Datacenter Sites in Meigs County, Ohio
Meigs County has 42 scored datacenter candidate sites averaging 55.4/100 DC Readiness, with a catalogued aggregate of 9,300 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.
42
Candidate sites
55.4/100
Avg DC Readiness
9,300 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
Site-selection context for Meigs County
Yessales_tax_exemption
Datacenter tax incentive
14.64¢/kWh
Commercial electricity
11.31¢/kWh
Industrial electricity
3
Fiber providers
Low
Water stress
$3,816
Land price / acre
900
Cooling degree days
5,400
Heating degree days
51°F
Mean annual temp
Incentive detail: DC sales tax exemption on equipment and electricity (2022 law); JobsOhio grants.
By site type
Top datacenter sites in Meigs County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| MOUNTAINTEER | Substation-Adjacent | 765 kV | 1,000 MW | 3.2 yrs | 71.7 |
| SPORN | Substation-Adjacent | 345 kV | 600 MW | 3.2 yrs | 71.4 |
| UNKNOWN137230 | Substation-Adjacent | 138 kV | 100 MW | 3.2 yrs | 70.6 |
| Greenfield (FLATLICK - GAVIN) | Greenfield | 765 kV | 1,000 MW | 3.2 yrs | 68.1 |
| Greenfield (WATERFORD POWER, LLC - SPORN) | Greenfield | 345 kV | 600 MW | 3.2 yrs | 66.2 |
| Greenfield (JOHN AMOS - MOUNTAINTEER) | Greenfield | 765 kV | 1,000 MW | 3.2 yrs | 66.1 |
| Greenfield (WATERFORD POWER, LLC - SPORN) | Greenfield | 345 kV | 600 MW | 3.2 yrs | 66.1 |
| Greenfield (MUSKINGUM RIVER - SPORN) | Greenfield | 345 kV | 600 MW | 3.2 yrs | 65.1 |
| Greenfield (MUSKINGUM RIVER - SPORN) | Greenfield | 345 kV | 600 MW | 3.2 yrs | 64.3 |
| GAVIN POWER, LLC | Substation-Adjacent | 138 kV | 100 MW | 3.2 yrs | 64.3 |
| UNKNOWN113936 | Substation-Adjacent | 138 kV | 100 MW | 3.2 yrs | 63.9 |
| UNKNOWN137797 | Substation-Adjacent | 138 kV | 100 MW | 3.2 yrs | 63.7 |
| TAP137813 | Substation-Adjacent | 138 kV | 100 MW | 3.2 yrs | 63.5 |
| Greenfield (WATERFORD POWER, LLC - SPORN) | Greenfield | 345 kV | 600 MW | 3.2 yrs | 63.3 |
| UNKNOWN137798 | Substation-Adjacent | 138 kV | 100 MW | 3.2 yrs | 61.9 |
| EC Coal Meigs County | Greenfield | — | — | 3.2 yrs | 61.8 |
| Greenfield (FLATLICK - GAVIN) | Greenfield | 765 kV | 1,000 MW | 3.2 yrs | 61.2 |
| Greenfield (MUSKINGUM RIVER - SPORN) | Greenfield | 345 kV | 600 MW | 3.2 yrs | 61.0 |
| Greenfield (UNKNOWN108805 - UNKNOWN116511) | Greenfield | 138 kV | 100 MW | 3.2 yrs | 59.8 |
| Greenfield (UNKNOWN113936 - TAP162260) | Greenfield | 138 kV | 100 MW | 3.2 yrs | 59.5 |
| EC FFE Meigs County | Greenfield | — | — | 3.2 yrs | 58.1 |
| EC Coal Meigs County | Greenfield | — | — | 3.2 yrs | 58.1 |
| Greenfield (UNKNOWN113936 - TAP162260) | Greenfield | 138 kV | 100 MW | 3.2 yrs | 58.0 |
| UNKNOWN172480 | Substation-Adjacent | 138 kV | 100 MW | 3.2 yrs | 57.9 |
| Greenfield (UNKNOWN108805 - GAVIN) | Greenfield | 138 kV | 100 MW | 3.2 yrs | 57.9 |
Meigs County datacenter FAQ
- How many datacenter sites are in Meigs County?
- 42 scored datacenter candidate sites, averaging 55.4/100 DC Readiness.
- Does Meigs County offer datacenter tax incentives?
- DC sales tax exemption on equipment and electricity (2022 law); JobsOhio grants.
- What is the natural-hazard risk in Meigs County?
- FEMA's National Risk Index rates Meigs County as "Relatively Moderate" (score 30).
- What are industrial electricity rates in Meigs County?
- Average industrial electricity is 11.31¢/kWh and commercial is 14.64¢/kWh in Meigs County.