Datacenter Sites in Colfax, New Mexico

Colfax has 29 scored datacenter candidate sites averaging 47.7/100 DC Readiness, with a catalogued aggregate of 1,150 MW. FEMA rates local natural-hazard risk as "Relatively Low".

At a glance

Colfax, New Mexico has 29 scored datacenter candidate sites averaging 47.7/100 DC Readiness, roughly in line with the New Mexico average of 47.8. It ranks 17th of 33 New Mexico counties by number of sites and 19th by average score. The top-scoring site is BURRO CANYON at 56.1/100.

29
Candidate sites
47.7/100
Avg DC Readiness
1,150 MW
Catalogued capacity
theoretical aggregate
Relatively Low
Hazard rating
◆ Loading map…
≥ 7560–7540–60≤ 40
Top 25 in Colfax

Site-selection context for Colfax

No
Datacenter tax incentive
15.48¢/kWh
Commercial electricity
8.10¢/kWh
Industrial electricity
5
Fiber providers
Extremely High
Water stress
$977
Land price / acre
1,400
Cooling degree days
4,000
Heating degree days
53°F
Mean annual temp

How does Colfax compare with other counties in New Mexico?

By number of scored sites, Colfax ranks 17th of the 33 New Mexico counties with a county page, holding 1.9% of the state's 1,535 sites. Its average DC Readiness of 47.7/100 ranks 19th in the state and is about 10% below the national average of 53.0. Nationally it has the 1305th-largest site inventory of 2,964 counties with five or more sites. 0 sites score 70 or higher and 1 score 55 or higher.

What types of datacenter sites are in Colfax?

Substation-Adjacent sites are the most common (14, 48% of the county's inventory), followed by industrial (5) and former mine (5). Site type reflects how the parcel was identified — next to a substation, on a former mine or brownfield, on industrial or federal excess land — and is scored on the same 14 factors either way.

What are power cost, hazard, water and fiber conditions in Colfax?

Industrial electricity averages 8.10¢/kWh and commercial 15.48¢/kWh. FEMA's National Risk Index rates the county "Relatively Low" (15). WRI water stress is extremely high. 5 fiber providers report service in the county. The climate runs 1,400 cooling degree days a year with a mean temperature of 53°F. Land is valued around $977 an acre.

By site type

Top datacenter sites in Colfax

Top datacenter sites in Colfax
SiteTypeVoltageCapacityQueue waitScore
BURRO CANYONSubstation-Adjacent230 kV300 MW4.3 yrs56.1
OZ ColfaxGreenfield——3.5 yrs53.2
EC Coal Colfax CountyGreenfield——3.5 yrs52.7
YORK CANYONSubstation-Adjacent115 kV100 MW3.5 yrs51.1
SPRINGERSubstation-Adjacent115 kV100 MW3.5 yrs51.1
TAP308008Substation-Adjacent115 kV100 MW3.5 yrs51.0
UNKNOWN306518Substation-Adjacent115 kV100 MW3.5 yrs50.7
EC Coal Colfax CountyGreenfield——3.5 yrs50.1
EC FFE Colfax CountyGreenfield——3.5 yrs49.2
TAP305480Substation-Adjacent69 kV50 MW3.5 yrs49.0
HOXIESubstation-Adjacent69 kV50 MW3.5 yrs48.8
TAP308116Substation-Adjacent69 kV50 MW3.5 yrs48.8
UNKNOWN303066Substation-Adjacent69 kV50 MW3.5 yrs48.7
TAP302529Substation-Adjacent69 kV50 MW3.5 yrs48.7
UNKNOWN309092Substation-Adjacent69 kV50 MW3.5 yrs48.5
CIMARRONSubstation-Adjacent69 kV50 MW3.5 yrs48.1
TAP308102Substation-Adjacent69 kV50 MW3.5 yrs47.5
ABBOTTSubstation-Adjacent69 kV50 MW3.5 yrs47.2
216 / 220 S. 2nd St.Industrial——3.5 yrs45.2
Raton - AtsfIndustrial——3.5 yrs45.2
Mine SiteFormer Mine——3.5 yrs45.1
Mine SiteFormer Mine——3.5 yrs45.0
Mine SiteFormer Mine——3.5 yrs44.8
CIMARRON, NMFederal Excess——3.5 yrs44.0
Mine SiteFormer Mine——3.5 yrs43.1

Every scored site in Colfax

All 29 sites, best first.

Colfax datacenter FAQ

How many datacenter sites are in Colfax?

29 scored datacenter candidate sites, averaging 47.7/100 DC Readiness. That is the 17th-most of 33 New Mexico counties with five or more sites.

What is the highest-scoring datacenter site in Colfax?

BURRO CANYON scores 56.1/100 DC Readiness, the highest of the 29 scored sites in Colfax (a substation-adjacent site).

Does Colfax offer datacenter tax incentives?

No datacenter-specific tax incentive is on record for Colfax in the GridCensus county dataset.

What is the natural-hazard risk in Colfax?

FEMA's National Risk Index rates Colfax as "Relatively Low" (score 15).

What are industrial electricity rates in Colfax?

Average industrial electricity is 8.10¢/kWh and commercial is 15.48¢/kWh in Colfax.

More in New Mexico

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published November 13, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Datacenter candidate sites in Colfax, New Mexico”, https://gridcensus.com/datacenter-sites/new-mexico/colfax (data as of November 13, 2026).

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

Every site and score for Colfax, New Mexico is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.