Datacenter Sites in Koochiching, Minnesota
Koochiching has 15 scored datacenter candidate sites averaging 56.0/100 DC Readiness, with a catalogued aggregate of 8,100 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.
15
Candidate sites
56.0/100
Avg DC Readiness
8,100 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
Site-selection context for Koochiching
Yessales_tax_exemption
Datacenter tax incentive
11.14¢/kWh
Commercial electricity
19.47¢/kWh
Industrial electricity
6
Fiber providers
Low
Water stress
$2,595
Land price / acre
600
Cooling degree days
7,700
Heating degree days
42°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment and electricity for qualified DCs.
By site type
Top datacenter sites in Koochiching
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| LITTLEFORK | Substation-Adjacent | 230 kV | 300 MW | 2.8 yrs | 60.3 |
| Greenfield (IRON RANGE - None) | Greenfield | 500 kV | 1,000 MW | 2.8 yrs | 58.3 |
| Greenfield (IRON RANGE - None) | Greenfield | 500 kV | 1,000 MW | 2.8 yrs | 58.3 |
| Greenfield (IRON RANGE - None) | Greenfield | 500 kV | 1,000 MW | 2.8 yrs | 57.8 |
| Greenfield (IRON RANGE - None) | Greenfield | 500 kV | 1,000 MW | 2.8 yrs | 57.8 |
| Greenfield (IRON RANGE - None) | Greenfield | 500 kV | 1,000 MW | 2.8 yrs | 57.5 |
| Greenfield (IRON RANGE - None) | Greenfield | 500 kV | 1,000 MW | 2.8 yrs | 57.3 |
| OZ Koochiching | Greenfield | — | — | 1.4 yrs | 57.0 |
| UNKNOWN130450 | Substation-Adjacent | 115 kV | 100 MW | 2.8 yrs | 56.8 |
| Greenfield (IRON RANGE - None) | Greenfield | 500 kV | 1,000 MW | 2.8 yrs | 56.7 |
| UNKNOWN129633 | Substation-Adjacent | 115 kV | 100 MW | 2.8 yrs | 56.1 |
| Greenfield (LITTLEFORK - TAP176211) | Greenfield | 230 kV | 300 MW | 2.8 yrs | 54.0 |
| Greenfield (LITTLEFORK - TAP176211) | Greenfield | 230 kV | 300 MW | 2.8 yrs | 53.6 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 49.8 |
| INTL FALLS. MN | Federal Excess | — | — | 3.8 yrs | 48.3 |
Koochiching datacenter FAQ
- How many datacenter sites are in Koochiching?
- 15 scored datacenter candidate sites, averaging 56.0/100 DC Readiness.
- Does Koochiching offer datacenter tax incentives?
- Sales tax exemption on DC equipment and electricity for qualified DCs.
- What is the natural-hazard risk in Koochiching?
- FEMA's National Risk Index rates Koochiching as "Relatively Moderate" (score 25).
- What are industrial electricity rates in Koochiching?
- Average industrial electricity is 19.47¢/kWh and commercial is 11.14¢/kWh in Koochiching.
Dataset updated . Screening estimates derived from public data sources.