Datacenter Sites in Uinta County, Wyoming
Uinta County has 57 scored datacenter candidate sites averaging 54.8/100 DC Readiness, with a catalogued aggregate of 8,300 MW. FEMA rates local natural-hazard risk as "Very Low". The county has a datacenter tax incentive on record.
57
Candidate sites
54.8/100
Avg DC Readiness
8,300 MW
Catalogued capacity
theoretical aggregate
Very Low
Hazard rating
Site-selection context for Uinta County
Yesno_income_tax
Datacenter tax incentive
10.53¢/kWh
Commercial electricity
7.72¢/kWh
Industrial electricity
2
Fiber providers
Medium-High
Water stress
$1,330
Land price / acre
300
Cooling degree days
7,600
Heating degree days
41°F
Mean annual temp
Incentive detail: No state corporate or personal income tax; low property taxes.
By site type
Top datacenter sites in Uinta County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| NAUGHTON | Substation-Adjacent | 230 kV | 300 MW | 1.7 yrs | 67.8 |
| UNKNOWN202399 | Substation-Adjacent | 230 kV | 300 MW | 1.7 yrs | 67.2 |
| SOUTH TRONA | Substation-Adjacent | 230 kV | 300 MW | 1.7 yrs | 66.0 |
| MONUMENT | Substation-Adjacent | 230 kV | 300 MW | 1.7 yrs | 65.1 |
| UNKNOWN202532 | Substation-Adjacent | 138 kV | 100 MW | 1.7 yrs | 64.1 |
| UNKNOWN202536 | Substation-Adjacent | 115 kV | 100 MW | 1.7 yrs | 62.9 |
| UNKNOWN204608 | Substation-Adjacent | 138 kV | 100 MW | 1.7 yrs | 62.7 |
| UNKNOWN204371 | Substation-Adjacent | 115 kV | 100 MW | 1.7 yrs | 62.4 |
| TAP204372 | Substation-Adjacent | 138 kV | 100 MW | 1.7 yrs | 62.1 |
| UNKNOWN205659 | Substation-Adjacent | 115 kV | 100 MW | 1.7 yrs | 61.5 |
| UNKNOWN204607 | Substation-Adjacent | 138 kV | 100 MW | 1.7 yrs | 61.4 |
| UNKNOWN204365 | Substation-Adjacent | 115 kV | 100 MW | 1.7 yrs | 61.3 |
| Greenfield (POPULUS - JIM BRIDGER) | Greenfield | 345 kV | 600 MW | 1.7 yrs | 60.9 |
| MOUNTAIN WIND POWER II LLC | Substation-Adjacent | 138 kV | 100 MW | 1.7 yrs | 60.9 |
| Greenfield (MONUMENT - UNKNOWN201362) | Greenfield | 230 kV | 300 MW | 1.7 yrs | 60.8 |
| Greenfield (POPULUS - JIM BRIDGER) | Greenfield | 345 kV | 600 MW | 1.7 yrs | 60.7 |
| WYOMING WIND ENERGY CENTER | Substation-Adjacent | 138 kV | 100 MW | 1.7 yrs | 60.7 |
| Greenfield (SOUTH TRONA - MONUMENT) | Greenfield | 230 kV | 300 MW | 1.7 yrs | 60.6 |
| Greenfield (MONUMENT - UNKNOWN201362) | Greenfield | 230 kV | 300 MW | 1.7 yrs | 60.4 |
| RAILROAD | Substation-Adjacent | 138 kV | 100 MW | 1.7 yrs | 60.4 |
| UNKNOWN204369 | Substation-Adjacent | 115 kV | 100 MW | 1.7 yrs | 60.1 |
| UNKNOWN202152 | Substation-Adjacent | 115 kV | 100 MW | 1.7 yrs | 60.0 |
| Greenfield (MONUMENT - UNKNOWN201362) | Greenfield | 230 kV | 300 MW | 1.7 yrs | 60.0 |
| Greenfield (MONUMENT - UNKNOWN201362) | Greenfield | 230 kV | 300 MW | 1.7 yrs | 59.8 |
| Greenfield (UNKNOWN201362 - BIRCH CREEK) | Greenfield | 230 kV | 300 MW | 1.7 yrs | 59.7 |
Uinta County datacenter FAQ
- How many datacenter sites are in Uinta County?
- 57 scored datacenter candidate sites, averaging 54.8/100 DC Readiness.
- Does Uinta County offer datacenter tax incentives?
- No state corporate or personal income tax; low property taxes.
- What is the natural-hazard risk in Uinta County?
- FEMA's National Risk Index rates Uinta County as "Very Low" (score 10).
- What are industrial electricity rates in Uinta County?
- Average industrial electricity is 7.72¢/kWh and commercial is 10.53¢/kWh in Uinta County.
Dataset updated . Screening estimates derived from public data sources.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for Uinta County, Wyoming. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.