Datacenter Sites in Loving County, Texas
Loving County has 18 scored datacenter candidate sites averaging 51.9/100 DC Readiness, with a catalogued aggregate of 1,400 MW. FEMA rates local natural-hazard risk as "Very High". The county has a datacenter tax incentive on record.
18
Candidate sites
51.9/100
Avg DC Readiness
1,400 MW
Catalogued capacity
theoretical aggregate
Very High
Hazard rating
Site-selection context for Loving County
Yessales_tax_exemption
Datacenter tax incentive
9.21¢/kWh
Commercial electricity
4.87¢/kWh
Industrial electricity
1
Fiber providers
Medium-High
Water stress
$1,671
Land price / acre
2,600
Cooling degree days
1,800
Heating degree days
65°F
Mean annual temp
Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.
By site type
Top datacenter sites in Loving County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| EL MAR | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 60.9 |
| TAP315848 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 60.7 |
| LOVING | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 59.7 |
| OCHOA | Substation-Adjacent | 115 kV | 100 MW | 3.4 yrs | 57.5 |
| Greenfield (EL MAR - LOVING) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 54.9 |
| ONCOR MASON | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 54.7 |
| Greenfield (OCHOA - WHITTEN) | Greenfield | 115 kV | 100 MW | 3.4 yrs | 54.1 |
| Greenfield (OCHOA - TAP307983) | Greenfield | 115 kV | 100 MW | 3.4 yrs | 52.4 |
| Greenfield (OCHOA - WHITTEN) | Greenfield | 115 kV | 100 MW | 3.4 yrs | 51.9 |
| Greenfield (OCHOA - TAP307983) | Greenfield | 115 kV | 100 MW | 3.4 yrs | 50.9 |
| Greenfield (ONCOR MASON - EL MAR) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 50.6 |
| Greenfield (ONCOR MASON - BLACK RIVER) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 50.2 |
| Greenfield (ONCOR MASON - BLACK RIVER) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 50.1 |
| OZ Loving | Greenfield | — | — | 3.4 yrs | 49.2 |
| Greenfield (ONCOR MASON - BLACK RIVER) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 47.5 |
| Mine Site | Former Mine | — | — | — | 43.3 |
| Mine Site | Former Mine | — | — | — | 43.2 |
| Mine Site | Former Mine | — | — | — | 42.4 |
Loving County datacenter FAQ
- How many datacenter sites are in Loving County?
- 18 scored datacenter candidate sites, averaging 51.9/100 DC Readiness.
- Does Loving County offer datacenter tax incentives?
- Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.
- What is the natural-hazard risk in Loving County?
- FEMA's National Risk Index rates Loving County as "Very High" (score 55).
- What are industrial electricity rates in Loving County?
- Average industrial electricity is 4.87¢/kWh and commercial is 9.21¢/kWh in Loving County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Loving County, Texas. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.