | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 70.7 |
| TAP139201 | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 70.3 |
| UNKNOWN117021 | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 70.2 |
| UNKNOWN116739 | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 69.9 |
| TAP139204 | Substation-Adjacent | 230 kV | 300 MW | 3.1 yrs | 69.9 |
| TAP139194 | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 69.8 |
| NOVEC COUNTRY CLUB | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 69.6 |
| TAP139206 | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 69.5 |
| LINDENDALE D.P. | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 68.7 |
| INDEPENDENT HILL D.P. | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 68.5 |
| Greenfield (BRISTERS - UNKNOWN156824) | Greenfield | 230 kV | 300 MW | 3.1 yrs | 68.2 |
| TAP139207 | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 67.3 |
| TAP139205 | Substation-Adjacent | 115 kV | 100 MW | 3.1 yrs | 66.6 |
| WOODBRIDGE | Substation-Adjacent | 230 kV | 300 MW | 3.1 yrs | 65.8 |
| OZ Prince William | Greenfield | — | — | 3.1 yrs | 64.1 |
| EC Near VMEA 1 Credit Gen | Greenfield | — | — | 3.1 yrs | 62.2 |
| EC Near Dominion/Lo Mar | Greenfield | — | — | 3.1 yrs | 62.1 |
Prince William datacenter FAQ
- How many datacenter sites are in Prince William?
- 137 scored datacenter candidate sites, averaging 57.7/100 DC Readiness.
- Does Prince William offer datacenter tax incentives?
- Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.
- What is the natural-hazard risk in Prince William?
- FEMA's National Risk Index rates Prince William as "Relatively Moderate" (score 30).
- What are industrial electricity rates in Prince William?
- Average industrial electricity is 5.41¢/kWh and commercial is 5.55¢/kWh in Prince William.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Prince William, Virginia. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.