Datacenter Sites in Orange County, New York

Orange County has 45 scored datacenter candidate sites averaging 51.6/100 DC Readiness, with a catalogued aggregate of 6,002 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.

45
Candidate sites
51.6/100
Avg DC Readiness
6,002 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating

Site-selection context for Orange County

Yessales_tax_exemption
Datacenter tax incentive
11.68¢/kWh
Commercial electricity
7.59¢/kWh
Industrial electricity
14
Fiber providers
Low
Water stress
$10,494
Land price / acre
700
Cooling degree days
6,100
Heating degree days
46°F
Mean annual temp

Incentive detail: Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.

By site type

Top datacenter sites in Orange County

Top datacenter sites in Orange County
SiteTypeVoltageCapacityQueue waitScore
ROCK TAVERNSubstation-Adjacent345 kV600 MW3.0 yrs74.8
UNKNOWN158122Substation-Adjacent345 kV600 MW3.5 yrs66.8
ROCK TAVERNSubstation-Adjacent345 kV600 MW3.5 yrs65.7
ROCK TAVERN (115KV)Substation-Adjacent115 kV100 MW3.5 yrs63.7
UNKNOWN129097Substation-Adjacent115 kV100 MW3.5 yrs63.6
Greenfield (ROCK TAVERN - COOPERS CORNER)Greenfield345 kV600 MW3.0 yrs63.6
Greenfield (ROCK TAVERN - COOPERS CORNER)Greenfield345 kV600 MW3.0 yrs63.2
UNKNOWN129024Substation-Adjacent115 kV100 MW3.5 yrs62.7
UNKNOWN129111Substation-Adjacent138 kV100 MW3.5 yrs62.2
Greenfield (ROCK TAVERN - COOPERS CORNER)Greenfield345 kV600 MW3.0 yrs62.1
UNKNOWN129109Substation-Adjacent115 kV100 MW3.5 yrs61.3
OZ OrangeGreenfield3.5 yrs59.4
Greenfield (ROCK TAVERN - UNKNOWN158122)Greenfield345 kV600 MW3.5 yrs59.2
Greenfield (ROCK TAVERN - ROSETON)Greenfield345 kV600 MW3.5 yrs58.6
UNKNOWN129098Substation-Adjacent115 kV100 MW3.5 yrs57.8
UNKNOWN129106Substation-Adjacent138 kV100 MW3.5 yrs57.8
Monroe Landfill SolarBrownfield2 MW57.0
SUGARLOAFSubstation-Adjacent138 kV100 MW3.5 yrs57.0
UNKNOWN129110Substation-Adjacent138 kV100 MW3.5 yrs55.4
Greenfield (UNKNOWN132608 - SUGARLOAF)Greenfield115 kV100 MW3.5 yrs54.6
Greenfield (UNKNOWN129096 - HILLBURN)Greenfield138 kV100 MW3.5 yrs54.3
OZ OrangeGreenfield3.5 yrs54.1
OZ OrangeGreenfield3.5 yrs53.8
Greenfield (UNKNOWN132608 - SUGARLOAF)Greenfield115 kV100 MW3.5 yrs53.4
Diamond Candle FactoryIndustrial44.0

Orange County datacenter FAQ

How many datacenter sites are in Orange County?
45 scored datacenter candidate sites, averaging 51.6/100 DC Readiness.
Does Orange County offer datacenter tax incentives?
Excelsior Jobs Program tax credits; IDA property tax abatements (PILOT); Empire State Digital Gaming.
What is the natural-hazard risk in Orange County?
FEMA's National Risk Index rates Orange County as "Relatively High" (score 35).
What are industrial electricity rates in Orange County?
Average industrial electricity is 7.59¢/kWh and commercial is 11.68¢/kWh in Orange County.

Dataset updated . Screening estimates derived from public data sources.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for Orange County, New York. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.