DC Readiness
55.1
Good / 100

HUGUENOT VOR is a federal excess datacenter candidate site in Orange County, New York, interconnecting through SPP. It screens at 55.1/100 DC Readiness and a 3.3 yrs average interconnection-queue wait.

Power & interconnection

UtilityORANGE & ROCKLAND UTILS INCinvestor ownedrestrictive to large load · terms ≥ 20 MWStandby / large-load service; NYISO Zone J

Speed to power

Interconnection outlookModerate
≈ 3.3 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth1
Avg queue wait3.3 yrs

Connectivity

Nearest IXPPlanet Networks Newton Datacenter
IXP distance25.7 mi
Fiber providers12
Fiber coverage72.9%

Site characteristics

Acreage13 ac
Buildable load (est.)~5–13 MWland-based
Former useNavigation and Traffic Aids

Risk & environment

Environmental constraintNone (0/100)
Water stress (WRI)Low
Wetlands (NWI)—
Critical habitat—
Superfund nearby—
Hazard sub-score65/100

Location context

Nearest datacenterPlanet Networks Newton Datacenter
DC distance25.7 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.68¢/kWh
Industrial electricity7.59¢/kWh
Cooling degree days700
Heating degree days6,100
Land price / acre$10,494

Regulatory climate

Restrictivestate posture · as of 2026-08

First statewide moratorium (2026): 1-yr hold on certain permits for large DCs + impact study.

DC tax incentiveNo / suspended
Large-load threshold≥ 50 MW

Moratorium/permit hold targets large datacenters.

Incentive detail: Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track HUGUENOT VOR

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
58
Fiber connectivity12%
71
Energy cost10%
50
Water risk7%
90
Natural hazard6%
65
Buildability7%
50
Labor market4%
50
DC cluster4%
60
Land / acreage3%
37
Construction cost3%
50
Gas pipeline2%
10
Tax incentive1%
100
Climate / cooling1%
90

Nearby comparable sites

Other scored datacenter candidate sites in Orange County, ranked by DC Readiness.

Sites near HUGUENOT VOR
SiteTypeVoltageCapacityQueue waitScore
ROCK TAVERNSubstation-Adjacent345 kV600 MW4.9 yrs63.3
UNKNOWN158122Substation-Adjacent345 kV600 MW4.9 yrs62.9
Monroe Landfill SolarBrownfield—2 MW4.9 yrs61.5
OZ OrangeGreenfield——3.5 yrs59.8
UNKNOWN129109Substation-Adjacent115 kV100 MW4.9 yrs58.7
UNKNOWN129024Substation-Adjacent115 kV100 MW4.9 yrs58.6
UNKNOWN129107Substation-Adjacent115 kV100 MW4.9 yrs58.3
UNKNOWN129097Substation-Adjacent115 kV100 MW4.9 yrs58.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

Every site and score for HUGUENOT VOR, Orange County is free to browse. Pro adds Watchtower on 25 sites, alerts when new candidate sites, datacenters or interconnection-queue requests appear in your markets, score and capacity history, and CSV export. Enterprise adds team seats, weekly data files for all 147,272 sites, the REST API and an MCP server for AI tools.