Datacenter Sites in Rhode Island
Rhode Island has 445 scored datacenter candidate sites averaging 56.3/100 DC Readiness. Industrial parcels lead the inventory (309 sites). Most sites interconnect through ISO-NE. The state's candidate sites carry a catalogued aggregate of 9.3k MW and average a 4.3 yrs interconnection-queue wait.
At a glance
Rhode Island has 445 scored datacenter candidate sites, the 48th-most of the 50 states, DC and Puerto Rico, averaging 56.3/100 DC Readiness against a national average of 53.0. Its average score ranks 8th among states. The state also has 2 operating datacenters and 5 internet exchange facilities on record.
How does Rhode Island compare with other states for datacenter sites?
By number of scored candidate sites, Rhode Island ranks 48th of the 50 states, DC and Puerto Rico (445 of 147,272 nationally, 0.3%). Its average DC Readiness of 56.3/100 ranks 8th and is roughly in line with the national average of 53.0. The average interconnection-queue wait at its sites, 4.3-year, is the 23rd-shortest of the group (national 4.2-year).
Across the five headline sub-scores, Rhode Island is strongest relative to the nation on fiber (91.2 vs 69.1 nationally) and weakest on power availability (33.8 vs 37.4). Power and speed to power carry 20% of the score each, fiber 12%, water 7% and hazard 6%.
Which counties in Rhode Island have the most datacenter sites?
Providence County (322 sites, average 56.7), Washington County (44 sites, average 53.6), and Kent County (32 sites, average 57.3) hold the largest inventories. Together the top 3 account for 89% of the state's scored sites. Kent County has the highest average score among counties with at least 10 sites (57.3/100). 5 counties have five or more scored sites and their own county page.
What kinds of sites and grid regions are in Rhode Island?
Industrial parcels are the largest category (309, 69%), followed by substation-adjacent (58) and greenfield (47). Every scored site sits in the ISO-NE region.
By site type
By grid region
- ISO-NE445
Average sub-score profile
How Rhode Island's candidate sites score on each DC Readiness dimension (0–100 average).
Top 25 datacenter sites in Rhode Island
Ranked by DC Readiness.
| Site | Type | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|
| KENT COUNTY | Substation-Adjacent | Kent County | 345 kV | 600 MW | 4.3 yrs | 67.3 |
| WEST FARNUM | Substation-Adjacent | Providence County | 345 kV | 600 MW | 4.3 yrs | 67.2 |
| OCEAN STATE | Substation-Adjacent | Providence County | 345 kV | 600 MW | 4.3 yrs | 65.5 |
| Kilvert Street Solar | Brownfield | Kent | — | 6 MW | 4.3 yrs | 64.6 |
| Ridgewood Providence Power | Brownfield | Providence | 115 kV | 20 MW | 4.3 yrs | 63.7 |
| EC Near Central Power Plant | Greenfield | Providence | — | — | 4.3 yrs | 62.9 |
| SOUTH STREET | Substation-Adjacent | Providence County | 115 kV | 100 MW | 4.3 yrs | 62.8 |
| TAP156254 | Substation-Adjacent | Providence County | 115 kV | 100 MW | 4.3 yrs | 62.7 |
| JOHNSTON | Substation-Adjacent | Providence County | 115 kV | 100 MW | 4.3 yrs | 62.6 |
| Beacon Solar Project | Brownfield | Kent | 115 kV | 4 MW | 4.3 yrs | 62.4 |
| OZ Providence | Greenfield | Providence | — | — | 4.3 yrs | 62.1 |
| PAWTUCKET | Substation-Adjacent | Providence County | 115 kV | 100 MW | 4.3 yrs | 61.7 |
| OZ Providence | Greenfield | Providence | — | — | 4.3 yrs | 61.7 |
| TAP140936 | Substation-Adjacent | Providence County | 115 kV | 100 MW | 4.3 yrs | 61.6 |
| OZ Providence | Greenfield | Providence | — | — | 4.3 yrs | 61.6 |
| HARTFORD AVENUE | Substation-Adjacent | Providence County | 115 kV | 100 MW | 4.3 yrs | 61.6 |
| BLACKBURN SWITCHING STATION | Substation-Adjacent | Kent County | 115 kV | 100 MW | 4.3 yrs | 61.5 |
| EC Near Central Power Plant | Greenfield | Providence | — | — | 4.3 yrs | 61.5 |
| UNKNOWN130071 | Substation-Adjacent | Kent County | 115 kV | 100 MW | 4.3 yrs | 61.5 |
| PUTNAM PIKE | Substation-Adjacent | Providence County | 115 kV | 100 MW | 4.3 yrs | 61.5 |
| TAP140939 | Substation-Adjacent | Providence County | 115 kV | 100 MW | 4.3 yrs | 61.5 |
| TAP136317 | Substation-Adjacent | Providence County | 115 kV | 100 MW | 4.3 yrs | 61.3 |
| TAP136305 | Substation-Adjacent | Providence County | 115 kV | 100 MW | 4.3 yrs | 61.3 |
| EC Near Central Power Plant | Greenfield | Providence | — | — | 4.3 yrs | 61.3 |
| UNKNOWN130752 | Substation-Adjacent | Kent County | 115 kV | 100 MW | 4.3 yrs | 61.3 |
Counties in Rhode Island
5 counties with five or more scored sites.
