Datacenter Sites in Pasco County, Florida
Pasco County has 92 scored datacenter candidate sites averaging 55.5/100 DC Readiness, with a catalogued aggregate of 9,000 MW. FEMA rates local natural-hazard risk as "Very High". The county has a datacenter tax incentive on record.
92
Candidate sites
55.5/100
Avg DC Readiness
9,000 MW
Catalogued capacity
theoretical aggregate
Very High
Hazard rating
Site-selection context for Pasco County
Yessales_tax_exemption
Datacenter tax incentive
11.63¢/kWh
Commercial electricity
7.76¢/kWh
Industrial electricity
8
Fiber providers
Low-Medium
Water stress
$12,190
Land price / acre
3,500
Cooling degree days
700
Heating degree days
72°F
Mean annual temp
Incentive detail: Sales tax exemption on manufacturing machinery including servers; no state income tax.
By site type
Top datacenter sites in Pasco County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| LAKE TARPON | Substation-Adjacent | 500 kV | 1,000 MW | 3.6 yrs | 79.2 |
| TAP143447 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 73.0 |
| HUDSON | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 72.8 |
| SEVEN SPRINGS | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 72.4 |
| Greenfield (BROOKRIDGE - LAKE TARPON) | Greenfield | 500 kV | 1,000 MW | 3.6 yrs | 71.9 |
| TAP143446 | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 71.6 |
| Greenfield (BROOKRIDGE - LAKE TARPON) | Greenfield | 500 kV | 1,000 MW | 3.6 yrs | 70.8 |
| ELFERS | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 69.7 |
| Greenfield (DALE MABRY - SHELDON ROAD) | Greenfield | 230 kV | 300 MW | 3.6 yrs | 69.7 |
| CHAPMAN | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 69.5 |
| TAP143155 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 69.5 |
| SHADY HILLS GENERATING STATION | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 69.3 |
| UNKNOWN108298 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 68.6 |
| NEW PORT RICHEY | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 68.5 |
| UNKNOWN108290 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 68.3 |
| Greenfield (BROOKSVILLE WEST - LAKE TARPON) | Greenfield | 230 kV | 300 MW | 3.6 yrs | 68.0 |
| UNKNOWN108686 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 67.8 |
| Greenfield (BROOKRIDGE - LAKE TARPON) | Greenfield | 500 kV | 1,000 MW | 3.6 yrs | 67.5 |
| UNKNOWN108284 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 67.5 |
| Greenfield (BROOKSVILLE WEST - LAKE TARPON) | Greenfield | 230 kV | 300 MW | 3.6 yrs | 67.0 |
| UNKNOWN108297 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 66.6 |
| Greenfield (UNKNOWN120347 - TAP143325) | Greenfield | 115 kV | 100 MW | 3.6 yrs | 66.2 |
| ZEPHYRHILLS NORTH | Substation-Adjacent | 230 kV | 300 MW | 3.6 yrs | 66.0 |
| Greenfield (UNKNOWN120347 - TAP143325) | Greenfield | 115 kV | 100 MW | 3.6 yrs | 65.4 |
| UNKNOWN108295 | Substation-Adjacent | 115 kV | 100 MW | 3.6 yrs | 65.2 |
Pasco County datacenter FAQ
- How many datacenter sites are in Pasco County?
- 92 scored datacenter candidate sites, averaging 55.5/100 DC Readiness.
- Does Pasco County offer datacenter tax incentives?
- Sales tax exemption on manufacturing machinery including servers; no state income tax.
- What is the natural-hazard risk in Pasco County?
- FEMA's National Risk Index rates Pasco County as "Very High" (score 55).
- What are industrial electricity rates in Pasco County?
- Average industrial electricity is 7.76¢/kWh and commercial is 11.63¢/kWh in Pasco County.
Dataset updated . Screening estimates derived from public data sources.