Datacenter Sites in DEARBORN, Indiana
DEARBORN has 56 scored datacenter candidate sites averaging 56.4/100 DC Readiness, with a catalogued aggregate of 6,300 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.
56
Candidate sites
56.4/100
Avg DC Readiness
6,300 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
Site-selection context for DEARBORN
Yessales_tax_exemption
Datacenter tax incentive
12.03¢/kWh
Commercial electricity
8.31¢/kWh
Industrial electricity
11
Fiber providers
Low
Water stress
$6,735
Land price / acre
1,000
Cooling degree days
5,500
Heating degree days
52°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.
By site type
Top datacenter sites in DEARBORN
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| WOODSDALE | Substation-Adjacent | 345 kV | 600 MW | 3.0 yrs | 77.4 |
| Tanners Creek | Brownfield | — | 1,100 MW | — | 75.2 |
| UNKNOWN130105 | Substation-Adjacent | 345 kV | 600 MW | 3.0 yrs | 74.9 |
| MIAMI | Substation-Adjacent | 345 kV | 600 MW | 3.0 yrs | 71.2 |
| UNKNOWN113754 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 68.9 |
| UNKNOWN137579 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 68.2 |
| UNKNOWN125321 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 65.6 |
| Greenfield (UNKNOWN124885 - HEADWATERS WIN) | Greenfield | 345 kV | 600 MW | 3.0 yrs | 65.2 |
| TAP173564 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 64.4 |
| Greenfield (UNKNOWN124885 - DESOTO) | Greenfield | 345 kV | 600 MW | 3.0 yrs | 64.3 |
| Greenfield (UNKNOWN124885 - HEADWATERS WIN) | Greenfield | 345 kV | 600 MW | 3.0 yrs | 64.3 |
| Greenfield (UNKNOWN124885 - HANNA) | Greenfield | 345 kV | 600 MW | 3.0 yrs | 63.4 |
| TAP137561 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 62.9 |
| UNKNOWN173565 | Substation-Adjacent | 138 kV | 100 MW | 3.0 yrs | 61.0 |
| EC Near Tanners Creek | Greenfield | — | — | 3.0 yrs | 60.7 |
| Greenfield (MADISON - TANNERS CREEK) | Greenfield | 138 kV | 100 MW | 3.0 yrs | 59.5 |
| EC Near Tanners Creek | Greenfield | — | — | 3.0 yrs | 58.9 |
| EC Near Tanners Creek | Greenfield | — | — | 3.0 yrs | 58.6 |
| EC Near Tanners Creek | Greenfield | — | — | 3.0 yrs | 58.6 |
| Greenfield (UNKNOWN124877 - TANNERS CREEK) | Greenfield | 138 kV | 100 MW | 3.0 yrs | 58.5 |
| EC Coal Dearborn County | Greenfield | — | — | 3.0 yrs | 58.5 |
| EC Near Tanners Creek | Greenfield | — | — | 3.0 yrs | 58.4 |
| EC Near Tanners Creek | Greenfield | — | — | 3.0 yrs | 58.4 |
| Greenfield (UNKNOWN124895 - TAP137561) | Greenfield | 138 kV | 100 MW | 3.0 yrs | 58.3 |
| EC Coal Dearborn County | Greenfield | — | — | 3.0 yrs | 57.5 |
DEARBORN datacenter FAQ
- How many datacenter sites are in DEARBORN?
- 56 scored datacenter candidate sites, averaging 56.4/100 DC Readiness.
- Does DEARBORN offer datacenter tax incentives?
- Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.
- What is the natural-hazard risk in DEARBORN?
- FEMA's National Risk Index rates DEARBORN as "Relatively Moderate" (score 32).
- What are industrial electricity rates in DEARBORN?
- Average industrial electricity is 8.31¢/kWh and commercial is 12.03¢/kWh in DEARBORN.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for DEARBORN, Indiana. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.