Datacenter Sites in LEAKE, Mississippi

LEAKE has 15 scored datacenter candidate sites averaging 49.6/100 DC Readiness, with a catalogued aggregate of 700 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.

At a glance

LEAKE, Mississippi has 15 scored datacenter candidate sites averaging 49.6/100 DC Readiness, roughly in line with the Mississippi average of 53.0. It ranks 56th of 80 Mississippi counties by number of sites and 77th by average score. The top-scoring site is Substation-Adjacent site · ea83e68c at 54.4/100.

15
Candidate sites
49.6/100
Avg DC Readiness
700 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
◆ Loading map…
≥ 7560–7540–60≤ 40
Top 15 in LEAKE

Site-selection context for LEAKE

Yessales_tax_exemption
Datacenter tax incentive
11.53¢/kWh
Commercial electricity
6.95¢/kWh
Industrial electricity
4
Fiber providers
Low
Water stress
$3,798
Land price / acre
2,400
Cooling degree days
2,400
Heating degree days
64°F
Mean annual temp

Incentive detail: Sales tax exemption on DC equipment for $50M+ investments; fee-in-lieu of property tax.

How does LEAKE compare with other counties in Mississippi?

By number of scored sites, LEAKE ranks 56th of the 80 Mississippi counties with a county page, holding 0.5% of the state's 3,104 sites. Its average DC Readiness of 49.6/100 ranks 77th in the state and is roughly in line with the national average of 53.0. Nationally it has the 2019th-largest site inventory of 2,964 counties with five or more sites. 0 sites score 70 or higher and 0 score 55 or higher.

What types of datacenter sites are in LEAKE?

Substation-Adjacent sites are the most common (5, 33% of the county's inventory), followed by manufacturing (4) and industrial (4). Site type reflects how the parcel was identified — next to a substation, on a former mine or brownfield, on industrial or federal excess land — and is scored on the same 14 factors either way.

What are power cost, hazard, water and fiber conditions in LEAKE?

Industrial electricity averages 6.95¢/kWh and commercial 11.53¢/kWh. FEMA's National Risk Index rates the county "Relatively High" (45). WRI water stress is low. 4 fiber providers report service in the county. The climate runs 2,400 cooling degree days a year with a mean temperature of 64°F. Land is valued around $3,798 an acre.

By site type

Top datacenter sites in LEAKE

Top datacenter sites in LEAKE
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN169468Substation-Adjacent161 kV100 MW4.3 yrs54.4
SINGLETONSubstation-Adjacent161 kV100 MW4.3 yrs54.2
LEAKESubstation-Adjacent161 kV100 MW4.3 yrs54.2
TAP169467Substation-Adjacent161 kV100 MW4.3 yrs54.2
CARTHAGE (MS)Substation-Adjacent115 kV100 MW4.3 yrs53.3
Transit Authority Old Dump SiteIndustrial——4.3 yrs47.8
Greenfield (UNKNOWN109387 - CARTHAGE (MS))Greenfield115 kV100 MW4.3 yrs47.7
Frontier Ford (former)Industrial——4.3 yrs47.5
TYSON FOODS, INC. (POULTRY PROCESSING)Manufacturing——4.3 yrs47.5
Mudcats (Facility ID #4314)Industrial——4.3 yrs47.4
H & H CHIEF SALES, INC. (MOTOR VEHICLE BODY MANUFACTURING)Manufacturing——4.3 yrs47.3
APPLIED GEO TECHNOLOGIES, INC. (OTHER ELECTRONIC COMPONENT MANUFACTURING)Manufacturing——4.3 yrs47.3
CENTRAL SNACKS, INC. (OTHER SNACK FOOD MANUFACTURING)Manufacturing——4.3 yrs47.3
MBCI-CME BuildingIndustrial——4.3 yrs47.3
Greenfield (SAND HILL - TAP169467)Greenfield161 kV100 MW7.6 yrs46.8

Every scored site in LEAKE

All 15 sites, best first.

LEAKE datacenter FAQ

How many datacenter sites are in LEAKE?

15 scored datacenter candidate sites, averaging 49.6/100 DC Readiness. That is the 56th-most of 80 Mississippi counties with five or more sites.

What is the highest-scoring datacenter site in LEAKE?

Substation-Adjacent site · ea83e68c scores 54.4/100 DC Readiness, the highest of the 15 scored sites in LEAKE (a substation-adjacent site).

Does LEAKE offer datacenter tax incentives?

Sales tax exemption on DC equipment for $50M+ investments; fee-in-lieu of property tax.

What is the natural-hazard risk in LEAKE?

FEMA's National Risk Index rates LEAKE as "Relatively High" (score 45).

What are industrial electricity rates in LEAKE?

Average industrial electricity is 6.95¢/kWh and commercial is 11.53¢/kWh in LEAKE.

More in Mississippi

About this data

Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published November 12, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.

Cite as: GridCensus, “Datacenter candidate sites in LEAKE, Mississippi”, https://gridcensus.com/datacenter-sites/mississippi/leake (data as of November 12, 2026).

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

Every site and score for LEAKE, Mississippi is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.