Datacenter Sites in Grant County, Arkansas
Grant County has 32 scored datacenter candidate sites averaging 57.4/100 DC Readiness, with a catalogued aggregate of 11,900 MW. FEMA rates local natural-hazard risk as "Relatively High".
32
Candidate sites
57.4/100
Avg DC Readiness
11,900 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Grant County
No
Datacenter tax incentive
11.95¢/kWh
Commercial electricity
7.81¢/kWh
Industrial electricity
5
Fiber providers
Low
Water stress
$3,912
Land price / acre
1,900
Cooling degree days
3,400
Heating degree days
60°F
Mean annual temp
By site type
Top datacenter sites in Grant County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| WHITE BLUFF | Substation-Adjacent | 500 kV | 1,000 MW | 1.4 yrs | 72.9 |
| SHERIDAN | Substation-Adjacent | 500 kV | 1,000 MW | 1.4 yrs | 67.2 |
| Greenfield (MABELVALE SUBSTATION - SHERIDA) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 65.5 |
| Greenfield (TAP149964 - SHERIDAN) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 64.4 |
| Greenfield (EL DORADO SUBSTATION - SHERIDA) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 64.3 |
| UNKNOWN108078 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 64.1 |
| Greenfield (WHITE BLUFF - SHERIDAN) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 63.7 |
| Greenfield (EL DORADO SUBSTATION - SHERIDA) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 63.2 |
| UNKNOWN121352 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 63.1 |
| UNKNOWN108039 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 62.5 |
| TAP149972 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 61.4 |
| Greenfield (MABELVALE SUBSTATION - SHERIDA) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 61.1 |
| Greenfield (WHITE BLUFF - UNKNOWN156961) | Greenfield | 230 kV | 300 MW | 1.4 yrs | 60.1 |
| Greenfield (TAP149964 - SHERIDAN) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 59.6 |
| UNKNOWN108041 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 58.8 |
| Greenfield (POYEN - UNKNOWN121621) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 57.7 |
| Greenfield (POYEN - TAP149972) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 57.7 |
| Greenfield (WHITE BLUFF - WRIGHTSVILLE) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 57.5 |
| POYEN | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 57.5 |
| UNKNOWN108006 | Substation-Adjacent | 115 kV | 100 MW | 1.4 yrs | 57.3 |
| Greenfield (WHITE BLUFF - SHERIDAN) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 56.9 |
| Greenfield (UNKNOWN108041 - TAP149978) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 55.9 |
| Greenfield (POYEN - TAP149972) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 55.8 |
| Greenfield (UNKNOWN108041 - WOODWARD SUBST) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 54.0 |
| Greenfield (UNKNOWN108041 - WOODWARD SUBST) | Greenfield | 115 kV | 100 MW | 1.4 yrs | 53.4 |
Grant County datacenter FAQ
- How many datacenter sites are in Grant County?
- 32 scored datacenter candidate sites, averaging 57.4/100 DC Readiness.
- Does Grant County offer datacenter tax incentives?
- No datacenter-specific tax incentive is on record for Grant County in our dataset.
- What is the natural-hazard risk in Grant County?
- FEMA's National Risk Index rates Grant County as "Relatively High" (score 38).
- What are industrial electricity rates in Grant County?
- Average industrial electricity is 7.81¢/kWh and commercial is 11.95¢/kWh in Grant County.
Dataset updated . Screening estimates derived from public data sources.