Datacenter Sites in Charlottesville, Virginia

Charlottesville has 24 scored datacenter candidate sites averaging 54.1/100 DC Readiness, with a catalogued aggregate of 2,400 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.

At a glance

Charlottesville, Virginia has 24 scored datacenter candidate sites averaging 54.1/100 DC Readiness, roughly in line with the Virginia average of 52.2. It ranks 66th of 122 Virginia counties by number of sites and 37th by average score. The top-scoring site is Substation-Adjacent site · 671472c7 at 61.5/100.

24
Candidate sites
54.1/100
Avg DC Readiness
2,400 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
◆ Loading map…
≥ 7560–7540–60≤ 40
Top 24 in Charlottesville

Site-selection context for Charlottesville

Yessales_tax_exemption
Datacenter tax incentive
4.81¢/kWh
Commercial electricity
4.19¢/kWh
Industrial electricity
4
Fiber providers
Low
Water stress
$5,900
Land price / acre
1,300
Cooling degree days
4,000
Heating degree days
55°F
Mean annual temp

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

How does Charlottesville compare with other counties in Virginia?

By number of scored sites, Charlottesville ranks 66th of the 122 Virginia counties with a county page, holding 0.4% of the state's 5,871 sites. Its average DC Readiness of 54.1/100 ranks 37th in the state and is roughly in line with the national average of 53.0. Nationally it has the 1511th-largest site inventory of 2,964 counties with five or more sites. 0 sites score 70 or higher and 9 score 55 or higher.

What types of datacenter sites are in Charlottesville?

Shovel-Ready sites are the most common (15, 63% of the county's inventory), followed by substation-adjacent (8) and greenfield (1). Site type reflects how the parcel was identified — next to a substation, on a former mine or brownfield, on industrial or federal excess land — and is scored on the same 14 factors either way.

What are power cost, hazard, water and fiber conditions in Charlottesville?

Industrial electricity averages 4.19¢/kWh and commercial 4.81¢/kWh. FEMA's National Risk Index rates the county "Relatively Moderate" (30). WRI water stress is low. 4 fiber providers report service in the county. The climate runs 1,300 cooling degree days a year with a mean temperature of 55°F. Land is valued around $5,900 an acre.

By site type

Top datacenter sites in Charlottesville

Top datacenter sites in Charlottesville
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN121546Substation-Adjacent230 kV300 MW5.1 yrs61.5
TAP140499Substation-Adjacent230 kV300 MW5.1 yrs60.6
CHARLOTTESVILLESubstation-Adjacent230 kV300 MW5.1 yrs60.5
UNKNOWN172570Substation-Adjacent230 kV300 MW5.1 yrs60.5
HOLLYMEADSubstation-Adjacent230 kV300 MW5.1 yrs60.5
TAP140472Substation-Adjacent230 kV300 MW5.1 yrs60.4
TAP140498Substation-Adjacent230 kV300 MW5.1 yrs60.4
UNKNOWN121545Substation-Adjacent230 kV300 MW5.1 yrs60.3
OZ CharlottesvilleGreenfield——5.1 yrs58.2
South BuildingShovel-Ready——5.1 yrs50.3
Waterhouse BuildingShovel-Ready——5.1 yrs50.3
Apex PlazaShovel-Ready——5.1 yrs50.3
315 NE 10th StShovel-Ready——5.1 yrs50.3
Tenth and MarketShovel-Ready——5.1 yrs50.3
The GleasonShovel-Ready——5.1 yrs50.3
H.M. Gleason BuildingShovel-Ready——5.1 yrs50.3
701 East Water StreetShovel-Ready——5.1 yrs50.3
321 E Main StShovel-Ready——5.1 yrs50.3
Queen Charlotte SquareShovel-Ready——5.1 yrs50.3
123 E. Main Street (Wells Fargo Building)Shovel-Ready——5.1 yrs50.3
Enterprise CenterShovel-Ready——5.1 yrs50.3
1215 E Market StShovel-Ready——5.1 yrs50.3
IX BuildingShovel-Ready——5.1 yrs50.3
The Triange BuildingShovel-Ready——5.1 yrs50.2

Every scored site in Charlottesville

All 24 sites, best first.

Charlottesville datacenter FAQ

How many datacenter sites are in Charlottesville?

24 scored datacenter candidate sites, averaging 54.1/100 DC Readiness. That is the 66th-most of 122 Virginia counties with five or more sites.

What is the highest-scoring datacenter site in Charlottesville?

Substation-Adjacent site · 671472c7 scores 61.5/100 DC Readiness, the highest of the 24 scored sites in Charlottesville (a substation-adjacent site).

Does Charlottesville offer datacenter tax incentives?

Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

What is the natural-hazard risk in Charlottesville?

FEMA's National Risk Index rates Charlottesville as "Relatively Moderate" (score 30).

What are industrial electricity rates in Charlottesville?

Average industrial electricity is 4.19¢/kWh and commercial is 4.81¢/kWh in Charlottesville.

More in Virginia

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published November 12, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Datacenter candidate sites in Charlottesville, Virginia”, https://gridcensus.com/datacenter-sites/virginia/charlottesville (data as of November 12, 2026).

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

Every site and score for Charlottesville, Virginia is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.