Datacenter Sites in Canadian County, Oklahoma
Canadian County has 50 scored datacenter candidate sites averaging 61.8/100 DC Readiness, with a catalogued aggregate of 9,800 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
50
Candidate sites
61.8/100
Avg DC Readiness
9,800 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Canadian County
Yessales_tax_exemption
Datacenter tax incentive
9.70¢/kWh
Commercial electricity
5.82¢/kWh
Industrial electricity
9
Fiber providers
Low-Medium
Water stress
$3,406
Land price / acre
1,900
Cooling degree days
3,600
Heating degree days
60°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment; 5-year ad valorem tax exemption.
By site type
Top datacenter sites in Canadian County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| CIMARRON | Substation-Adjacent | 345 kV | 600 MW | 3.4 yrs | 75.0 |
| CANADIAN HILLS WIND | Substation-Adjacent | 345 kV | 600 MW | 3.4 yrs | 74.3 |
| MINCO WIND III, LLC | Substation-Adjacent | 345 kV | 600 MW | 3.4 yrs | 73.3 |
| MINCO WIND II, LLC | Substation-Adjacent | 345 kV | 600 MW | 3.4 yrs | 71.6 |
| UNKNOWN118467 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 71.3 |
| UNKNOWN168552 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 71.1 |
| Greenfield (CIMARRON - DRAPER) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 70.4 |
| UNKNOWN119066 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 70.3 |
| UNKNOWN119065 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 69.8 |
| UNKNOWN118464 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 69.2 |
| Greenfield (CIMARRON - MATHEWSON) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 68.7 |
| Greenfield (CIMARRON - MINCO) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 68.5 |
| TAP149226 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 68.0 |
| TAP168551 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 67.9 |
| Greenfield (CANADIAN HILLS WIND - CIMARRON) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 67.4 |
| EL RENO | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 66.9 |
| UNKNOWN118513 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 66.7 |
| UNKNOWN118516 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 66.4 |
| UNKNOWN118463 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 66.0 |
| DARLINGTON ROAD | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 66.0 |
| UNKNOWN118465 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 65.3 |
| UNKNOWN168547 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 64.9 |
| UNKNOWN168549 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 64.4 |
| Greenfield (NORTHWEST - MATHEWSON) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 63.9 |
| Greenfield (CIMARRON - MATHEWSON) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 63.6 |
Canadian County datacenter FAQ
- How many datacenter sites are in Canadian County?
- 50 scored datacenter candidate sites, averaging 61.8/100 DC Readiness.
- Does Canadian County offer datacenter tax incentives?
- Sales tax exemption on DC equipment; 5-year ad valorem tax exemption.
- What is the natural-hazard risk in Canadian County?
- FEMA's National Risk Index rates Canadian County as "Relatively High" (score 42).
- What are industrial electricity rates in Canadian County?
- Average industrial electricity is 5.82¢/kWh and commercial is 9.70¢/kWh in Canadian County.