Datacenter Sites in Bremer County, Iowa
Bremer County has 32 scored datacenter candidate sites averaging 58.9/100 DC Readiness, with a catalogued aggregate of 456 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.
At a glance
Bremer County, Iowa has 32 scored datacenter candidate sites averaging 58.9/100 DC Readiness, roughly in line with the Iowa average of 56.3. It ranks 22nd of 85 Iowa counties by number of sites and 10th by average score. The top-scoring site is EC Near Waverly Municipal Electric North Plant · f6047f27 at 64.9/100.
Site-selection context for Bremer County
Incentive detail: Sales tax exemption on DC equipment for $1M+ investments; property tax phase-in for new construction.
How does Bremer County compare with other counties in Iowa?
By number of scored sites, Bremer County ranks 22nd of the 85 Iowa counties with a county page, holding 1.2% of the state's 2,572 sites. Its average DC Readiness of 58.9/100 ranks 10th in the state and is about 11% above the national average of 53.0. Nationally it has the 1196th-largest site inventory of 2,964 counties with five or more sites. 0 sites score 70 or higher and 28 score 55 or higher.
What types of datacenter sites are in Bremer County?
Greenfield sites are the most common (24, 75% of the county's inventory), followed by substation-adjacent (6) and brownfield (1). Site type reflects how the parcel was identified — next to a substation, on a former mine or brownfield, on industrial or federal excess land — and is scored on the same 14 factors either way.
What are power cost, hazard, water and fiber conditions in Bremer County?
Industrial electricity averages 7.56¢/kWh and commercial 18.32¢/kWh. FEMA's National Risk Index rates the county "Relatively Moderate" (30). WRI water stress is low. 9 fiber providers report service in the county. The climate runs 900 cooling degree days a year with a mean temperature of 48°F. Land is valued around $9,905 an acre.
By site type
Top datacenter sites in Bremer County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| EC Near Waverly Municipal Electric North Plant | Greenfield | — | — | 4.3 yrs | 64.9 |
| EC Near Waverly Municipal Electric North Plant | Greenfield | — | — | 4.3 yrs | 63.4 |
| EC Near Waverly Municipal Electric North Plant | Greenfield | — | — | 4.3 yrs | 62.4 |
| EC Near Waverly Municipal Electric North Plant | Greenfield | — | — | 4.3 yrs | 62.3 |
| EC Near Sumner | Greenfield | — | — | 4.3 yrs | 61.5 |
| EC Near Waverly Municipal Electric North Plant | Greenfield | — | — | 4.3 yrs | 61.3 |
| EC Near Waverly Municipal Electric North Plant | Greenfield | — | — | 4.3 yrs | 61.0 |
| EC Near Waverly Municipal Electric North Plant | Greenfield | — | — | 4.3 yrs | 60.9 |
| EC Near Waverly Municipal Electric North Plant | Greenfield | — | — | 4.3 yrs | 60.5 |
| EC Near Waverly Municipal Electric North Plant | Greenfield | — | — | 4.3 yrs | 60.4 |
| EC Near Sumner | Greenfield | — | — | 4.3 yrs | 60.2 |
| UNKNOWN130703 | Substation-Adjacent | 161 kV | 100 MW | 4.3 yrs | 60.0 |
| EC Near Sumner | Greenfield | — | — | 4.3 yrs | 59.8 |
| EC Near Waverly Municipal Electric North Plant | Greenfield | — | — | 4.3 yrs | 59.7 |
| EC Near Sumner | Greenfield | — | — | 4.3 yrs | 59.7 |
| EC Near Sumner | Greenfield | — | — | 4.3 yrs | 59.3 |
| EC Near Waverly Municipal Electric North Plant | Greenfield | — | — | 4.3 yrs | 59.3 |
| EC Near Sumner | Greenfield | — | — | 4.3 yrs | 59.1 |
| EC Near Sumner | Greenfield | — | — | 4.3 yrs | 58.4 |
| UNKNOWN133180 | Substation-Adjacent | 69 kV | 50 MW | 4.3 yrs | 58.1 |
| TAP136998 | Substation-Adjacent | 69 kV | 50 MW | 4.3 yrs | 57.9 |
| UNKNOWN132058 | Substation-Adjacent | 69 kV | 50 MW | 4.3 yrs | 57.8 |
| EC Near Sumner | Greenfield | — | — | 4.3 yrs | 57.6 |
| TAP163593 | Substation-Adjacent | 69 kV | 50 MW | 4.3 yrs | 57.4 |
| TAP163594 | Substation-Adjacent | 69 kV | 50 MW | 4.3 yrs | 57.2 |
Every scored site in Bremer County
All 32 sites, best first.
