Waller County has 31 scored datacenter candidate sites averaging 62.0/100 DC Readiness, with a catalogued aggregate of 8,500 MW. FEMA rates local natural-hazard risk as "Very High". The county has a datacenter tax incentive on record.
31
Candidate sites
62.0/100
Avg DC Readiness
8,500 MW
Catalogued capacity
theoretical aggregate
Very High
Hazard rating
Site-selection context for Waller County
Yessales_tax_exemption
Datacenter tax incentive
11.17¢/kWh
Commercial electricity
7.41¢/kWh
Industrial electricity
10
Fiber providers
Medium-High
Water stress
$5,777
Land price / acre
2,600
Cooling degree days
1,800
Heating degree days
65°F
Mean annual temp
Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.
By site type
Top datacenter sites in Waller County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| ZENITH | Substation-Adjacent | 345 kV | 600 MW | 3.4 yrs | 70.9 |
| UNKNOWN308809 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 66.2 |
| UNKNOWN300814 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 66.0 |
| Greenfield (ZENITH - SINGLETON) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 65.5 |
| Greenfield (SINGLETON - ZENITH) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 65.5 |
| KATY | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 65.4 |
| TAP310802 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 65.3 |
| Greenfield (ZENITH - SINGLETON) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 65.2 |
| UNKNOWN310141 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 65.2 |
| UNKNOWN310483 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 65.0 |
| UNKNOWN307542 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 64.9 |
| UNKNOWN300397 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 64.6 |
| TAP310790 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 63.9 |
| Greenfield (SINGLETON - ZENITH) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 63.4 |
| UNKNOWN306457 | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 62.5 |
| FREEMAN | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 61.9 |
| Greenfield (SINGLETON - ZENITH) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 61.7 |
| Greenfield (ZENITH - SINGLETON) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 61.7 |
| Greenfield (UNKNOWN304285 - ZENITH) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 61.4 |
| Greenfield (O'BRIEN - ZENITH) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 61.0 |
| Greenfield (KATY - FRANZ) | Greenfield | 138 kV | 100 MW | 3.4 yrs | 60.7 |
| Greenfield (SINGLETON - ZENITH) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 60.5 |
| Greenfield (ZENITH - SINGLETON) | Greenfield | 345 kV | 600 MW | 3.4 yrs | 59.3 |
| RACOON BEND | Substation-Adjacent | 138 kV | 100 MW | 3.4 yrs | 58.4 |
| EC FFE Waller County | Greenfield | — | — | 3.4 yrs | 58.1 |
Waller County datacenter FAQ
- How many datacenter sites are in Waller County?
- 31 scored datacenter candidate sites, averaging 62.0/100 DC Readiness.
- Does Waller County offer datacenter tax incentives?
- Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.
- What is the natural-hazard risk in Waller County?
- FEMA's National Risk Index rates Waller County as "Very High" (score 55).
- What are industrial electricity rates in Waller County?
- Average industrial electricity is 7.41¢/kWh and commercial is 11.17¢/kWh in Waller County.