Datacenter Sites in Somerset, New Jersey

Somerset has 29 scored datacenter candidate sites averaging 60.3/100 DC Readiness, with a catalogued aggregate of 2,807 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.

29
Candidate sites
60.3/100
Avg DC Readiness
2,807 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
◆ Loading map…
≥ 7560–7540–60≤ 40
Top 25 in Somerset

Site-selection context for Somerset

Yessales_tax_exemption
Datacenter tax incentive
9.73¢/kWh
Commercial electricity
7.37¢/kWh
Industrial electricity
11
Fiber providers
Low
Water stress
$21,660
Land price / acre
1,000
Cooling degree days
4,900
Heating degree days
53°F
Mean annual temp

Incentive detail: UEZ sales tax exemption (reduced rate); BEIP/Grow NJ incentives for job creation.

By site type

Top datacenter sites in Somerset

Top datacenter sites in Somerset
SiteTypeVoltageCapacityQueue waitScore
BRANCHBURGSubstation-Adjacent500 kV1,000 MW3.8 yrs68.1
MIDDLESEXSubstation-Adjacent230 kV300 MW3.8 yrs64.8
UNKNOWN132377Substation-Adjacent230 kV300 MW3.8 yrs64.7
GREENBROOKSubstation-Adjacent230 kV300 MW3.8 yrs64.5
UNKNOWN132267Substation-Adjacent230 kV300 MW3.8 yrs64.3
UNKNOWN132271Substation-Adjacent230 kV300 MW3.8 yrs63.7
SUNNYMEADESubstation-Adjacent230 kV300 MW3.8 yrs63.6
EC Near Rariton OMPGreenfield2.6 yrs62.8
EC Near CIP II/AR Bridgewater Holdings - NJCOEGreenfield2.6 yrs62.4
EC Near Rariton OMPGreenfield2.6 yrs61.4
EC Near Rariton OMPGreenfield2.6 yrs61.4
EC Near CIP II/AR Bridgewater Holdings - NJCOEGreenfield2.6 yrs61.1
EC Near Rariton OMPGreenfield2.6 yrs60.4
EC Near CIP II/AR Bridgewater Holdings - NJCOEGreenfield2.6 yrs60.3
EC Near CIP II/AR Bridgewater Holdings - NJCOEGreenfield2.6 yrs60.1
Rariton OMPBrownfield3 MW2.6 yrs60.0
EC Near CIP II/AR Bridgewater Holdings - NJCOEGreenfield2.6 yrs59.9
EC Near Rariton OMPGreenfield2.6 yrs59.9
CIP II/AR Bridgewater Holdings - NJCOEBrownfield4 MW2.6 yrs59.6
EC Near CIP II/AR Bridgewater Holdings - NJCOEGreenfield2.6 yrs58.8
EC Near Rariton OMPGreenfield2.6 yrs58.7
EC Near Rariton OMPGreenfield2.6 yrs58.4
Somerville Asset Management ServiceFederal Excess3.3 yrs57.5
VA New Jersey HCSFederal Excess3.3 yrs57.3
EC Near CIP II/AR Bridgewater Holdings - NJCOEGreenfield2.6 yrs56.9

Somerset datacenter FAQ

How many datacenter sites are in Somerset?
29 scored datacenter candidate sites, averaging 60.3/100 DC Readiness.
Does Somerset offer datacenter tax incentives?
UEZ sales tax exemption (reduced rate); BEIP/Grow NJ incentives for job creation.
What is the natural-hazard risk in Somerset?
FEMA's National Risk Index rates Somerset as "Relatively Moderate" (score 28).
What are industrial electricity rates in Somerset?
Average industrial electricity is 7.37¢/kWh and commercial is 9.73¢/kWh in Somerset.

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Somerset, New Jersey. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.