Datacenter Sites in Morton County, Kansas

Morton County has 5 scored datacenter candidate sites averaging 53.6/100 DC Readiness, with a catalogued aggregate of 350 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.

5
Candidate sites
53.6/100
Avg DC Readiness
350 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
◆ Loading map…
≥ 7560–7540–60≤ 40
Top 5 in Morton County

Site-selection context for Morton County

Yesproperty_tax_exemption
Datacenter tax incentive
11.98¢/kWh
Commercial electricity
10.67¢/kWh
Industrial electricity
2
Fiber providers
Medium-High
Water stress
$1,234
Land price / acre
1,400
Cooling degree days
5,000
Heating degree days
55°F
Mean annual temp

Incentive detail: PEAK program payroll tax incentives; IRB property tax exemptions available.

By site type

Top datacenter sites in Morton County

Top datacenter sites in Morton County
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN119535Substation-Adjacent115 kV100 MW3.3 yrs55.2
UNKNOWN119534Substation-Adjacent115 kV100 MW3.3 yrs54.0
UNKNOWN120031Substation-Adjacent69 kV50 MW3.3 yrs53.2
UNKNOWN118702Substation-Adjacent69 kV50 MW3.3 yrs52.9
UNKNOWN203944Substation-Adjacent69 kV50 MW6.9 yrs52.7

Morton County datacenter FAQ

How many datacenter sites are in Morton County?
5 scored datacenter candidate sites, averaging 53.6/100 DC Readiness.
Does Morton County offer datacenter tax incentives?
PEAK program payroll tax incentives; IRB property tax exemptions available.
What is the natural-hazard risk in Morton County?
FEMA's National Risk Index rates Morton County as "Relatively High" (score 35).
What are industrial electricity rates in Morton County?
Average industrial electricity is 10.67¢/kWh and commercial is 11.98¢/kWh in Morton County.