Datacenter Sites in Craighead County, Arkansas
Craighead County has 36 scored datacenter candidate sites averaging 51.4/100 DC Readiness, with a catalogued aggregate of 7,100 MW. FEMA rates local natural-hazard risk as "Relatively High".
36
Candidate sites
51.4/100
Avg DC Readiness
7,100 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Craighead County
No
Datacenter tax incentive
10.54¢/kWh
Commercial electricity
8.76¢/kWh
Industrial electricity
8
Fiber providers
Low
Water stress
$4,451
Land price / acre
1,900
Cooling degree days
3,400
Heating degree days
60°F
Mean annual temp
By site type
Top datacenter sites in Craighead County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| JONESBORO EHV | Substation-Adjacent | 500 kV | 1,000 MW | 1.4 yrs | 66.5 |
| Greenfield (DELL - JONESBORO EHV) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 66.1 |
| Greenfield (DELL - JONESBORO EHV) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 65.0 |
| Greenfield (DELL - JONESBORO EHV) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 65.0 |
| Greenfield (INDEPENDENCE SUBSTATION - JONE) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 64.7 |
| UNKNOWN107982 | Substation-Adjacent | 161 kV | 100 MW | 1.4 yrs | 62.4 |
| HERGETT JCWL | Substation-Adjacent | 161 kV | 100 MW | 1.4 yrs | 61.6 |
| Greenfield (INDEPENDENCE SUBSTATION - JONE) | Greenfield | 500 kV | 1,000 MW | 1.4 yrs | 60.2 |
| TRUMANN | Substation-Adjacent | 161 kV | 100 MW | 1.4 yrs | 58.8 |
| Greenfield (UNKNOWN117316 - JONESBORO SPA) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 58.7 |
| OZ Craighead | Greenfield | — | — | 1.4 yrs | 58.7 |
| UNKNOWN121128 | Substation-Adjacent | 161 kV | 100 MW | 1.4 yrs | 58.6 |
| OZ Craighead | Greenfield | — | — | 1.4 yrs | 58.3 |
| JONESBORO | Substation-Adjacent | 161 kV | 100 MW | 1.4 yrs | 58.1 |
| Greenfield (UNKNOWN121128 - JONESBORO) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 57.5 |
| OZ Craighead | Greenfield | — | — | 1.4 yrs | 56.9 |
| Greenfield (JONESBORO SPA - UNKNOWN121232) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 56.4 |
| Greenfield (JONESBORO SPA - UNKNOWN121232) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 56.1 |
| Greenfield (JONESBORO - JONESBORO EHV) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 52.7 |
| Greenfield (UNKNOWN107787 - JONESBORO SPA) | Greenfield | 161 kV | 100 MW | 1.4 yrs | 50.7 |
| JONESBORO, AR | Federal Excess | — | — | — | 42.7 |
| Former Wolverine Shoe Factory | Industrial | — | — | — | 42.6 |
| Mine Site | Former Mine | — | — | — | 42.5 |
| Old Citizens Bank Building | Industrial | — | — | — | 42.5 |
| TRG Jonesboro, LLC | Industrial | — | — | — | 42.5 |
Craighead County datacenter FAQ
- How many datacenter sites are in Craighead County?
- 36 scored datacenter candidate sites, averaging 51.4/100 DC Readiness.
- Does Craighead County offer datacenter tax incentives?
- No datacenter-specific tax incentive is on record for Craighead County in our dataset.
- What is the natural-hazard risk in Craighead County?
- FEMA's National Risk Index rates Craighead County as "Relatively High" (score 38).
- What are industrial electricity rates in Craighead County?
- Average industrial electricity is 8.76¢/kWh and commercial is 10.54¢/kWh in Craighead County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Craighead County, Arkansas. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.