Operating datacenters in Rhode Island
2 operating datacenter facilities in Rhode Island are on record, the 52nd-most of any state. Providence has the largest cluster (2 facilities). The operators with the most facilities here are Provdotnet LLC (1), Crown Castle Inc. (1).
Providence (2)
- Crown Castle Providence (235 Promenade) · Crown Castle Inc.
- Prov.net PVD1 (1155 Westminster) · Provdotnet LLC
Internet exchange and peering facilities in Rhode Island
5 peering and colocation facilities in Rhode Island are listed in PeeringDB. Providence has the most (5). The best-connected facility hosts 5 networks; the median facility in the state hosts 2 networks.
Providence (5)
- Prov.net PVD2 (304 Carpenter) · 5 networks
- Crown Castle Providence (235 Promenade) · 3 networks
- Prov.net PVD1 (1155 Westminster) · 2 networks
- Crown Castle Providence (300 Carpenter) · 0 networks
- Prov.net 935 · 0 networks
Rhode Island datacenter site selection FAQ
How many datacenter sites are in Rhode Island?
GridCensus catalogs 445 scored datacenter candidate sites in Rhode Island, with an average DC Readiness score of 56.3/100. That is the 48th-largest inventory of the 50 states, DC and Puerto Rico.
How many operating datacenters are in Rhode Island?
2 operating datacenter facilities in Rhode Island are on record, the 52nd-most of any state. Providence has the most (2). Provdotnet LLC operates the most facilities in the state (1).
What is the average interconnection-queue wait in Rhode Island?
Candidate sites in Rhode Island average a 4.3-year interconnection-queue wait, with an average queue depth of 2 projects. The national average across all scored sites is 4.2-year, and Rhode Island has the 23rd-shortest average wait of the 50 states, DC and Puerto Rico.
Which county in Rhode Island has the most datacenter sites?
Providence County has the most scored candidate sites in Rhode Island (322), followed by Washington County (44) and Kent County (32). Among counties with at least 10 sites, Kent County has the highest average DC Readiness (57.3/100).
What kind of datacenter sites are most common in Rhode Island?
Industrial sites are the most common category in Rhode Island (309 sites, 69% of the inventory), and most sites fall within the ISO-NE grid region.
How many internet exchange facilities are in Rhode Island?
5 peering and colocation facilities listed in PeeringDB are in Rhode Island. Providence has the most (5). The best-connected one hosts 5 networks.
Looking for a specific record? The directory lists every scored datacenter site in Rhode Island, A to Z.
More Rhode Island infrastructure
- Electric substations in Rhode Island
- Brownfield and retired power plant sites in Rhode Island
- ISO-NE grid region· 445 sites here
- Industrial sites in Rhode Island· 309
- Substation-Adjacent sites in Rhode Island· 58
- Greenfield sites in Rhode Island· 47
- Former Mine sites in Rhode Island· 24
- States ranked by datacenter readiness
About this data
Source: GridCensus composite of HIFLD transmission and substation data, EIA, FEMA National Risk Index, FCC broadband data, PeeringDB and ISO interconnection queues, as published November 12, 2026 — GridCensus refreshes it monthly. See the methodology for how records are matched, cleaned and scored.
Cite as: GridCensus, “Datacenter candidate sites in Rhode Island”, https://gridcensus.com/datacenter-sites/rhode-island (data as of November 12, 2026).
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
Every site and score for Rhode Island is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.