EC Near Mulvane Power Plant

Greenfield

Sumner, Kansas · SPP

DC Readiness
57.8
Good / 100

EC Near Mulvane Power Plant is a greenfield datacenter candidate site in Sumner, Kansas, interconnecting through SPP. It screens at 57.8/100 DC Readiness and a 3.5 yrs average interconnection-queue wait.

Power & interconnection

Nearest grid bottleneckTP1136_32015 · 43 km (SPP)
LMP zoneSPP_NORTH
Wholesale LMP$21.13/MWh
Utility commercial rate0.11¢/kWh
UtilityEVERGY KANSAS CENTRAL, INCinvestor ownedfavorable to large load · terms ≥ 75 MWLarge Load Power Service (LLPS, ≥75 MW) · 80% min take · 12 yr

Speed to power

Interconnection outlookModerate
≈ 3.5 yrs typical interconnection wait

Middle-of-the-pack interconnection conditions for this grid.

ISO / RTO regionSPP
Queue depth64
Avg queue wait3.5 yrs
Recent queue wait3.5 yrs
Completion rate16%
Withdrawal rate84%

Connectivity

Nearest IXPOneNet OSU Tulsa
IXP distance113.6 mi
Fiber providers11
Fiber coverage81.1%
Nearest cloud providerGCP
Nearest cloud regionus-central1
Cloud region distance277.4 mi

Site characteristics

Site typeGreenfield
Land contactSumner County Assessor
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops
Former usenear retired gas plant (10km)

Risk & environment

Environmental constraintLow (25/100)
Flood zoneZone AE (SFHA)
Water stress (WRI)2.40
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score50/100
Construction cost index89.0 (avg 100)

Location context

Nearest datacenterSC DC
DC distance69.9 mi
Nearest rail2.3 mi
Nearest gas pipeline0.7 mi
Nearest fiber route1.2 mi
County hazard (FEMA NRI)Relatively High (35)
DC tax incentiveYes (property_tax_exemption)
Commercial electricity11.42¢/kWh
Industrial electricity9.27¢/kWh
Cooling degree days1,400
Heating degree days5,000
Land price / acre$2,223

Regulatory climate

Moderatestate posture · as of 2026-08

No notable statewide DC restriction on record; confirm local zoning and utility tariffs.

DC tax incentiveNo / suspended

Incentive detail: PEAK program payroll tax incentives; IRB property tax exemptions available.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Get alerts

Track EC Near Mulvane Power Plant

Get an email when its DC-readiness score, available capacity, or interconnection-queue status changes.

No spam. Just the alerts you asked for.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
30
Speed to power20%
60
Fiber connectivity12%
71
Energy cost10%
90
Water risk7%
66
Natural hazard6%
50
Buildability7%
65
Labor market4%
50
DC cluster4%
20
Land / acreage3%
52
Construction cost3%
76
Gas pipeline2%
98
Tax incentive1%
100
Climate / cooling1%
55

Nearby comparable sites

Other scored datacenter candidate sites in Sumner, ranked by DC Readiness.

Sites near EC Near Mulvane Power Plant
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN168687Substation-Adjacent345 kV600 MW3.3 yrs61.9
EC Near Oxford (KS)Greenfield3.5 yrs60.3
EC Near Mulvane Power PlantGreenfield3.5 yrs60.1
EC Near Wellington 1Greenfield3.5 yrs60.1
EC Near Oxford (KS)Greenfield3.5 yrs60.0
EC Near Wellington 1Greenfield3.5 yrs59.5
EC Near Wellington 1Greenfield3.5 yrs59.2
EC Near Wellington 1Greenfield3.5 yrs58.6

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for EC Near Mulvane Power Plant, Sumner. Pro and Enterprise plans unlock the full 147,272-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.