Datacenter Sites in Chowan, North Carolina
Chowan has 14 scored datacenter candidate sites averaging 51.2/100 DC Readiness, with a catalogued aggregate of 901 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
14
Candidate sites
51.2/100
Avg DC Readiness
901 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Chowan
Yessales_tax_exemption
Datacenter tax incentive
14.14¢/kWh
Commercial electricity
9.38¢/kWh
Industrial electricity
5
Fiber providers
Low
Water stress
$3,973
Land price / acre
1,600
Cooling degree days
3,300
Heating degree days
59°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment and electricity for $75M+ investments; property tax abatement.
By site type
Top datacenter sites in Chowan
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| UNKNOWN111643 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 66.8 |
| UNKNOWN111642 | Substation-Adjacent | 230 kV | 300 MW | 4.3 yrs | 58.4 |
| Edenton Generators | Brownfield | — | 1 MW | 4.3 yrs | 55.6 |
| EC Near Edenton Generators | Greenfield | — | — | 4.3 yrs | 53.7 |
| EC Near Edenton Generators | Greenfield | — | — | 4.3 yrs | 52.8 |
| Greenfield (UNKNOWN111643 - WINFALL) | Greenfield | 230 kV | 300 MW | 4.3 yrs | 52.2 |
| EC Near Edenton Generators | Greenfield | — | — | 4.3 yrs | 52.0 |
| EC Near Edenton Generators | Greenfield | — | — | 4.3 yrs | 50.7 |
| EC Near Edenton Generators | Greenfield | — | — | 4.3 yrs | 49.2 |
| EC Near Edenton Generators | Greenfield | — | — | 4.3 yrs | 47.8 |
| EC Near Edenton Generators | Greenfield | — | — | 4.3 yrs | 47.1 |
| EC Near Edenton Generators | Greenfield | — | — | 4.3 yrs | 43.8 |
| EC Near Edenton Generators | Greenfield | — | — | 4.3 yrs | 43.4 |
| EC Near Edenton Generators | Greenfield | — | — | 4.3 yrs | 43.2 |
Chowan datacenter FAQ
- How many datacenter sites are in Chowan?
- 14 scored datacenter candidate sites, averaging 51.2/100 DC Readiness.
- Does Chowan offer datacenter tax incentives?
- Sales tax exemption on DC equipment and electricity for $75M+ investments; property tax abatement.
- What is the natural-hazard risk in Chowan?
- FEMA's National Risk Index rates Chowan as "Relatively High" (score 42).
- What are industrial electricity rates in Chowan?
- Average industrial electricity is 9.38¢/kWh and commercial is 14.14¢/kWh in Chowan.
Dataset updated . Screening estimates derived from public data sources.