Datacenter Sites in Woodward County, Oklahoma
Woodward County has 52 scored datacenter candidate sites averaging 57.5/100 DC Readiness, with a catalogued aggregate of 9,211 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
52
Candidate sites
57.5/100
Avg DC Readiness
9,211 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Woodward County
Yessales_tax_exemption
Datacenter tax incentive
10.80¢/kWh
Commercial electricity
6.43¢/kWh
Industrial electricity
3
Fiber providers
Low-Medium
Water stress
$1,481
Land price / acre
1,900
Cooling degree days
3,600
Heating degree days
60°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment; 5-year ad valorem tax exemption.
By site type
Top datacenter sites in Woodward County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| THISTLE | Substation-Adjacent | 345 kV | 600 MW | 3.4 yrs | 72.1 |
| WOODWARD | Substation-Adjacent | 345 kV | 600 MW | 3.4 yrs | 71.7 |
| UNKNOWN159777 | Substation-Adjacent | 345 kV | 600 MW | 3.4 yrs | 66.0 |
| UNKNOWN118333 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 65.4 |
| Greenfield (THISTLE - WOODWARD) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 64.5 |
| OU SPIRIT WIND FARM | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 64.4 |
| UNKNOWN118851 | Substation-Adjacent | 138 kV | 100 MW | 3.5 yrs | 64.3 |
| Greenfield (WOODWARD - BORDER) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 64.2 |
| UNKNOWN118881 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 64.1 |
| Greenfield (THISTLE - WOODWARD) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 63.9 |
| UNKNOWN118867 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 63.9 |
| TAP168522 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 63.7 |
| Greenfield (TATONGA - WOODWARD) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 63.6 |
| Greenfield (THISTLE - WOODWARD) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 62.5 |
| UNKNOWN118358 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 62.4 |
| MOORELAND | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 61.7 |
| Greenfield (WOODWARD - BEAVER COUNTY) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 61.4 |
| Greenfield (UNKNOWN118688 - WOODWARD) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 59.9 |
| UNKNOWN118333 | Substation-Adjacent | 138 kV | 100 MW | 3.5 yrs | 59.4 |
| Greenfield (WOODWARD - WOODWARD) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 59.3 |
| Greenfield (WOODWARD - BORDER) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 59.2 |
| Greenfield (MOORELAND - UNKNOWN118881) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 59.1 |
| Greenfield (UNKNOWN118333 - UNKNOWN118358) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 59.1 |
| Greenfield (WOODWARD - UNKNOWN173369) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 59.1 |
| Greenfield (MOORELAND - TALOGA) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 59.0 |
Woodward County datacenter FAQ
- How many datacenter sites are in Woodward County?
- 52 scored datacenter candidate sites, averaging 57.5/100 DC Readiness.
- Does Woodward County offer datacenter tax incentives?
- Sales tax exemption on DC equipment; 5-year ad valorem tax exemption.
- What is the natural-hazard risk in Woodward County?
- FEMA's National Risk Index rates Woodward County as "Relatively High" (score 42).
- What are industrial electricity rates in Woodward County?
- Average industrial electricity is 6.43¢/kWh and commercial is 10.80¢/kWh in Woodward County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Woodward County, Oklahoma. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.