- EC Near Waverly Municipal Electric North Plant · f6047f27 · 64.9
- EC Near Waverly Municipal Electric North Plant · 503f4aa6 · 63.4
- EC Near Waverly Municipal Electric North Plant · bea10c06 · 62.4
- EC Near Waverly Municipal Electric North Plant · 0d34137f · 62.3
- EC Near Sumner · a8839fda · 61.5
- EC Near Waverly Municipal Electric North Plant · 33dd371f · 61.3
- EC Near Waverly Municipal Electric North Plant · 80080eb2 · 61.0
- EC Near Waverly Municipal Electric North Plant · f3dfd67b · 60.9
- EC Near Waverly Municipal Electric North Plant · 563aae68 · 60.5
- EC Near Waverly Municipal Electric North Plant · e0ba353e · 60.4
- EC Near Sumner · d5b9860b · 60.2
- Substation-Adjacent site · a0123932 · 60.0
- EC Near Sumner · bdc9d283 · 59.8
- EC Near Waverly Municipal Electric North Plant · 25f25313 · 59.7
- EC Near Sumner · 1068cee8 · 59.7
- EC Near Sumner · 49bbc58a · 59.3
- EC Near Waverly Municipal Electric North Plant · 18602a24 · 59.3
- EC Near Sumner · 391f58eb · 59.1
- EC Near Sumner · 5567c21d · 58.4
- Substation-Adjacent site · 3c327a96 · 58.1
- Substation-Adjacent site · 9372f959 · 57.9
- Substation-Adjacent site · a45d7911 · 57.8
- EC Near Sumner · dc62c873 · 57.6
- Substation-Adjacent site · ea674963 · 57.4
- Substation-Adjacent site · 0bd569a3 · 57.2
- Sumner · 56.9
- EC Near Sumner · d97b3490 · 55.5
- EC Near Sumner · c155743b · 55.2
- EC Near Sumner · 140b063c · 54.8
- Greenfield (BLACK HAWK - UNKNOWN130703) · 54.5
- Waverly Yard Waste Site · 54.2
- EC Near Sumner · dac7d144 · 54.0
Bremer County datacenter FAQ
How many datacenter sites are in Bremer County?
32 scored datacenter candidate sites, averaging 58.9/100 DC Readiness. That is the 22nd-most of 85 Iowa counties with five or more sites.
What is the highest-scoring datacenter site in Bremer County?
EC Near Waverly Municipal Electric North Plant · f6047f27 scores 64.9/100 DC Readiness, the highest of the 32 scored sites in Bremer County (a greenfield site).
Does Bremer County offer datacenter tax incentives?
Sales tax exemption on DC equipment for $1M+ investments; property tax phase-in for new construction.
What is the natural-hazard risk in Bremer County?
FEMA's National Risk Index rates Bremer County as "Relatively Moderate" (score 30).
What are industrial electricity rates in Bremer County?
Average industrial electricity is 7.56¢/kWh and commercial is 18.32¢/kWh in Bremer County.
More in Iowa
- All datacenter sites in Iowa· 2,572 sites
- Operating datacenters in Iowa
- Electric substations in Iowa
- Black Hawk County· 126 sites · avg 58.4
- Pottawattamie County· 123 sites · avg 57.0
- Clinton County· 118 sites · avg 54.2
- Johnson County· 112 sites · avg 57.9
- Linn County· 105 sites · avg 58.3
- Dubuque County· 101 sites · avg 55.8
- Greenfield sites in Iowa
- Substation-Adjacent sites in Iowa
About this data
Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published November 12, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.
Cite as: GridCensus, “Datacenter candidate sites in Bremer County, Iowa”, https://gridcensus.com/datacenter-sites/iowa/bremer-county (data as of November 12, 2026).
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
Every site and score for Bremer County, Iowa is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.